G-2 Forming Systems Flashcards

1
Q

Formwork for footings must be…

A

correctly positioned, level, accurately dimensioned and easy to remove (strip)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Concrete footings must be cast…

A

directly on an undisturbed bearing surface

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Simple Forms consist of…

A
Form sides (either partial or full)
And cleats (which also act as spreaders)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

when setting footing forms with a level

A

always set them a little high. pounding the stakes slightly further into the ground makes the final adjustment

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Continuous strip footings

A

Are footings that support a foundation wall and are normally continuous.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

The foundation wall..

A

Resists the pressure caused by the compacted backfill
The floor joists at the top
and the footing at the bottom support the wall

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Keyway

A

A cut out in the concrete when pouring footings and foundation walls separately.
Normally with a beveled 2x4 or etched in after the pour

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Maximum vertical step & minimum horizontal distace to next step

A

600mm (BC Building Code)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly