FM - Decision 1 - 8) Critical path analysis Flashcards

(3 cards)

1
Q

Way to calculate early and late event times

A
  • Early → forwards → largest
  • Late → backwards → smallest
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Formula for float time of an activity and meaning of a critical activity

A
  • Float time = late finish time - duration - early start time
  • Critical activity if float time = 0
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Method of drawing a Gantt chart

A
  1. Draw duration axis along the top
  2. Draw and label solid-edged boxes for all critical activities on the first row
  3. For each non-critical activity (in chronological order of early start time) draw and label a solid-edged box for 0 float and then extend it with a dotted-edged box for its maximum float, (each activity on separate rows)
    ·
    (On day 10 means between columns labelled 9 and 10)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly