Exam Flashcards
(167 cards)
Project Phases of E.P.C Companies
1) Planning and Designing
2) Procurement
3) Construction - done by sub-contractors; but both the client (owner) and EPC firms have site representatives. Regular inspections will be done on the construction site.
4) Commissioning - Equipment is cleaned (blown, flushed, purged), pumps, meters, controls are energized, checked and adjusted. Process is first tested with water then with the actual chemicals (Start-up). This process is carefully planned and may take years.
5) Handover - to owner who will operate and maintain the plant. Training will be provided to the people who will be operating the plant.
Operations
Plant Manager
- Technical
- Production
- Utilities
- Maintenance
- Admin
Technical Section
- “Engineering” - analysis of operations, design of modification in existing plant, expansions, planning for shut downs/start ups, etc.
Production Section
- Heart of the plant - running the plant makes profit.
- Costs the same if the plant is idle or at full capacity.
- Dominated by shifts (8 hr, 12 hr, etc.)
Utilities Section
- May be blended with production
- Provides operation of utilities - steam, water, air and power.
- Normally operates with the same shift schedule as the production section.
Maintenance Section
- Provides mechanical and electrical (control) services.
- Shift workers or contractors will be hired for larger projects
Admin Section
- HR, Payroll, Accounting etc.
Fine Chemicals
- High purity
- High Unit Value (>$10/kg)
- Often produced in small quantities (<1000 tons/year)
- E.g. Gold, heavy water, pharmaceutical products.
Bulk Chemicals
- Lower unit value
- Typically low purity
- Produced in large quantities
- E.g. Fuel, fertilizers, paper
Raw Material
- Could be a natural material that is extracted or recovered at the plant site; e.g. NaOH for making soap, NiCL, for preparing and electrolytic solution.
Process - “creating” a product
- Common case is a reaction
- The vessel is called a reactor.
- The reaction converts the raw material to a product
- May have multiple stages with multiple reactions and processes.
Purification
- Most chemical reactions produce more than one product
- Require pure products not mixtures
- Most of the products can be sold, those that cannot are termed as “waste products”
- Sometimes the purification process is a reaction that occurs to precipitate certain materials which can then be separated from a solution
- Sometimes it involves removing an unwanted solvent, commonly by heating.
Batch Processes
- Shorter time periods.
- Can create a variety of products in limited quantities, e.g polymers.
- Less control required.
- Can be operated manually.
- Production can be done in stages with intermediate storage.
- Plant will not operate on a shift basis.
Continuous Process
- Continuous flow of feed and product streams.
- Can create a specific type of product in very large quantities.
- Well controlled and monitored.
- Mostly automatic processes.
- Less storage space required.
- Plant operates on shift basis, 24 hours, 7 days a week.
- Production is stopped only for maintenance
Two main types of reactors
Batch and Continuous
Batch Reactors
- Used in a laboratory
- Reactants are placed in a test-tube, flask or beaker. Mixed together, often heated for the reaction to take place and are then cooled. The products are poured out and, if necessary. purified.
Continuous Reactors
- Reactants are continuously fed into the reactor at one point, and products are withdrawn continuously from another point. There must be an equal flow rate of reactants and products.
- Large quantities of chemical can be produced.
- Operated hours, 7 days a week.
- Product has a more consistent quality than a batch reactor because the reaction parameters (eg, residence time, temperature and pressure) are better controlled.
- Produce less waste and require lower storage of both raw materials and products.
- Capital costs per tonne of product produced are consequently lower.
Main Disadvantage of a Continuous Reactor
Their lack of flexibility.
Tubular Reactors (Continuous)
- AKA plug flow reactors.
- Fluids (gases and/or liquids) flow through hollow tubes at high velocities.
- Mixing provided by turbulence.
- High turbulence is achieved in small diameter pipes (high velocity)
- As reactants flow along the tubes/pipes which may be heated or cooled, they are converted to products.
- There is little/no back mixing. The conditions are referred to as plug flow.
- Reduces side reactions and increases the yield of the desired product.
- With constant flow rate, changes in time of the reaction are measure in terms of the position along the length of tube.
- Reaction rate is faster at pipe inlet.
- Reaction rate reduces as reactants flow through pipe due to the decrease in concentration of the reactant.
Advantages if Tubular Reactors
- Easy to maintain and clean - no moving parts.
- Simple and good for rapid reactions.
- Low pressure drops.
- High conversion per unit volume.
Disadvantages of Tubular Reactors
- Difficult to control - temperature and composition varies along the tube.
- Hot spots may occur.
Fixed Bed or Packed Bed Reactors (PBRs) (Continuous Reactors)
- Gases flow through a fixed bed of solid catalyst.
Advantages of Fixed Bed/Packed Bed Reactors
- Construction, operation and maintenance costs are low.
- Good for high pressure and high temperature systems.
Disadvantages of Fixed Bed/Packed Bed Reactors
- Difficult to control.
- Channeling may occur.
- Temperature variations may occur.
- Side reactions possible.