FS Testing (Cement Head) Flashcards
1
Q
To release the bottom plug put the following steps in order
A
Open middle valve, unscrew pin, close bottom valve
2
Q
- To release the top plug put the following steps in the correct order
A
Open top plug, unscrew pin, close middle valve
3
Q
Regarding the pin puller of the cement head what do you need to check before the job
A
tattle tail
4
Q
You have finished dropping the top plug. After 10-20 bbl displacement what must be done
A
open all plugs