Exam 2 Flashcards
Exam 2 questions (174 cards)
(3.6.1) What is the PMB?
Time-phased plan for accomplishing each piece of authorized work.
(3.6.1) What are the steps in developing the PMB?
- Define the scope of work
- Schedule the work
- Budget the work
3a. Time-phase the budget
(3.6.1) What are 3 reasons for PMB changes?
- Formal contract change
- Internal re-planning
- Formal reprogramming (OTB)
(3.6.1) When is EVM required in DoD?
- cost/incentive contracts >$20M, compliant system
- cost/incentive contracts >$100M, DCMA validation required
- optional for below ^ thresholds
(3.6.1) What is EVM?
A program management tool for integrating cost, sched, and technical parameters of a contract. Helps provide PM with progress information needed for decision-making and risk management.
(3.6.1) EVM is a recognized function of ______ _________ which applies throughout the _________ process.
EVM is a recognized function of PROGRAM MANAGEMENT which applies throughout the ACQUISITION process.
(3.6.1) What is a reason for a PMB change and a disadvantage of a PMB change?
Reason for: to keep a PMB as a useful management tool.
Disadvantage: PMB changes do not retain historical performance data and may signal added risk.
(3.6.1) With respect to PMB, what should management reserve be tied to?
Risk areas
(3.6.1) What is an IBR?
Joint assessment conducted by PM and contractor to verify realism and accuracy of PMB; ensuring it captures technical scope, schedule requirements, and is adequately resourced.
Done within 6 months of contract award.
(3.5.3) What is the purpose of Configuration Management?
- Avoid Cost
- Reduce Risk
- Control Design Changes
(3.5.3) What are the four functions of Configuration Management (CM)?
- Identification: ID functional and physical characteristics
- Status Accounting: Recording and reporting all changes
- Control: How information is archived, accessed, and documented throughout the life cycle
- Verification and Audits: QA checks that the right product was built
(3.5.3) Designating items as Configuration Items (CI) requires more _____ and ______
Oversight and Control
(3.5.3) What are the 3 types of configuration baselines?
- Functional
- Allocated
- Product
(3.5.3) What are the 3 types of changes during the CM process?
- Engineering Change Proposal
- Deviation
- Waiver
(3.5.3) The current approved configuration is the ____ and ____
Approved Baseline and Approved Changes
(3.5.3) What are the roles and responsibilities for the Interface Control Working Group (ICWG)?
- Identifying, documenting, and controlling all functional and physical characteristics of the interface.
- To produce interface control documents.
(3.5.3) Changes to requirements, design, and production processes can have impacts across multiple levels of the system and have major negative implications to ______ and ______
Cost and Schedule
(3.5.3) What are the steps to an effective design review
- Plan
- Familiarize
- Individual Review
- Team Review
- Resolve
- Follow up
(3.5.3) What are the impacts to configuration management when commercial items are used?
- Government does not control design details
- Detailed technical data package may not be available
- Requires careful definition of interfaces
- Support strategies must address repairs and updates in commercial environment
- Test strategies ensure performance not only at item level, but in integrated units
(3.5.1) What is verification?
“Did we build it right?”
Verification Provides evidence that the system or system element performs its intended functions and meets all performance requirements listed in the system performance specification and functional and allocated baselines; involves
developmental testing of the system.
(3.5.1) What is validation?
“Did we build the right thing?”
Validation Provides objective evidence that the capability provided by the system complies with stakeholder performance requirements in its intended environment; consists of evaluating operational effectiveness, operational suitability, sustainability and survivability.
(3.5.1) What are the key provisions of Department of Defense policy that relate to systems
engineering requirements in the DoD?
DoD 5000 mandates SE and an SE Plan (Plan approved by MDA) for all programs
(3.5.1) What characteristics are included in a good design?
Producibility, testability, affordability, Fully integrated software, tech transition, supportability, mission performance, cost efficiency
(3.5.1) What are the goals of the 7 areas of SE?
- Production, Quality & Manufacturing (PQM)
– Ensure the producibility or relative ease of manufacturing an item or system - Science and Technology (S&T)
– Ensures system solution considers transition of new and emerging technologies - Test and Evaluation (T&E)
– Compares a system or components against requirements and specifications through testing –
Verification & Validation - Hardware/Software Engineering
– Ensures systematic approach to the development, operation and maintenance of
hardware/software - Acquisition Logistics
– Considers support strategy that can be cost‐effectively supported throughout a systems life cycle - System Engineering
– Technical design and management of a system that includes hardware, software and life‐cycle
elements
– Technical effort through which systems products and processes are simultaneously developed
– Integrated Product and Process Development (IPPD) is the Management philosophy to achieve this - Cybersecurity
– Encompasses necessary actions taken to ensure the Confidentiality, Integrity, and Availability of
system information to enable warfighting operations