Earned Value Management - Monitoring Cost & Schedule Flashcards
(12 cards)
BAC
Budget at Completion: Original budget of the project
No formula
PV
Planned Value: amount of work that SHOULD be done at this point
PV = Planned % Complete x BAC
Ex: (⅗ days in) x $100 = $60
EV
Earned Value (EV): Amount of money worth of work you actually did on the project (not necessarily the money spent though)
EV = Actual % Complete x BAC
Ex: (actually 75% complete) x $100 = $75
AC
Actual Cost (AC): Amount of money you already spent on the project
No formula
CV
Cost Variance (CV): Work done vs actual money spent
CV = EV - AC
Positive = under budget
CPI
Cost performance index: spend rate %
CV = EV / AC
SV
Schedule Variance: How much work we should have done vs. how much work you actually did
Positive = ahead of schedule
SV = EV - PV
Ex: $75 - $60 = $15 worth of work you’re ahead of sched by
SPI
Schedule Performance Index: The rate (%) of how we are meeting the project schedule.
SPI = EV / PV
EAC
Estimate at Completion: Forecasting the total cost of the project at the end based on the current spending rate of the project.
EAC = BAC / CPI
ETC
Estimate to Completion: How much more $ will be needed to complete the current project
ETC = EAC - AC
VAC
Variance at Completion: The difference between the original budget and new forecasted budget.
Postive = under budget!
VAC = BAC - EAC
TCPI
To-Complete Performance Index: How hard you have to work to finish the project within the budget. Over 1 = work harder
TCPI = (BAC – EV) / (BAC – AC)