Earned Value Management Meanings Flashcards

(15 cards)

1
Q

CV

A

Cost Variance (Negative is bad, Positive is good)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

SV

A

Schedule Variance (Negative is bad, Positive is good)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

CPI

A

Cost Performance Index (Under 1 is bad, Over 1 is good)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

SPI

A

Schedule Performance Index (Under 1 is bad, Over 1 is good)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

EAC

A

Estimate at Completion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

ETC

A

Estimate to Completion (Value of work remaining)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

VAC

A

Variance at Completion (Negative is bad, Positive is good)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

TCPI

A

To Complete Performance Index

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

PV

A

Planned Value (Budgeted value of work planned to be done)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

EV

A

Earned Value (Budgeted value of work completed)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

AC

A

Actual Costs (Actual total costs of work completed)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

BAC

A

Budget at Completion (Cost Baseline)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

EAC

A

Expected at Completion (Expected total costs - Forecast)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

ETC

A

Estimate to Complete (Expected remaining cost; now until end)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

VAC

A

Variance at Completion (Expected variance over/under budget)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly