FM - Decision 1 - 8) Critical path analysis Flashcards
(3 cards)
1
Q
Way to calculate early and late event times
A
- Early → forwards → largest
- Late → backwards → smallest
2
Q
Formula for float time of an activity and meaning of a critical activity
A
- Float time = late finish time - duration - early start time
- Critical activity if float time = 0
3
Q
Method of drawing a Gantt chart
A
- Draw duration axis along the top
- Draw and label solid-edged boxes for all critical activities on the first row
- For each non-critical activity (in chronological order of early start time) draw and label a solid-edged box for 0 float and then extend it with a dotted-edged box for its maximum float, (each activity on separate rows)
·
(On day 10 means between columns labelled 9 and 10)