Formulas Flashcards

(64 cards)

1
Q

Cost Variance (CV) Formula
Concept
Results Interpretation

A

FORMULA: CV = EV – AC
Concept:
Provides cost performance of the
project. Helps determine the amount
of budget deficit or surplus at a given
point in time

Results:
Negative = over budget = over planned
cost
Zero = on budget = on planned cost
Positive = under budget = under
planned cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Cost Performance Index (CPI)
Concept
Results Interpretation

A

FORMULA: CPI = EV / AC

Concept:
The measure of cost efficiency on a
project. The ratio of earned value to
actual cost.

Results
<1 = over budget = over planned cost.
The project is getting <$1 for every $1
spent.
1 = on budget = on planned cost.
The project is getting $1 for every $1
spent.
>1 = under budget = under planned
cost. The project is getting >$1 for
every $1 spent.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Schedule Variance (SV)
Concept
Results Interpretation

A

FORMULA: SV = EV – PV

CONCEPT: Provides schedule performance
of the project. Helps determine if
the project work is proceeding as
planned

RESULTS
Negative = behind schedule
Zero = on schedule
Positive = ahead of schedule

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Schedule Performance Index (SPI)
Concept
Results Interpretation

A

FORMULA: SPI = EV / PV

CONCEPT:
The measure of schedule efficiency
on a project. The ratio of earned value
to planned value. Used to determine
if a project is behind, on or ahead of
schedule. Can be used to help predict
when a project will be completed.

RESULTS
<1 = behind schedule. The project
is progressing at a slower rate than
originally planned.
1 = on schedule. The project is
progressing at the originally planned
rate.
>1 = ahead of schedule. The project
is progressing at a faster rate than
originally planned.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Schedule Variance (SV), an
alternative method
Concept
Results Interpretation

A

FORMULA: SV = ES – AT

CONCEPT: Provides schedule performance of the
project in terms of Earned Schedule
(ES) and Actual Time (AT).

RESULTS:
Negative = behind schedule.
The project earned less than planned
Zero = on schedule. The project earned
as planned.
Positive = ahead of schedule. The
project earned more than planned.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Schedule Performance Index (SPI)
(Alternative Method)
Concept
Results Interpretation

A

FORMULA: SPI = ES / AT

CONCEPT: Measure of schedule efficiency on a project in terms of Earned Schedule
(ES) and Actual Time (AT).

RESULTS: <1 = behind schedule. The project
is progressing at a slower rate than
originally planned.
1 = on schedule. The project is
progressing at the originally planned
rate.
>1 = ahead of schedule. The project
is progressing at a faster rate than
originally planned.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Estimate at Completion (EAC)

A

CONCEPT:
Expected final and total cost of a
project based on project performance.
Helps determine an estimate of the
total costs of a project based on actual
costs to date. There are several ways
to calculate EAC depending on the
current project situation and how the
actual work is progressing as compared
to the budget. Look for keywords in
the exam questions to determine what
assumptions were made

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Assumption: use this formula if the
current cost performance is expected
to remain the same for the remainder
of the project.

A

FORMULA
EAC = BAC / CPI

RESULTS
Original budget modified by the cost
performance. The result is a monetary
value.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Assumption: use this formula if the
original estimate was fundamentally
flawed or conditions have changed
and invalidated original estimating
assumptions.

A

FORMULA
EAC = AC + Bottom-up ETC

RESULTS
Actual cost plus a new bottom-up
estimate for the remaining work. The
result is a monetary value.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Assumption: use this formula if the
current cost variance is not expected
to occur again for the remainder of
the project, which means the original
budget is still reliable.

A

FORMULA
EAC = AC + (BAC – EV)

RESULTS:
Actual cost to date (AC) plus unearned
budget (BAC – EV). The result is a
monetary value

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Assumption: use this formula if
both the CPI and SPI influence the
remaining project work.

A

FORMULA
EAC = AC + [(BAC – EV) / (CPI * SPI)]

RESULTS:
Actual cost to date (AC) plus unearned
budget (BAC – EV) modified by both
cost performance and schedule
performance. The result is a monetary
value.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Estimate to Complete (ETC)

A

The expected cost needed to complete
all the remaining project work. Helps
predict what the final cost of the
project will be upon completion.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Assumption: Use this formula if no keywords could
be found.

A

FORMULA: ETC = EAC – AC

RESULTS:
Expected total cost minus actual cost
to date. The result is a monetary value
that tells how much more the project
will cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Assumption: A new estimate is developed when it is thought that the original estimate was flawed.

A

RESULTS:
This is neither a formula nor the result
of a calculation. It is simply a new
bottom-up cost estimate (re-estimate)
of the remaining project work.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Assumption: use this formula if
current variances are not expected
to occur again for the remainder of
the project, which means the original
budget is still reliable.

A

Formula: ETC = BAC – EV

Results:
The value of the unearned project
work. The result is a monetary value.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Assumption: use this formula if
both the CPI and SPI influence the
remaining project work.

A

Formula: ETC = (BAC – EV) / (CPI * SPI)
Results:
The value of the unearned project work
modified by both cost performance
and schedule performance. The result
is a monetary value.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Assumption: use this formula if
current cost performance is expected
to remain the same for the remainder
of the project.

A

Formula: ETC = (BAC / CPI) – AC

Results:
Original budget modified by the cost
performance minus the actual cost.
The result is a monetary value.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

To-Complete Performance Index (TCPI)

A

Assumption:
A measure of cost performance that
must be achieved on the remaining
work to meet a specific management
goal (e.g., BAC or EAC).
It is the work remaining divided by the
funds remaining.

Formula:
Based on BAC:
TCPI = (BAC – EV) / (BAC – AC)
Based on EAC:
TCPI = (BAC – EV) / (EAC – AC)

Results:
>1 = harder to complete. The project
needs to improve its cost performance
to be completed on target.
1 = same to complete. Same cost
efficiency can be maintained to
complete the project.
<1 = easier to complete. The project is
expected to achieve its cost targets.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

Variance at Completion (VAC)

A

Assumption:
Anticipates the difference between the
originally estimated BAC and a newly
calculated EAC. In other words, the cost
that was originally planned minus the
cost that is now expected.

Formula:
VAC = BAC – EAC

Result Interpretation:
The result is a monetary value that
estimates how much over or under
budget (the variance) the project will
have by its completion.
<0 = over planned budget
=0 = on planned budget
>0 = under planned budget

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

Earned Value (EV)

A

Assumptions:
A measure of completed work
expressed in terms of the budget
authorized for that work.

Formula:
EV = Sum of PV of completed work
Assumption: use this formula if PV for
all completed work is given.
EV = % complete * BAC
Assumption: use this formula if PV for
all completed work is not given.

Results:
The result is the EV, a monetary value.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

Activity Duration

A

Assumptions:
Determines how long an activity lasts.
There are two formulas; both will give
the same result

Formula’s:
Duration = EF – ES + 1
Duration = LF – LS + 1

Results:
Number of days an activity lasts.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

Free Float

A

Assumptions:
The amount of time a schedule activity
can be delayed without delaying
the early start date of any successor
activity or violating a schedule
constraint.

Formula’s:
Free Float = ES of Successor Activity
– EF of Present Activity –

Results:
A number of time units (typically
days) an activity can be delayed
without delaying the early start of the
successor activity.
Note: If the present activity has more
than one successor activity, then use
the earliest ES of any of the successor
activities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

Total Float

A

Assumptions:
The amount of time a schedule activity
can be delayed or extended from
its early start date without delaying
the project finish date or violating a
schedule constraint. There are two
formulas, both will give the same
result.

Formula:
Total Float = LS – ES
Total Float = LF – EF

Results:
A number of time units (typically days)
an activity can be delayed without
delaying the finish date of the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

Early Finish (EF)1

A

Assumptions:
Determine when an activity can finish
at the earliest.

Formula:
EF = (ES + duration) – 1

Results:
A number of time units (typically days)
an activity can be delayed without
delaying the finish date of the project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Early Start (ES)1
Assumptions: Determine when an activity can start at the earliest. Formula: ES = (EF of predecessor) + 1 Results: The earliest day on which an activity can start.
26
Late Finish (LF)1
Assumptions: Determine when an activity can finish at the latest Formula: LF = (LS of successor) – 1 Results: The latest day on which an activity can finish.
27
Late Start (LS)1
Assumptions: Determine when an activity can start at the latest Formula: LS = (LF – duration) + 1 Results: The latest day on which an activity can start.
28
Net Present Value (NPV)
Results: Positive NPV is good. Negative NPV is bad. The project with the higher NPV is the “better” project.
29
Return on Investment (ROI)
The project with the higher ROI is better
30
Internal Rate of Return (IRR)
The project with the higher IRR is better.
31
Payback period
A project with a shorter payback period is better.
32
Benefit-Cost Ratio (BCR)
Assumption: A ratio that describes the cost versus benefits of a project Formula: Benefit / Cost Results: BCR < 1 is bad. BCR > 1 is good. The project with the higher BCR is the “better” one.
33
Cost-Benefit Ratio (CBR)
Formula: Cost / Benefit Results: CBR < 1 is good. CBR > 1 is bad. The project with the lower CBR is the “better” one.
34
Opportunity Cost
Results: For the PMP exam, the opportunity cost is usually a monetary value: Project B was selected over project A, therefore the opportunity cost is the unrealized profit of project A. Note that NO calculation is required.
35
Communication Channels
Concept: The number of all possible communication channels on a project. Formula: n * (n – 1) / 2 Results: A total number of communication channels among n people of a group.
36
Expected Monetary Value (EMV)
Formula: EMV = Probability * Impact
37
AC
Term: Actual Cost Description: Total cost expended and reported during the accomplishment of a project task or project. This can be labor hours alone; direct costs alone; or all costs, including indirect costs.
38
AT
Term: Actual Time Description: The time in calendar units between the actual start date of the project till the project status date.
39
BAC
Term: Budget at Completion Description: The sum of all budgets allocated to a project.
40
BCR
Term: Benefit-Cost Ratio Description: A ratio that compares benefits to cost
41
CBR
Term: Cost-Benefit Ratio Description: o A ratio that compares cost to benefit (inversion of BCR).
42
CPI
Term: Cost Performance Index Description: Cost efficiency rating on a project, expressed as a ratio of EV to AC
43
CV
Term: Cost Variance Description: A measure of cost performance on the project, expressed as the difference between earned value and actual cost.
44
EAC
Term: Estimate at Completion Description: The expected total cost for a scheduled activity, a group of activities, or the project when the work will be completed.
45
EF
Term: Early Finish Description: Early finish of an activity.
46
EMV
Term: Expected Monetary Value Description: This is a statistical technique that calculates the probable financial results of events.
47
ES
Term: Early Start Description: Early start of an activity.
48
ES
Term: Earned Schedule Description: A method of deriving time-based performance measure.
49
ETC
Term: Estimate to Complete Description: ETC is the expected cost needed to complete all the remaining work for a scheduled activity, a group of activities, or the project. ETC helps project managers predict what the final cost of the project will be upon completion
50
EV
Term: Earned Value Description: EV is the value of completed work expressed in terms of the approved budget assigned to that work for a scheduled activity or a work breakdown structure component.
51
FV
Term: Future Value Description: Value of money on a given date in the future
52
IRR
Term: R Internal Rate of Return Description: A capital budgeting metric used to decide whether an investment should be made. It is an indicator of the efficiency of an investment.
53
JIT
Term: Just-in-Time Description: An inventory strategy that strives to improve a business’s return on investment by reducing in-process inventory and associated carrying costs.
54
LF
Term: Late Finish Description: Late finish of an activity
55
LS
Term: Late Start Description: Late start of an activity.
56
NPV
Term: Net Present Value Description: A standard method for the financial appraisal of long-term projects. Measures the excess or shortfall of cash flows, in present value (PV) terms, once financing charges are met.
57
PERT
Term: Program Evaluation and Review Technique Description: A method that allows the estimation of the weighted average duration of tasks
58
PV
Term: Planned Value Description: The authorized budget assigned to the scheduled work to be accomplished for a scheduled activity or a work breakdown structure component.
59
PV
Term: Present Value Description: Value of money received today instead of in the future.
60
ROI
Term: Return on Investment Description: A ratio of money gained or lost on an investment relative to the amount of money invested.
61
SPI
Term: Schedule Performance Index Description: A ratio of work accomplished versus work planned, for a specified time period. The SPI is an efficiency rating for work accomplishment, comparing work accomplished to what should have been accomplished. It is a ratio of earned value and planned value. Alternatively, it is also expressed as a ratio of earned schedule to actual time.
62
SV
Term: Schedule Variance Description: A measure of schedule performance on the project, expressed as the difference between earned value and planned value. Alternatively, it is also expressed as the difference between earned schedule and actual time.
63
TCPI
Term: To-Complete Performance Index Description: The calculated project cost performance that must be achieved on the remaining work to meet a specific project goal (e.g., BAC or EAC). It is the work remaining divided by the funds remaining.
64
VAC
Term: Variance at Completion Description: VAC forecasts the difference between the Budget-at-Completion and the expected total costs to be accrued over the life of the project based on current trends