Exam 1 Flashcards
(76 cards)
Estimating is not an exact science Good estimating requires:
- Knowledge of construction
- Common sense
- Judgement
What are the types of estimates?
Rough order of Magnitude (ROM) Estimates, Square foot and Cubic foot estimates, Assemblies
(Systems) Estimates, and Unit Price Estimate
- Educated guess
2. Accuracy is -30% to +50%
Rough Order of Magnitude (ROM) Estimates
- Used when proposed size and use of building are known
2. Accuracy is -20% to +30%
Square Foot and Cubic Foot Estimates
- Budgetary tool in planning stages
2. Accuracy is -10% to +20%
Assemblies (Systems) Estimates
- Based on working plans and full specifications
2. Accuracy is -5% to +10%
Unit Price Estimate
Uniformat has how many levels?
Uniformat has three levels
Unitformat level 1 categories.
- Substructure
- Shell
- Interiors
- Services
- Equipment and Furnishings
- Special Construction
- Building Sitework
CSI MasterFormat ( __ cost divisions)
50
is a standard for organizing specifications and other
written information for commercial and institutional building projects in the U.S. and Canada.
MasterFormat
MasterFormat is a product of the ______________.
Construction Specifications Institute (CSI) and Construction Specifications Canada (CSC)
- The most insignificant piece of information will become the item that is most important if you don’t document it.
- The item you don’t document will be the one
that someone wants to see.
Murphy’s Law in documentation
change during bidding process
1. After specifications issued but before bids submitted.
2. Issued by owner or designer.
3. Bidders must acknowledge receipt of all addenda.
4. Bidders must include cost of all addenda in
bid.
Addendum
- change after contract is signed.
- Additions/modifications to work; adverse weather conditions.
- Add or delete work; increase or decrease cost or time.
- May not make any adjustment to cost or time.
Change Order
Overhead
costs that are not materials, labor or equipment
- chargeable to a specific project
- Superintendent/staff
- salaries; temporary utilities; testing;
permits
Job Overhead
- not chargeable to a specific project
Costs incurred at main office of company; executive/staff
salaries, office rent; office equipment; office utilities; insurance; shops and yards
General Overhead
What are the types of bonds?
Bid Bond, Performance Bond, Payment Bond
Assures contractor will sign contract with owner.
Bid Bond
Assures contractor will perform work.
Performance Bond
Assures contractor will pay subs and
suppliers.
Payment Bond
Public liability and Property Damage insurance
covers actions of contractor’s employees during construction of project.
Basic Builders Risk insurance
provides coverage of the project during construction.
Bidding Requirements:
- Bid Solicitation
- Instructions to Bidders
- Information Available to Bidders
- Bid Forms and Supplements
- Bidding Addenda