Formulas Flashcards

1
Q

What is the PERT estimate formula?

A

(O +4M + P)/6 Example: If Optimistic is 2, most likely is 4 and pessimistic is 12 days the formula would be [2+(4*4) +12]/6 = 30/6 = PERT estimate is 5 days

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What is the Free Float (FF) formula?

A

Free float is the Early Start (ES) of the successor activity minus the Early Finish (EF) of the activity you are calculating the Free Float (FF) for.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is the Total Float (TF) formula?

A

The total float (TF) formula is the Late Start (LS) - Early Start (ES) of the activity you are calculating the TF for.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is the Early Start (ES) formula?

A

Early Start formula is the maximum of all predecessor activities Early Finish (EF). Example: If Activity D is a successor of Activity B and Activity C, and Activity B has an EF of 12 Weeks and activity C has an EF of 6 weeks, the ES of Activity D would be 12. Since you can not start activity D until both B and C have finished.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is the Early Finish (EF) formula?

A

Early Finish (EF) = Early Start (ES) + T where T equals the time estimated to complete the activity. Example: Say Activity Zed has an early start date of 3 and an estimated time of 5, that would be 3 + 5 = 8, giving Activity Zed an EF of 8

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is the Late Finish (LF) formula?

A

Late Finish (LF) = Is the minimum Late Start (LS) of all successor activities.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is the Late Start (LS) formula?

A

Late Start (LS) = Late Finish (LF) - T, where T equals the time estimated to complete the activity. Note that you start with the project’s LF which is the same as the projects EF which would be calculated in your forward pass through.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is the formula for Estimate at completion (EAC)?

A

Estimate At Completion(EAC) = Actual Cost (AC) + Estimate to Complete (ETC)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What is Planned Value (PV)

A

Planned Value (PV) is the target cost and schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is Earned Value (EV)?

A

Earned Value (EV) is the actual schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is Actual Cost (AC)?

A

Actual Cost (AC) is the actual cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What are the Earned Value Management (EVM) metrics?

A

Planned Value (PV)
Earned Value (EV)
Actual Cost (AC)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is Budget at Completion (BAC)?

A

Budget at Completion (BAC) equals the project’s cost baseline. There is no formula for calculating it, thus it is not often listed as a EVM metric.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is Planned Value (PV)’s formula?

A

Planned Value (PV) = Planned%Complete x Budget at Completion (BAC)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is the Cost Variance (CV) formula?

A

Cost Variance (CV) = Earned Value (EV) - Actual Cost (AC)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is the Cost Performance Index (CPI) formula?

A

Cost Performance Index (CPI) = Earned Value (EV) / Actual Cost (AC)

17
Q

What is the Schedule Variance (SV) formula?

A

Schedule Variance (SV) = Earned Value (EV) - Planned Value (PV)

18
Q

What is the Schedule Performance Index (SPI) formula?

A

Scheduled Performance Index (SPI) = Earned Value (EV) / Planned Value (PV)

19
Q

What is the Bottom - Up formula for recalculating the estimate of the remaining work?

A

Estimate At Completion (EAC) = Actual Cost (AC) + Estimate to Complete (ETC) (Where ETC = the sum of all remaining activities)

20
Q

What is the budgeted rate formula?

A

Estimate At Completion (EAC) = Actual Cost (AC) + (Budget At Completion ((BAC)) - Earned Value ((EV))) Since Estimate to Complete (ETC) = Budget At Completion(BAC) - Earned Value (EV)

21
Q

What is the Cost Performance Index (CPI) formula?

A

Estimate at Completion (EAC) = Budget at Completion (BAC) / Cost Index Performance (CPI)

22
Q

What is the formula for Cost Performance Index (CPI) and Schedule Performance Index (SPI) to factor in Cost Variance (CV) and Schedule Variance (SV)?

A

Estimate at Completion (EAC) = Actual Cost (AC) + (Budget at Completion ((BAC)) - Earned Value ((EV))/ Cost Performance Index ((CPI)) x Schedule performance index ((SPI)))

23
Q

What is the Variance at Completion (VAC) formula?

A

Variance at Completion (VAC) = Budget at Completion (BAC) - Estimate At Completion (EAC) ((Using any of the formulas for calculating EAC is acceptable))