ffinal Flashcards

(49 cards)

1
Q

cement warehouse calucaltionss

A

A = 0.4*N/n
A = area required
N = # sandbags
n = max stack layers (13)
0.4 = area of one
#cement bag = 40 kg
*IF > 600 bags only store a third at site (multiply by 1/3)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

quantity take off temporary facility

A

Temporarily installed facilities to support construction works at the site
GC decide method/material

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

scaffold tempreatry calucations

A

gives space for workers temporary
Types
1. staright line
2. double line
Target
#Surface area vertical for scaffolding
FORMULA
(Sum of perimeter + 8D)H
D = seperation distance = 0.45 single, 0.9 double
H - height
*Perimeter = square if weired shape

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Foundation types

A

Individaul
= form of single upright column

Combined
=multiple com,bined columns

Strip
= entire wall = foundation

Map
=many many upright columns

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Earthwork

A

3 main steps
1. excavation
= remove soild in ground

  1. Backfill
    = soil placment and tamping
  2. Residual soil treatment

Estimate all 3

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Earthwork Estimation

A

Excavation volume
= volume of what is removed and values are given, easy to find

Backgfill
= ((Volume excavation - volume 2(given))1/Sh)Sw
Sw = percent swell = percent which it increases by
BCM * Sw = LCM
typ value = 1.25
Sh = shirnkage factor = compact volume to bank volume
BCM * Sh = CCm
typ value = 0.9

Residual vlume
= (1-(1-2)1/Sh)Sw

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Soil Volume Units

A

Bacnk cubic meter = natural state
Loose cubic meter = swelled from distruption/movement
Compacted cubic meter = soil compacted and becomes dense

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Reinforced concrete

A

Everyewher
in foundation
slab
wall
column
beam/girder

COMPONENTS
fine aggregate = sand
coarse aggregate = gravel
Cement = 10-15%
aggreageate - 60-75% (1:2 fine to coarse)
water 15-20%

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

RC calculate

A

Volume = BHL
Formwork = contact area = sides = 2AH + 2BH
Mass rebar

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

SURETY BOND DEFINITION

A

DEFINITION
A bond is a guarantee by one person (the surety) that if another person (the contractor) does not fulfill a responsibility to another (the owner) the surety will
THIRD PARTY AGGREMENT where
contractor = principal (required to be bonded)
owner is obligee (requireed bonds)
wurety is guranter(provide bonds to protect obligee from any mishap by principal)

Surety gurantee PARTICULAR ACTIVVIES OF CONTRACTOR(PRCINPIOPAL) to owner and contractor workers

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

BOND vs Insurance

A

INSURANCE = relieve contrcator from LOSS due to claims or damages insued

Surety bond
= GURANTEE PREFORMANCEW of deifned contract duty
= bond is CREDIT (CONTRACTOR = liable for all losses/payment by bond company)
= Guranttee to OWNER

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

SURETY AS CONTRACT

A

Contract
Failur in duty = breach of contract
= REQUIRED BY LAW IN PUBLIC CONTRACT
GC CAN REQUIRE BOND FROM SUB CONTRACTOR

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

SURETY COVERAGE

A

if GC FAILS to fullfill contract obligation surety assumes obligation seeing contract compelted and paying costs upto bond face amount
resposible for FINISHING CONTRACT

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

SURETY WHY?

A

construction = RISKY

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

HOw surety WOrks

A

bond CANNOT be invoked until BREACH of contract
BONDS = WRITTEN documents
Obligation ofo bond = PROVISION of document
for PRIVATE = OWNERS call
amount surety liable for = PENALTY AMOUNT

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

BOND TYPES

A

bid
preformance
paymetn

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

GC Duties/responsibilites ionn bond

A
  1. honor bid and sign all contracts
  2. preform objective of contract
  3. pay all costs for work
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

honor bid and sign all contracts: bid bond

A

Gurantees that:
enter into contract and provide other bonds required by bidding documents
pay difference btwn bid and next loewts responsible bid
up to limit of bid guranttee or pay damages

Surety= Recommended amount is 5-10% of max. possible contract amount

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

preformance bond to pregform objective

A

contractor or surety complete project
protect owner from costs about contract sum
surety has 3 choies
1. complete contract through competion contractor
2. select new contractor to contract directly with owner
3. allow owner to complete work within surety paying the costs
face valu eof bond = amount of money

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Payment Bond

A

pay gurantted, usually 100 percent
protects opwner from paying those not payed

21
Q

risk managemtn 5 steps

A
  1. Recognize/Idenitfy risks
  2. identify risk exposure
  3. decide how to eliminate
    elimination
    assume risk
    get INSURANCE
  4. company program
  5. montiro results
22
Q

Construciton risks

A

property-related risks
libaility risks
worker related risks
insurance covers contractors for these risks

23
Q

Insurance + risk managment

A

NOT ELIVIMANTE but SHIFT to professional risk bearer
insurance companies PAY FOR LOSSES and WORK ALONGSIDE the project for risk managemetn

24
Q

Why Insurance

A
  1. owner needs it
  2. cover risks
  3. required by law
  4. insurance comapny attournies defense in court
25
Insuarance Policty
TWO PARTY agrement prenium paid in advance
26
3 main insurance types
Property insurance Liability insurance WOrker insurance
27
Property insurance
project proterpty = lsoses from smoke, fire vandalism collapse and all ppl are covered builders risk=building construction w/ land specific stuff Equipment Floater Policy Named-Peril Builder’s Risk Insurance ll-Risk Builder’s Risk Insuranc
28
Liabiliyt insurance
29
Andrea Palladio
First modern archiect, italy renossance
30
John Smeaton
Fathre of civil eng + founder of society
31
Abraham Darby
Cast iron production/iondustrail revolution cast iorn super populatr
32
Bessemer process
steel cheaper and steel grinder
33
skyscrapers
steel girder + construction + saftey design = cause chicago home insurance first one
34
INfrastrucre projects post skyscraerp
unstructed + dynamic
35
saftey stats/trends
falls = most injury reason to not get hlep = shame, fear of losing job/judgment and not knowing alcohol abuse lack of skilled workers
36
non fatal leading
heavy lifting improper grip akward posture repetitve task
37
Accident
avoidable action by person or equitment that interputs production or potential to harm
38
hazard
potential of causing /contribute to accident
39
risk
measure of likelhood and concequnce of all hazards of activity/condition
40
injury
wound or damage to body in work enviornment
41
Heinrich’s Domino Theory
insight in preventative actions injury cause by accident cause by unsafe action caused by personne this personne due to social enviornment /ancetry = poor skills
42
Ergonomics
Design job to fit workers rather than have workers body fit the job adapt task, equitment tools ect to fit worker reduces stress uses phisiology, biomechanics, kinesiology, industrial hygiene
43
WSDS
injury / disorder in soft tissue = joint, msucle tendon carilge and nervous system
44
6 risk factors
akward postion forced elevation static muslces repetition physcial agressors organized poorly
45
seriousss risk factor on 3 characteristisc
inetnisy, duration, frequency
46
problem identifaciton
identiy prevelance and type of problems
47
risk factor analysis
what job factors expose ppl to it ex. wsha
48
risk evaluation
evaluate degree of risk ex. nosh, RULA, 3DSSPP
49