Flashcards

exam focused (43 cards)

1
Q

What is a Functional Structure?

A

An org structure where project work is divided by functions (e.g., marketing, HR).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is a Matrix Structure?

A

A hybrid org structure where team members report to both functional and project managers.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is a Dedicated Project Team?

A

A separate full-time team focused solely on one project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is Organizational Culture?

A

Shared values and norms that influence behavior within an organization.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is a Project Scope Statement?

A

A formal definition of what the project will and won’t include.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is a Work Breakdown Structure (WBS)?

A

A hierarchical decomposition of project deliverables into work packages.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is a Priority Matrix?

A

A grid showing what’s constrained, enhanced, or accepted in terms of time, cost, and scope.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is a Responsibility Matrix (e.g., RACI)?

A

A chart that defines who is Responsible, Accountable, Consulted, and Informed for tasks.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is Top-Down Estimating?

A

High-level estimates based on past projects or expert judgment.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is Bottom-Up Estimating?

A

Detailed estimates for each task rolled up into a total.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is Parametric Estimating?

A

Using statistical relationships (e.g., cost per square meter × size).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is the PERT formula for Three-Point Estimating?

A

TE = (O + 4M + P) / 6

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is the Learning Curve Effect?

A

Repetitive tasks take less time due to gained efficiency.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Direct vs Indirect Costs?

A

Direct = tied to project activities; Indirect = shared across multiple projects/org units.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is a Project Network Diagram?

A

A visual representation of task sequences and dependencies.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is the Critical Path?

A

The longest path in the network with zero slack—controls project duration.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

What is Slack (Float)?

A

The time a task can be delayed without delaying the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Formula: Slack = ?

A

Slack = LS - ES or LF - EF

19
Q

What is the Forward Pass?

A

Method to calculate earliest start/finish times.

20
Q

What is the Backward Pass?

A

Method to calculate latest start/finish times.

21
Q

What are the 4 major risk response strategies?

A

Mitigate, Avoid, Transfer, Accept.

22
Q

What is a Risk Matrix?

A

A grid showing risk impact vs probability.

23
Q

What is a Contingency Plan?

A

A pre-planned response to a specific risk event.

24
Q

What is Opportunity Management?

A

Proactively managing positive risks to maximize benefit.

25
What is a Risk Owner?
The person responsible for monitoring and managing a specific risk.
26
What is Project Crashing?
Reducing project duration by adding cost/resources to critical tasks.
27
What is Fast-Tracking?
Performing tasks in parallel instead of sequentially.
28
What is the Optimum Project Duration?
The duration where total cost (direct + indirect) is minimized.
29
What is Crash Cost per Day formula?
(Normal Cost – Crash Cost) / (Normal Time – Crash Time)
30
What is EV (Earned Value)?
Value of work actually completed: % complete × Budget (BAC).
31
What is PV (Planned Value)?
Value of work planned to be done at a point in time.
32
What is AC (Actual Cost)?
Total cost incurred to date.
33
CV (Cost Variance) = ?
EV - AC
34
SV (Schedule Variance) = ?
EV - PV
35
CPI (Cost Performance Index) = ?
EV / AC
36
SPI (Schedule Performance Index) = ?
EV / PV
37
EAC (Estimate at Completion) = ?
BAC / CPI or AC + ETC
38
ETC (Estimate to Complete) = ?
EAC - AC
39
VAC (Variance at Completion) = ?
BAC - EAC
40
What are the 5 closure types?
Normal, Premature, Perpetual, Failed, Changed Priority.
41
What is a Project Audit?
A structured review of project performance, processes, and lessons learned.
42
What are Lessons Learned?
Documented experiences used to improve future projects.
43
What is the purpose of project closure?
Finalize deliverables, release resources, document performance, and learn.