Earned Value Formulas Flashcards

1
Q

PV

A

Planned Value

The authorized budget assigned to scheduled work.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

EV

A

Earned Value
Measure of work performed expressed in terms of the budget authorized for that work.

EV=sum of the planned value of completed work.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

AC

A

Actual Cost

The realized cost incurred for work performed on an activity during a specific time period.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

BAC

A

Budget at Completion

The sum of all budgets established for the work to be performed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

CV

A
Cost Variance
The amount of budget deficit or surplus at a given point in time, expressed as the difference between earned value and the actual cost.
CV=EV-AC
Positive = Under planned cost
Neutral = On planned cost
Negative = Over planned cost
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

SV

A
Schedule Variance
Amount by which the project is ahead or behind the planned delivery date.
SV=EV-PV
Positive = Ahead of schedule
Neutral=On schedule
Negative=Behind schedule
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

VAC

A
A PROJECTION of the amount of budget deficit or surplus.
VAC=BAC-EAC
Positive = Under planned cost
Neutral = On planned cost
Negative = Over planned cost
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

CPI

A
Cost Performance Index
A measure of the cost efficiency of budgeted resources expressed as the ratio of earned value to actual cost.
CPI=EV/AC
>1.0 = Under planned cost
=1.0 = On planned cost
<1.0 = Over planned cost
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

SPI

A

Schedule Performance Index
A measure of schedule efficiency expressed as the ratio of earned value to planned value.

SPI = EV/PV
>1.0 = Ahead of schedule
Exactly 1.0=On schedule
<1.0 =Behind schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

CPI Interpretation

A
>1.0 = Under planned cost
=1.0 = On planned cost
<1.0 = Over planned cost
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

SPI Interpretation

A

> 1.0 = Ahead of schedule
Exactly 1.0=On schedule
<1.0 =Behind schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

CV Interpretation

A
Positive = Under planned cost
Neutral = On planned cost
Negative = Over planned cost
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

VAC Interpretation

A
Positive = Under planned cost
Neutral = On planned cost
Negative = Over planned cost
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

SV Interpretation

A

Positive = Ahead of schedule
Neutral=On schedule
Negative=Behind schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

EAC Definition

A

Estimate at Completion

The expected total cost of completing all work expressed as the sum of the actual cost to date and estimate to complete.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

EAC if the CPI is expected to be the same for the remainder of the project.

A

EAC=BAC/CPI

17
Q

EAC if future work will be accomplished at the planned rate

A

EAC=AC+BAC-EV

18
Q

EAC if the initial plan is no longer valid

A

EAC=AC+Bottom-up estimating

19
Q

EAC if both the CPI and SPI influence the remaining work.

A

EAC=AC+((BCA-EV)/(CPI*SPI))

20
Q

ETC

A

Estimate to complete
The expected cost to finish all remaining work.
Assuming work is proceeding on plan, the cost of completing the reamaining work - ETC=EAC-AC

ETC=Reestimate

21
Q

TCPI Definition

A

To Complete Performance Index
A measure of the cost performance that must be achieved with the remaining resources in order to meet a specified goal, expressed as the ratio of the cost to finish the outstanding work to the budget available.

22
Q

TCPI - Efficiency required to complete on PLAN

A

TCPI = (BAC-EV)/(BAC-AC)

23
Q

TCPI - Efficiency required to complete the current EAC

A

TCPI=(BAC-EV)/(EAC-AC)

24
Q

TCPI Interpretation

A

> 1.0 Harder to complete
=1.0 Same to complete
<1.0 Easier to complete