Discharge Flashcards
Discharging a contract
Releases parties from their contractual obligations and can occur through
- Acceptance
- Performance
- Breach (Repudiatory Breach, Breach of fundamental terms, Anticipatory Repudiatory breach)
- Frustration
Hannah Blumenthal
Contract can be terminated by agreement for valid consideration
Mutual release exception
The exception to this rule is the ‘mutual release exception’ where the contract is discharged with mutual abandonment of the contractual obligations under a separate contract, amounting to valid
consideration. The requirements are that
(i) the discharge is mutual; and (ii) the consent is free.
Performance
Both express and implied obligations need to be performed. The performance is
either:
(i) of the strict contractual obligations; or
(ii) of the qualified contractual obligations. ‘Qualified’ means they will not result in a specific outcome, but the obligation will be performed to a certain standard.
Cutter v Powell
Complete performance is required. Plaintiff was executor of an estate of a man to whom the defendant had promised 30 guineas to be paid after the man had performed all his duties in return
for services rendered on his ship. The man failed to abide by his contractual obligations for the entire journey and the p sought money from d on a quantum meruit (QM) basis for the services discharged
up to that point. Held: contract for services was to be performed for the duration of the voyage and this condition was no met.
Quantum Meruit
QM means ‘what he has earned/entitled to’. A claim for QM cannot arise if the parties have a contract to pay an agreed sum.
Where can a claim of quantum meruit not arise?
A claim for QM cannot arise
if the parties have a contract to pay an agreed sum. In such circumstances, the parties’ relationship is governed by the law of contract. However, a claim for QM may arise where the parties:
(i) have not agreed a contract, or there is a so-called quasi-contract e.g. have failed to reach an agreement on an essential term, such as price;
(ii) have not fixed a price for the services or goods supplied;
(iii) have an agreement to pay a reasonable sum for the services or goods supplied; or (iv) have agreed a scope of
work under the original contract and the work carried out falls outside that scope.
Bolton v Mahadeva
Equity intervenes
in certain circumstances and will accept substantial performance with minor deviations.
Planche v Colburn
Plaintiff is entitled to payment on a QM basis where defendant attempts to prevent the completion of performance
Startup v MacDonald
If a party tender’s performance which is subsequently rejected, they
are entitled to terminate the contract
Coughlan v Moroney
Plaintiff agreed to build a house for the defendant before a deadline for a lump sum. House was no completed by the deadline and defendant took possession of the unfinished building and refused plaintiff access and refused to pay plaintiff the balance. Plaintiff could not recover on a QM basis because d had received the benefits of part performance unless the existence of a contract to pay for the work done could be inferred from the circumstances which in
this case there wasn’t. This case was argued on the basis that d could recover from the original contract not on the ground that a new contract existed and no such contract existed.
Sumpter v Hedges
If voluntarily acceded to some level of part / incomplete performance that can be binding. where the contract is to do something for a lump sum, the price cannot be recovered until the work is done. In the absence of a fresh contract, p cannot recover from p on a QM basis.
Taylor v Laird
Payment for part
performance can also be due if contract is a divisible contract
Startup v MacDonald
or if an attempt has
been made to perform
Breach
Where there is a failure or refusal by one or both parties to perform one or all of the
obligations imposed by a contract, breach occurs. Breach and termination are related as early termination can occur for breach as well as other circumstances as specified in the contract.
A. Termination for breach
Express term of the contract. National Power plc v United Gas: for a breach to be ‘material’ it does not have to be ‘repudiatory’. Where a breach is capable of being remedied, the defaulting party is to be given a specified time period in which to remedy the breach before the right to terminate arises.
B. Termination for convenience
Right to terminate on giving notice without having a reason to justify the termination such as default. There will normally be a defined notice period and the method by which the notice is to be communicated.
Other types of breach
c. Termination for insolvency.
d. Termination for change of control.
e. Termination for force majeure.
Repudiatory breach
Outside of the contract, there can be common law termination i.e. a repudiatory
breach which goes to the root of the contract. Repudiatory breach is a breach of contract that gives the aggrieved party the right to choose either to end the contract (terminate) or affirm it, either way
they may also claim for damages.
Breach of condition may be repudiatory
A breach of condition would be repudiatory as it goes to the heart
or the root of the contract, as is the breach of an intermediate term that deprives the other party substantially the whole benefit of the contract. A contract may also be repudiated before the time for performance has arrived.
How to determine if a breach is repudiatory
For repudiatory breach look at
(i) the type of the term which has been
breached;
(ii) what obligations are ‘entire’; and (iii) has the party who breached the contract indicated an intention to abandon its contractual obligations. Conduct must be clear and unequivocal. Time of
performance is not essential unless the contract considers it so.
Fundamental terms
Usually, only breach of a condition, or a fundamental term constitutes a breach
of contract whereas breach of warranties or non-fundamental terms do not give right of action. The breach must be sufficiently serious so as to allow the right of election i.e. to choose to end the contract
and sue: the Simona.
Allows right of election under the Simona
These are: (a) breach of condition: Re Moore, (b) repudiatory breach: serious
and deliberate and must go to root of contract: Decro Wall
Decro Wall
where deliberate late payments are not
sufficiently serious for a deliberate breach