Domain 4: Site Visits and Observations Flashcards
(105 cards)
A. Participate in project meetings as required in the contract documents.
B. Participate in pre-construction conference.
C. Make periodic visits to the site during construction and observe the quality and progress of the
work.
D. Identify on-site design issues and engage project team to formulate solutions.
E. Document field conditions and determine if conditions differ from the provided reference
documents.
https://www.cram.com/flashcards/ccca-5-site-visits-6991371
Under a standard Owner-A/E agreement the A/E is responsible to:
- Resolve disputes
- Review submittals
- Represent the owner
- Perform inspections of the work
What party has the ability to commit the owner’s funds?
the owner
True or False:
The delivery method selected for the project does not affect the construction contract administration and contractor project management processes.
False
Communications to sub-contractors from the A/E, the owner and their consultants should pass through the:
contractor
Progress meetings involving the A/E and the contractor typically occur prior to:
Submission of an application for payment.
Match the responsible project participant with the following responsibilities:
Has the right to reject defective work? A/E.
Schedules and facilitates testing. Contractor
Has the right to stop the work for good cause. Owner.
Interprets the contract documents. A/E.
- A/E
- Contractor
- Owner
- A/E
True or False:
The Contractor conducts inspections to determine the date of substantial completions and to verify final completion.
False
The A/E does this.
Periodic site visits by the A/E appropriate to the stage of construction helps to ensure:
- conformance with the contract documents.
- coordination with the design and construction.
- accurate interpretation of the contract documents.
- timely communication between A/E and the contractor
The date established by the A/E when the project, or portion of the project, is so nearly complete that the owner can use the project for its intended purpose is:
substantial completion
True or False:
Final inspection provided verification by the A/E that the contractor has satisfied the completion of tasks and corrections listed on the final punch list.
True
True or False:
Mechanic’s liens generally do not apply to public projects.
True
Before the owner occupies the project under the terms established by substantial completion, the A/E verifies that the contractor has submitted to the owner:
A. The Construction progress schedule.
B. The punch list.
C. The keying schedule
D. All of the above.
C. The keying schedule
True or False:
The party responsible for payment of the testing agency may vary from project to project.
True
owner or contractor.
Construction activities can be divided into to broad categories. What are they?
construction contract administration (CCA) and contractor project management (CPM)
True or False:
The standard agreements between owner and contractor require the contractor to visit the site prior to bidding or commencing work.
True
True or False:
The term “reasonably inferred” allows the architect or owner to require items that may or may not be adequately described.
False
A first pre-construction meeting may cover administrative procedures, such as communication and testing. A second meeting may address ___.
use of site (mobilization)
Another term of procedural meeting may be _____.
pre-construction meeting
The purpose of the procedural meeting includes to clarify individuals who have contractual authority to sign change orders and make ____.
binding decisions.
Examples of procedures for measurement and payment include the schedule of values and applications for payment.
applications for payment.
Examples of contract modifications include:
- minor changes
- change directives
- proposal requests
- change orders
What should the focus be on in a pre-construction meeting?
CPM/CCA and/or site mobilization (contractor, subs, use of site)