Earned Value Flashcards
(16 cards)
Planned value (PV)
Planned value (PV)
What the project should be worth.
Earned value (EV)
Earned value (EV)
What the project is worth
Percent complete X BAC
Actual cost (AC)
Actual cost (AC)
What the project has spent so far
Budget at Completion (BAC)
Budget at Completion (BAC)
What the project budget is
Cost variance (CV)
Cost variance (CV)
The difference between earned value and the actual costs
EV-AC
Positive – under budget
Negative – over budget
Schedule variance (SV)
Schedule variance (SV)
The difference between earned value and planned value
EV-PV
Positive – ahead of schedule
Negative – behind schedule
Variance at Completion (VAC)
Variance at Completion (VAC)
Projection of being over or under budget based on current performance
BAC-EAC
Positive – under budget
Negative – over budget
Cost Performance Index (CPI)
Cost Performance Index (CPI)
Shows overall cost efficiency on the project.
EV/AC
Greater than 1 – under budget
Less than 1 – over budget
Schedule Performance Index (SPI)
Schedule Performance Index (SPI)
Shows overall schedule adherence
EV/PV
Greater than 1 – ahead of schedule
Less than 1 – behind schedule
Estimate at Completion (EAC)
Standard formula
Estimate at Completion (EAC) Standard formula
Forecasts final project costs based on current performance
BAC/CPI
Estimate at Completion (EAC) Future work at planned costs formula
Estimate at Completion (EAC) Future work at planned costs formula
Forecasts final project costs based on
current performance
AC + BAC – EV
Estimate at Completion (EAC) Initial costs estimates flawed
Estimate at Completion (EAC) Initial costs estimates flawed
Forecasts final project costs based on current performance
AC + Estimate for remainder of project
Estimate at Completion (EAC) CPI and SPI affect remainder of project
Estimate at Completion (EAC) CPI and SPI affect remainder of project
Forecasts final project costs based on current performance
AC + [BAC-EV/(CPI x SPI)]
Estimate to Complete
Estimate to Complete
Predict how much more the remainder of the project will costs
EAC-AC
TCPI Utilizing BAC
TCPI Utilizing BAC
Predicts likelihood of reaching BAC
(BAC-EV)/(BACAC)
Greater than 1 – harder to
complete and meet BAC
Less than 1 – easier to complete
and meet BAC
TCPI Utilizing EAC
TCPI Utilizing EAC
Predicts likelihood of reaching EAC
(BAC-EV)/(EACAC)
Greater than 1 – harder to
complete and meet EAC
Less than 1 – easier to complete
and meet EAC