Earned Value Management Formulas & Meanings Flashcards

(8 cards)

1
Q

CV =

A

Cost Variance | Formula: EV - AC | Negative is bad, positive is good

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

SV =

A

Schedule Variance | Forumla: EV - PV | Negative is bad, positive is good

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

CPI =

A

Cost Performance Index | Formula: EV/AC | Under 1 is bad, Over 1 is good

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

SPI =

A

Schedule Performance Index | Formula: AC + (BAC - EV) | AC plus work remaining. use budget rate (atypical)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

EAC =

A

Estimate at Completion | Formula: AC + (BAC - EV) or BAC/CPI or AC + [BAC - EV]/[CPI *SPI] | Assumes poor cost performance & schedule performance will continue

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

ETC =

A

Estimate to Completeion | Formula: EAC - AC | Value of work remaining

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

VAC =

A

Variance at Completion | BAC - EAC | Negative is bad, Positive is good

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

TCPI =

A

To Complete Performance Index | Formula: (BAC - EV) /(BAC - AC) | Optimal rate to complete within budget or (BAC - EV)/(EAC - AC) | Assumes original budget cannot be achieved.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly