1
Q

Rapid physical removal of the material is the single most important action associated with effective decontamination.

T/F

A

true

2
Q

All exposed people must be immediately removed from the area of release to an area of safe refuge. This area is considered the _________ zone.

a. hot
b. warm
c. cold

A

b. warm

3
Q

Removing a victims clothing removes up to________ percent of the contamination.

A

90

for a ff in full gear/scba its even higher

4
Q

When setting up mass decon with a 2 1/2 handline it should be equipped with __________ nozzle.
The recommended pressure is between ___to___psi.
Additional hand lines should be opposite each other ___ to ___ feet apart

A

Aquastream fog noz

50-80 psi

25’-30’ apart

5
Q

When using 2 pumpers parallel to each for mass devon other, they should be ___ feet apart with the control panels facing [inside/outside].

A

25’

control panel outside

6
Q

When using 2 pumpers for mass devon the ________ nozzle should be placed on the selected discharge gate and the recommended operating pressure is ____ to ____ psi.

A

aquastream fog noz

50-80 psi

7
Q
  1. For mass decon a tower ladder uses the ________ nozzle

2. The ladder pipe uses the _________ nozzle.

A
  1. TL- turbomaster fog noz

2. aerial Aquastream fog noz

8
Q

If a secondary personal decontamination is warranted, after it is performed the victims are not considered clean and should not be removed from the scene.

T/F

A

False

they are considered clean and can be removed