Formulas Flashcards

(22 cards)

1
Q

PERT Triangular Distribution

A

(O+M+P)/3

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

PERT Beta Distribution

A

(O+4M+P)/6

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Standard Deviation of an Activity

A

(P-O)/6

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Variance of an Activity

A

[(P-O)/6] squared

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Range of an Activity Duration

A

EAD plus or minus SD

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Total Float

A

LS-ES (Late and Early Start)
or
LF-EF (Late and Early Finish)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

EV

A

Earned Value

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

PV

A

Planned Value

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

AC

A

Actual Cost

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

CV

A

Cost Variance

EV-AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

SV

A

Schedule Variance

EV-PV

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

CPI

A

Cost Performance Index

EV/AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

SPI

A

Schedule Performance Index

EV/PV

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

BAC

A

Budget at Completion
Determined during cost management, in Determine Budget Process. Includes contingency reserves and defines total cost to be spent during project.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

ETC

A

Estimate to Complete
Re-estimation of remaining work
EAC-AC

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

EAC

A

Estimate at Completion
Three different approaches using EV, SPI, and CPI
AC+(BAC-EV) - assumes future work to be accomplished at budgeted rate
BAC/CPI - assumes cost performance til now is expected to continue
(BAC-EV)/(CPI*SPI) - considers both cost and schedule performance indices when estimating efficiency of ETC work

17
Q

VAC

A

Variance at Completion

BAC-EAC

18
Q

TCPI

A

To-Complete Performance Index
Two approaches
No new EAC value: (BAC-EV)/(BAC-AC)
New EAC value: (BAC-EV)/(EAC-AC)

19
Q

PV

A

Present Value
Time value of money and value of a future cash flow
FV/[(1+r)to the n]

20
Q

Number of Communication Channels Formula

21
Q

EMV

A

Expected Monetary Value of opportunity or threat

Probability * Impact

22
Q

PTA

A

Point of Total Assumption
Applicable only in FPIF contracts. Costs above PTA are considered to be due to mismanagement.
[(Ceiling price-target price)/Buyer’s sharing ratio]+Target Cost