how to convert degree minutes seconds to degrees
divide minutes by 60 and seconds by 3600 and add to the degrees
how to convert gons/ gradians to degrees
x 180/200 or x 9/10
360 degrees = ____ radians
2*pi
list elements of engineering surveying (max 6)
investigate land
producing plans for design
on-site 3D construction (setting out)
monitoring the construction process
recording the final ‘as-built’ position
providing control points to monitor structural movements
what is the standard area units (other than m^2)
how does this convert to m^2
hectares
1 hectare = 10,000m^2
or acre = 100m^2 (since hec- =100)
calculator conversion functions for:
- dms to degrees
- polar to rectangular and vice versa
button with symbols on it (after each value - INLCUDE zeros)
Pol and Rec (bottom right) via shift key and use shift comma (bracket button) between
how is leveling used
vertical control systems
setting out
contouring
alignment in designs
if the error is less than 1 mm per 20m, _________. However if the error is _________, ____________.
don’t adjust the instrument
greater than 1mm per 20m, adjust the instrument (check the compensator)
Vertical angles above the horizontal plane are said to be _____, and those below ______.
elevation
depression
radians to seconds
x206265
What are fiberglass tapes made of
fiberglass strands embedded in PVC
Properties of fiberglass tapes
stretchy, light, flexible
List some key properties of steel tapes
fragile/ brittle
must be kept dry
What is the composition of a steel tape
steel protected by coats of polyester or nylon
steel tapes are calibrated _____________________.
at a specific temperature and tension
phase measurements are used for distance between ______ and ____. Timed pulse is used for __________.
200m and 300m, distance up to 2000m
is accurate alignment necessary in EDM?
no, only ±10% incidence needed
what is a control network? when is this completed?
a circuit of control points/ stations of known height/ TBMs if necessary which link together as a network
before surveying commences
what are the three types of control network
horizontal (rectangular co-ordinates based on grid with origin)
vertical (points defined relative to a datum
combined
which type(s) or north are typically used and not used in surveying
NOT true north
magnetic north (prismatic compass) or arbitrary north (assigned for good grid alignment)
what are the conventions of whole circle bearings
3 figures
measured clockwise from north
misclosure tolerance for control traverses
±30*sqrt(n)
n = no. of stations
advantages of terrestrial laser scanning
creates digital terrain models (DTMs)
non-contact (limited site disruption)
independent of daylight
high precision and accuracy
disadvantages of terrestrial laser scanning
line of sight dependent
laser diverges at long ranges
dark/ reflective features difficult to map
high power input required