Final Revision Flashcards
Name some other programming software other than MS Project?
- ProjectLibre
- Asta Power Project
What was on the critical path in the pre-planning programme?
VP formed the critical path due to the inability to do some of the required surveys such as R&D Asbestos
Bat surveys - requirement to conduct over time (Must have 1 survey in May to August date range) Multiple required overall
Design & Access statement was required prior to submission of some of the architects design
What is the difference between valuation certificate and payment certificate?
Valuation cert is the precursory QS valuation
Pay cert is issued by the EA/CA
Pay cert can be amended to include deductions for LDs or works not in accordance.
What does RAAC stand for?
Reinforced airated autoclaved concrete
How might you improve structural load of an existing building?
Underpinning.
Efficient W2F ratio?
0.4 to 0.5
4 risk headings in NRM1?
Design Development
Construction Risks Estimate
Employer Change Risks
Employer Other Risks
Final account timelines in JCT D&B?
Contractor submit = 2 months post PC
Recommendation issued = 3 months (by EA)
Final account timelines in JCT SBC?
Contractor submit = 6 months post PC
Recommendation issued = 3 months (by CA)
How much was the civils package on the DC project?
£58m final B5.
£38m budget!
Price per KW on London?
£7500/kW
How much was the steels package on the DC project?
£64m final B5.
£55m budget.
Name 10 RICS Black Books?
- Acceleration
- Cashflow
- Change ctrl and management
- Commercial mngmnt
- Conflict avoidance & Dispute Resolution
- Construction Security & Performance Documents
- Cost Reporting
- Defining completion
- EA D&B
- E-Tendering
- EOT’s
- Final Accounts
- Fluctuations
- Interim Valuations & Payment
- Life Cycle Costing
- Management of Risk
- Surveying Safely
- Retention
- Tendering Strategies
- Termination/Corporate Recovery
- Value Management & VE
- Valuing Change
6 bribery prevention things?
P - Proportionate Procedures
T - Top Level Commitment
R - Risk Assessments
D - Due Diligence
C - Communication
M - Monitoring and Review
What is the currently anticipated final cost for the DC build?
Currently excluding all fees, indirects, and contingency pot: £780m
PTE budget = £760m
What risks did you highlight to your client going for a D&B Route?
Hard to prepare sufficient brief
Commit early to concept design (variation cost higher later as result)
Hard to compare tenders
Quality of design contingent on competency of contractor. Novation of eng/arch can mitigate.
Advantages of two stage tender?
Early contractor involvement - buildability
Collaborative working environment
Earlier start on site due to potential to overlap
Client can control supply chain selection
Contractor can use expertise to mitigate risk
Disadvantages of two stage tender?
Cost certainty not achieved 100% until final package is let
Additional PCSA fees
Ramp up costs 2nd stage (retender maybe?)
Advantages of D&B procurement route?
Time - Fast track overlap design/con
Cost - Option for lump sum/GMP
Contractor assumes all risk
Solid price certainty from early
Novation - benefits quality
With reference to the Tendering Practice Note 2017 - how would you deal with errors?
A - Accept or withdraw
B - Confirm or amend
How would a procurement route affect your costing?
Traditional = full design so less requirement on risk allowances.
D&B = More unknowns so more risk pot.
FIDIC timelines for valuation and change?
Valuation = 28 submit, 28 review (56 total)
Change = 28 submit, 42 review (70 total)
JCT payment timelines?
Valuation submitted 7 days prior to DD
Due date - +7 days
Payment Notice - +5 days
Final Payment - 21 days from Valuation date
Time period for relevant EVENT?
12 wks