Formulas and Memorization Flashcards
(23 cards)
BAC
Budgeted at Completion
PV
Planned Value
PV = “Planned% Complete” x BAC
EV
Earned Value
EV = “Actual% Complete” x BAC
AC
Actual Cost
CV
Cost Variance
CV = EV - AC
SV
Schedule Variance
SV = EV - PV
CPI
Cost Performance Index
CPI = EV/AC
CPI^c
Cumulative CPI
CPI^c = EV^c/AC^c
SPI
Schedule Performance Index
SPI = EV/PV
EAC
Estimate at Completion
EAC = BAC/CPI^c
AC+(BAC-EV)
AC + (BAC-EV)/(CPI*SPI)
AC+ETC
ETC
Estimate to Completion
ETC = EAC - AC
VAC
Variance at Completion
VAC = BAC - EAC
TCPIc
To-Complete Performance Index
BAC - EV) / (ETC
Beta Distribution
PERT (Three-Point Estimating)
(P+4R+O)/6
Standard Deviation (sigma)
PERT (Three-Point Estimating)
(P-O)/6
sigma^2 = [sum(x - mu)^2] / N
mu = mean
Triangular Distribution
PERT (Three-Point Estimating)
(P+R+O)3
EF
Early Finish
EF = ES + Duration - 1
LS
Late Start
LS = ES + Float
LF
LF = LS + Duration - 1
Float
Float = LS-ES or LF-EF
Bottom-left minus top-left, or bottom-right minus top-right
Communication Channels
Channels = n(n-1)/2
PTA
Point of Total Assumption
Target cost + (Ceiling price - target price) / (Buyer’s % share of cost overrun)
Discount Formula
PV = FV / (1 + ‘discount rate’)^period
PV = Present Value FV = Future Value