Earned Value Management Vocab Flashcards

(20 cards)

1
Q

Planned Value - define

A

budgeted value of work planned to be done at a given time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Earned Value - define

A

budgeted value of work completed at a given time

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Actual Cost - define

A

actual cost of work completed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Budget at completion - define

A

the original cost baseline plus or minus all approved cost changes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Estimate at completion - define

A

expected total project cost (forecasted based on performance to date)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

estimate to completion - define

A

expected remaining cost (now until project completion)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Variance at completion - define

A

expected variance over/under budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Cost variance - formula

A

EV - AC

Negative is bad, Positive is good. Zero is on budget.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Schedule Variance - formula

A

EV - PV

Negative is bad, Positive is good, Zero is on schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Cost Performance Index - formula

A

EV/AC

Under 1 is bad, Over 1 is good, Exactly 1 is on budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Schedule Performance Index - formula

A

EV/PV

Under 1 is bad, Over 1 is good, Exactly 1 is on schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Estimate at Completion - formula

A

AC + (BAC-EV)
AC plus work remaining, use budget rate (variances atypical)

(BAC/CPI)
Assumes same rate of spending will continue (variances typical)

AC + [(BAC-EV)/(CPI*SPI)]
Assumes current cost and schedule performance will continue

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Estimate to Completion - formula

A

EAC - AC

Expected cost of work remaining

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Variance at Completion - formula

A

BAC - EAC

Negative is bad, Positive is good, Zero is on budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

To Complete Performance Index - formula

A

(BAC - EV) / (BAC - AC)
CPI needed to complete project within budget

(BAC - EV) / (EAC - AC)
CPI needed to hit EAC - Assumes original budget unachievable

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Forward Pass

A

EF is determined by adding the duration to the ES and subtracting 1
ES of Successor tasks is equal to the latest EF of the Predecessor tasks plus 1

17
Q

Backward Pass

A

LS is determined by subtracting the duration from the LF and adding 1
LF of Predecessor tasks is equal to the earliest LS of the Successor tasks minus 1

18
Q

Float - define & formula

A

The float (aka slack) is determined by LF - EF

19
Q

Critical Path

A

The critical path is the longest duration path through the network diagram. Any delays along the critical path will delay the project.

The tasks that have float can be delayed by the amount of the float and not delay the project.

20
Q

Time-Phased Budget

A

Determining the budget over time based on the resources needed to complete the work on schedule