EVM_flashcards_concepts_only

(14 cards)

1
Q

What is Planned Value (PV)?

A

The budgeted value of work scheduled to be completed by a certain point in time.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is Earned Value (EV)?

A

The budgeted value of work that has actually been completed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is Actual Cost (AC)?

A

The actual amount of money spent on the work completed.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is Cost Variance (CV)?

A

A measure of cost performance.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What does a negative Cost Variance (CV) mean?

A

The project is over budget.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is Schedule Variance (SV)?

A

A measure of schedule performance.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What does a negative Schedule Variance (SV) mean?

A

The project is behind schedule.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is the Cost Performance Index (CPI)?

A

A ratio that indicates cost efficiency.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What does a CPI less than 1 indicate?

A

Costs are higher than planned (over budget).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is the Schedule Performance Index (SPI)?

A

A ratio that indicates schedule efficiency.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What does an SPI less than 1 indicate?

A

Work is progressing slower than planned (behind schedule).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is Estimate at Completion (EAC)?

A

The expected total cost of the project at completion.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is Estimated Time to Complete (ETTC)?

A

The expected duration to complete the project at the current rate.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is BAC?

A

Budget at Completion: the total planned budget for the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly