Faults Flashcards
(93 cards)
You have just replaced a fellow project manager. After reviewing the project documents, you couldn’t find any project charter, and by speaking with the sponsor you were told that your company executes many projects without using project charters. As a project manager, you should:
A) Conduct a meeting with the sponsor to discuss the urge of having a project charter.
B) Establish a project charter and conduct a meeting with your team to explain everyone’s duties and responsibilities and to clarify the project’s key deliverables.
C) Establish a draft of the project charter and raise to your manager. D) Conduct a kick-off meeting and announce project start.
A
You are an owner of a small start-up technical office. You have been awarded a fixed price project by a governmental organization which you are requirec to complete in 3 months. The project charter is approved and the key people who were affected by success and failure of the project have been identifie After working with the project team, you have decided to execute the project by using agile approach. What should you do next? A) Perform qualitative risk analysis. B) Conduct kick-off meeting. C) Complete stakeholder analysis. D) Work with team and build an implementation strategy.
D
During project closure and transfer of the completed project deliverables to the operations group, the project manager discovers that an audit report from an early project phase is missing. What should he do? A) Inform the operations group about the missing audit report. B) Ask the operations group to accept the project without the audit report. C) Complete project closure and update the OPA. D) Remove the audit report from the required project documents and update the project management plan.
A
A Change request involving scope change has been approved by CCB. The project sponsor is part of the CCB, but the sole technical resource who is planned to work on the change request has suddenly gone for one week of vacation. If the work start date gets delayed, then the upcoming milestone will be impacted. In a project team meeting, a team member said that there is an alternative way of addressing the current situation and it is available. What should the project manager do? A) Create a change request for an additional resource B) Review the risk register with the project team and implement the risk response as stated by the project team member. C) Have a meeting with the project sponsor for buying out extra 2-weeks’ time in the project. D) Inform the current situation to the stakeholder which is most concerned with the change request.
B
Lucas is managing an underground tunnel project. The project sponsor got some information about the project that it is behind schedule and over budget, but he needs more details about the project’s progress. What should Lucas provide him to know about the status of the project? A) Work Performance Report B) Work Performance Information C) Work Performance Data D) Earned Value Report
A
Antonio is a project manager who is working with the project team to prepare project management plan. The project requires at least 5 resources who have specialized knowledge on a particular niche technology. What needs to be reviewed to find out whether such resources are available internally? A) WBS Dictionary B) Enterprise Environmental Factors C) Organizational Process Assets D) Project Team Assignments
B
An infrastructure project is near its closure. The project manager is now carrying out all of the activities associated with project closure. Which of the following activities should the project manager and team perform as a part of the process? A) Update enterprise environmental factors. B) Update all the project documents and mark them as final version. C) Ask the customer for a letter recommending that the contract can be closed. D) Update organizational process asset to include the final version of pre-approved sellers list and seller performance evaluation documentation
B
During one of the project’s meeting, some of your team members had a heated discussion regarding the resources required for a certain work activity. You let each one of them presents his point of view and after consultation with the rest of the team, you reached an agreed amount for the resources used for the activity. The approach you used is called: A) Problem Solving B) Forcing C) Compromising D) Smoothing
A
You have been recently assigned to a project as a project manager. You are involved in creating a document that would formally authorize the project and capture the initial requirements of the stakeholders. Which of the following should you complete in order to conduct a kick-off meeting? A) Initiating B) Closing C) Planning D) Executing
C
After completing the work in your project, you want to communicate formal project closure and ensure transfer of liability. As a project manager, what should you do? A) Obtain final acceptance of the project deliverables. B) Transfer the ownership of deliverables to the assigned stakeholders. C) Obtain financial, legal, and administrative closure. D) Prepare and share the final project report.
C
You are managing a marketing project. Halfway of the implementation phase, it came to your knowledge that a competitor is going to put out the same products into the market. As a project manager, what should you do? A) Update the project charter. B) Perform cost-benefit analysis. C) Advise the sponsor to cancel the project. D) Perform stakeholder analysis.
B
You have just been hired to work in an ongoing project in which the functional managers are responsible for arranging work groups while the project manager is responsible for managing the project budget. What organizational structure type is being used in such project? A) Functional (Centralized) B) Matrix - Strong C) Matrix - Weak D) Matrix - Balanced
B
You have just been hired to work in an ongoing project in which the functional managers are responsible for arranging work groups while the project manager is responsible for managing the project budget. What organizational structure type is being used in such project? A) Functional (Centralized) B) Matrix - Strong C) Matrix — Weak D) Matrix - Balanced
C
Two of your best software developers had an intense argument regarding the way of performing a certain task in the deliverable of the project you are leading. You reviewed each of their viewpoints and you discovered that each one has a point. You tried to convince each of them with the other’s viewpoint and you succeeded to reach an agreement which lead to significant impact on the project. The method you used in handling such situation is called: A) Withdraw/avoid B) Smooth/accommodate C) Force/direct D) Collaborate/problem solve
D
Edward has that skill which makes him a super talented engineer. He has the skill that if someone with no experience got hired within his organization, it would take him many years to catch his skill. This type of knowledge is called: A) Explicit Knowledge B) Tacit Knowledge C) Experience Knowledge D) Embedded Knowledge
B
Assume that you are a project manager and you are having a phase gate meeting to decide whether to proceed with the following phase or not. Which of the following documents you are most likely to use? A) Milestone List B) Issue Log C) Activity List D) Project Charter
D
You received a phone call from your client asking to add a feature in the next deliverable that he thinks will have no impact on the project schedule or cost As a project manager, what is the first thing you should do? A) Hold a meeting with the client to further understand the change. B) Ask the client to raise a formal change request. C) Assess the impact of the change with your team. D) Implement the change immediately.
B
Throughout the life cycle of any project a lot of changes may happen to the original project management plan due to common problems and inconsistencies which lead to several corrective and preventive actions to be taken. In order for a project manager to be able to effectively manage such gaps, which document should be of help? A) Issue Log B) Assumption Log C) Configuration Management Plan D) Risk Register
A
Andrew is a new project manager who has joined the luxury complex construction project during the middle of its execution. He is trying to determine whether the modification of any of the project documents is subject to change request. What needs to be reviewed to obtain this necessary information? A) Scope Management Plan B) Configuration Management Plan C) Requirement Traceability Matrix D) Change Management Plan
B
Mark is assigned to a construction project as a project manager. As he was writing the key deliverables for the project charter, he found that he has 2 alternatives and is unsure which one of them to choose: one is safer and the other is cheaper. What should Mark do to determine the key deliverables for the project? A) Establish requirements with the project sponsor. C) Use the cheaper technology in order to maintain the budget. B) Meet with the client to understand the technological requirements D) Choose the best option based on the project manager’s experience.
B
C
D
D
A