GENERAL FOCUS Flashcards

(256 cards)

1
Q

What is the acceptable height of the bottom of an
overhead cabinet in the kitchen (from floor
to bottom of cabinet)?

A

1.4 meters

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

T/F An over-reinforced beam is ideal and safe.

A

FALSE.

Why?
- Concrete will
fail instantaneously
without warning
after the failure
of steel
reinforcements

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

A wood or metal material used to anchor
and elevate a roof tile over its
undersheeting.

A

Batten

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Which type of hardboard made from wood
fibers glued under heat and
pressure and may be utilized for doors and
furniture?

A

Medium Density
Board

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

How is a concrete cantilevered beam
reinforced?

A

By providing extra top
bars at and near the
support to resist
tension

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Concrete cover for cast-in-place concrete
permanently exposed to earth ,such as a
footing?

A

75 mm

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

A ferrous material with a very low carbon
content which is malleable, tough and
ductile and is produced from pig iron in a
way to remove carbon and
other impurities

A

Wrought Iron

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

A mat footing may be ideal for this kind of
situation where there is a possible
relative movement of parts of a structure
caused by uneven settlement of the
underlying soil.

A

Differential
Settlement

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

A bolt which has smooth, domed heads,
with a square section underneath,
that pulls into the material to prevent
spinning during installation, and used
where the head may be inaccessible during
tightening.

A

Carriage Bolt

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Due to its appearance, this waterproofing
material used for roof decks and
basements, and may require a concrete
topping to protect from any impact that
may compromise the system as well as
have a more presentable surface. The
system may be installed by torching the
surface to activate adhesion to the concrete
base.

A

Bituminous
Waterproofing

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

T/F

The slab has main reinforcements running
in both ways if the ratio of the long span to the short span of the slab is less than 2.

A

TRUE

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

How do you reinforce a 0.60m-wide wall
footing for a 3-meter long CHB wall?

A

3 pcs 12mm main
bars with 12mm
transverse bars
every 0.30m O.C.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

A column has a size of 0.40 x 0.40 meters.

If 20mm steel bars are to be used, which of
the following is an appropriate and
acceptable number of vertical steel
reinforcements to be provided?

A

12 pieces

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

How do you determine the thickness of a
cantilevered slab?

A

Length of Slab / 10

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

A test that utilizes open ended conical
cones and measures the workability of
a freshly mixed concrete.

A

Slump Test

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

A layer between the finishing roof material
and the surface or framing and

usually serving as an additional layer of
weatherproofing and drainage such as
in the case of installing clay tiles.

A

Undersheeting

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Length of end lapping for corrugated Gl
roofing

A

10 - 12 inches

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

How are the steel reinforcements in a CHB
wall laid out?

A

10mm dia every 3
rows vertical and
0.60m horizontal

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Which of the following is the most
reasonable reinforcement for an 8-inch
thick retaining wall?

A

16mm vertical bars
spaced at 200mm
and 12mm
horizontal bars
spaced
at 250m. Both faces.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

L-shaped, machine threaded bolts. typically
embedded in concrete during
pouring used to fasten steel or wood with
it.

A

Anchor Bolts

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

T/F

Dead load includes the weight of the
construction materials, fixtures and
furniture.

A

FALSE

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

An arrangement of braces fixed between
wood floor joists to keep them in place and
distribute the load to adjacent floor joists.

A

Bridging

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

This component dissolves the paint to
make it usable and workable at normal
room temperature.

A

Solvent

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

The part of a wooden staircase supports
the steps

A

Stringer

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
How do you measure the depth of footing?
From the NGL to the bottom of footing
25
Elements added to steel to create stainless steel.
Nickel & Chromium
26
What will be the length of the extra bottom bars on a suspended beam which has a clear span of 8 meters?
1.6 meters 3.2 meters 4.8 meters 5.4 meters
27
A reinforcing material to resist shear and diagonal tension stresses in a beam.
Stirrups
28
Which of the following is not a consideration in determining the spacing of column ties?
not more than 20 main bar diameter
29
Which of the following represents the available sizes (diameter) of reinforcing steel bars (mm).
10, 20, 28, 32
30
A door has a height of 2.10 meters and a width of 1.20 meters. How many board feet of a 2'x6' wood is needed to construct a door jamb?
18 board feet 26 board feet
31
Identify the type of specification - The painted surface shall show no sign of alligatoring, flaking or cracking or of equivalent defects.
Performance
32
Reinforcements which absorbs the stresses resulting from shrinkage particularly during the curing of concrete
Temperature Bars
33
How are wood floor joists attached to concrete beams?
Wood floor joists are bolted or nailed directly on the concrete beam
34
A type of glass processed by controlled thermal or chemical treatments to increase its strength by putting the outer surfaces into compression and the interior into tension such that the glass shatters into small granular chunks when broken.
Tempered Glass
35
A pile depending on the resistance of soil or rock beneath its foot or support for its stability.
End Bearing Pile
36
Which of the following represents an acceptable depth of a countertop (from wall to edge)?
60 cm
37
The hardening of concrete which requires a favorable temperature, time and continuous presence of water or moisture in concrete after pouring.
Curing
38
Metal pins that are used for joining two or more members by passing a headed shank through a pre-drilled hole in each piece and hammering down the plain end to form a second head.
Rivet
39
A classroom has an interior dimension of 7x 9 meters and a height of 3.2 meters. There are 2 doors measuring 2.10 x 0.9 meters and a window measuring 1.2x 3.0 meters. Disregarding any protruding beams and columns, how many gallons of paint are needed to coat the interior walls with 3 coats of paint to create a smooth finish?
10 gallons
40
A room has a dimension of 7.5 x 11 meters. A perimeter 600x600mm tile is provided inside the room. How many board feet of 50mm thick planks are needed to finish the remainder of the floor area?
1,550 board feet
41
An office space has a column to column spacing of 8 meters and will utilize a centralized all-air system air condition system. If the office space is in a 5 storey building made of reinforced concrete which of the following may be a reasonable and optimal floor to floor height of the office space?
3.40 meters
42
What will be the minimum number of steps for a stair with a floor to floor height of 4.3 meters?
22 Steps
43
Which of the following is considered a function of a gusset plate?
It provides a greater surface area to connect chords and web members together through welding, bolting or bolting
44
T/F The contractor failed to perform his payment duties to the subcontractors and suppliers. This may result in forfeiture of his performance bond to be able to pay his dues.
False
45
A perimeter wall which bounds a rectangular 12 x 20 meter lot has a height of 2.4 meters on all sides except for a 12-meter frontage. How many bags of cement are needed to install, fill and plaster both faces of the 6-inch CHB wall using class B mortar? (Unit volume of cement mortar for 6'''; Mortar = 0.0008 cub. m.; Filler = 0.006 cub m.; Plaster = 0.003; Class B: 12 bags per cubic meters)"
1498 Bags
46
A layer of gravel placed on undisturbed soil to prevent the capillarity rise of moisture to a ground slab.
Substrate
47
A type of beam that is only supported on one side.
Cantilever beam
48
Waterproofing technique with cement no needed expertise
Cementitious
49
Defect paint too wet; paint surface that occurs when the top coat dries before the bottom layer.
Wrinkling
50
A long slender column of wood, steel, or reinforced concrete, driven or hammered vertically into the earth to form a part of a foundation system.
Piles
51
Architectural Bronze
Brass
52
It contains a considerable amount of water and cement
Grout
53
A mixture of water, cement, and, fine aggregates such as sand.
Mortar
54
Process of Joining Materials through Coalescence
Welding
55
The concrete curing time takes about _____ to be fully cured.
28 days
56
Hanging out in the sun or baking in a kiln with plastic
Brick
57
Made up of small particles to coarse
Medium Density Board
58
A chalk-based board with paper on the sides
Gypsum Fiberboard or Particle Board
59
Stronger than ceramic
Porcelain, Vitrified, Homogenous
60
Glass Without heat
Annealed Glass
61
Glass With heat or chemical
Tempered Laminated Annealed Float Glass
62
Sand and water pressured matte finish
Abraded honed sandblasted Glass
63
Sandblasted Glass also called
Frosted Glass
64
It is the structural member that supports the transverse load which usually rests on supports at its end
Beam
65
A beam having a single span supported at its end
Simple Beam
66
It is a beam that rests on more than 2 supports.
Continuous Beam
67
A beam with 2 span
Semi-continuous Beam
68
Movable Loads imposed on the floor such as people, furniture, and the like
Live Load
69
Static Load such as the weight of the construction materials that generally carry the live load
Dead Load
70
Those parts of the floor system placed on the girder of the beams where the floorboards are fastened.
Floor Joist
71
A short traverse joist that supports the end of the cut-off joist at a stairwell hole.
Header of Trimmer
72
A structural wood That supports and attaches the wood floor joist to the beam.
Corbel
73
Braces are fixed between floor joists to keep them in place.
Bridging
74
It is a steel reinforcing bar manufactured with surface deformations to provide a locking anchorage with the surrounding concrete.
Deformed Bars
75
A steel bar having ribs to provide greater bonding strength when used as a reinforcing bar in reinforced concrete.
Rebars
76
A reinforcement device to resist shear and diagonal tension stresses in beam
Stirrups
77
Length of steel bars
20', 25', 30', 35', 40'
78
Concrete is an artificial stone made out of _______
Cement, sand, gravel, water
79
The materials over 9 mm in diameter
Course Aggregate
79
The materials smaller than 9 mm in diameter
Fine Aggregate
79
It is an inert granular material such as sand, round or crushed gravel, etc.
Aggregate
80
It is the hardening of concrete which requires time, favorable temperature, and continuous presence of water or moisture in concrete after pouring.
Curing
81
An excavating machine for cutting trenches. a boom-mounted bucket moves toward the machine, cutting the ground like hoe, then the machines turn away from the cut to permit the operator to dump the spoil.
Backhoe
82
A container of known volume used to measure and mixed the constituents of a batch of concrete, plaster or mortar, to ensure proper proportions
Batch Box
83
Soil is replaced in an area that has been excavated previously.
Backfill
84
A material other than WATER, AGGREGATE, LIME or CEMENT used as an INGREDIENT of CONCRETE or mortar, and added to the batch immediately before or during its mixture
Admixture
85
It refers to the soil or rock directly beneath the footing
Foundation Bed
86
The main reinforcements are placed at a right angle perpendicular to the wall uniformly spaced with each other and longitudinal reinforcement parallel with the wall.
Wall Footing
87
Voids left in the concrete owing to the failure of the mortar to fill effectively the space among coarse aggregate particles
Honeycomb
88
A piece of concrete that holds or supports steel reinforcement in its proper position.
Space
89
It has reinforcement consisting of vertical or longitudinal bars held in position by lateral ties
Tied Column
90
A deformed bar used as tie to hold vertical reinforcements of columns in place.
Tie Bars or Lateral Bars
91
A short reinforcing bars of steel that extend approximately equally into two abutting pieces of concrete to increase the strength of the joints.
Dowel
92
Size of wire to attach or connect steel reinforcement
16 GI Wire
93
To connect two similar members, usually in a straight line by fastening lapped ends using mechanical end connectors.
Splice
94
The thickness of galvanized iron (GI) roofing is measured in terms of __________
Gauge
95
The standard commercial width of corrugated gi sheet is _____
(32") 2.00 M / 6.6'
96
The sheet becomes thicker as the gauge number increases. (TRUE/FALSE)
FALSE - sheet becomes thinner
97
The standard length of a corrugated GI sheet ranges from _______
(5' to 12') 1.50 to 3.60 M
98
Plain GI sheet commercial standard size is
(36" x 8') 90 x 2.40 M
99
A type of corrugated GI roofing sheet that is either 1 ½ or 2 ½ corrugations.
Side Lapping
100
A type of corrugated GI roofing sheet that is from 20 cm to 30 cm depending upon the slope of the roof and the number of sheets in a longitudinal row.
End Lapping
101
Gutter should have a slope of ______ per meter for effective drainage.
5mm
102
Designed to prevent water penetration and provide drainage between a roof and a wall.
Flashing
103
T/F: The sheet becomes thicker as the gauge number increases.
FALSE - sheet becomes thinner
104
Plain GI sheet commercial standard size is___
0.90 x 2.40 M
105
A type of corrugated GI roofing sheet that is either 1 ½ or 2 ½ corrugations.
Side Lapping
106
A type of corrugated GI roofing sheet that is from 20 cm to 30 cm depending upon the slope of the roof and the number of sheets in a longitudinal row.
End Lapping
107
A shallow channel of metal, wood, or concrete below & along eaves to catch and carry off rainwater.
Gutter
108
Gutter should have a slope of ______ per meter for effective drainage.
5mm
109
It conveys the water from the gutter down to the storm drain.
Downspouts
110
The part of a roof of a building that projects beyond the wall.
Eaves
111
A metal or tile covering which caps the ridge of a roof.
Ridge Roll
112
A piece of timber or steel laid horizontally on the rafters of a roof to support the common rafters on which the roof covering is laid.
Purlin
113
A fastener used to secure a purlin to its support.
Purlin Cleat
114
One of a series of inclined members to which the roof covering is fixed.
Rafter
115
In a truss, any member that joins the top and bottom chord.
Web Member
116
In a truss, is a vertical member extending from the apex of the inclined rafters to the tie beam between the rafters at their lower end.
King Post
117
The ties between rafters on opposite sides of the roof.
Collar Plate
118
A device such as metal rod wire or strap, for fixing one object to another, as specially formed metal connectors used to fasten together, timbers, masonry, trusses, etc.
Anchorage
119
A principal member of a truss that extends from one end to the other, primarily to resist bending.
Chord
120
It is a board that is nailed horizontally to the ends of roof rafters.
Fascia Board
121
A type of corrugated GI roofing fastener that requires plain GI straps, GI rivets, and GI washers. The GI strap is folded 3 cm at one end, then a hole is punched using a nail set. A rivet and GI washer are inserted into the hole of the strap and then punched to hold it in position.
Riveting
122
A type of corrugated GI roofing fastener that is the simplest and most economical method. GI roofing sheets are anchored to the purlins using roof nails and a pair of GI washers.
Nailing
123
It is considered as the simplest form of roof consisting of one single slope.
Shed or lean-to Roof
124
It is the most common and economical form of a roof, made of triangular sections consisting of two slopes meeting at the center ridge.
Gable Roof
125
It is commonly used in factories where extra light is required through the window on the vertical side.
Saw Tooth Roof
126
It is a modification of a gable or a hip and valley roof
Double Gable Roof
127
A roof having four straight sides all sloping towards the center of the building terminating at the ridge.
Hip Roof
128
A combination of a hip roof and an intersecting gable roof forms a T or L-shaped building
Hip and Valley Roof
129
It is a modification of the gable roof with each side having two slopes.
Gambrel Roof
129
It is a modification of the hip roof wherein the four straight sides are sloping towards the center terminating at a point.
Pyramid Roof
130
It is a modification of the mansard roof where the sides are concave.
French or Concave Mansard Roof
130
The two sides of the roof slopes steeply from each side of the building towards the center forming a flat deck on top
Mansard Roof
131
It is a pyramid form having steep sides sloping to the center.
Ogee Roof
132
It is a steep roof of the circular section that tapers uniformly from the circular base to a central point.
Conical Roof or Sphire
133
It is a two-shed roof where the slopes meet at the center of the building.
Butterfly Roof
134
These are nailers to which the ceiling is attached.
Ceiling Joist
135
A strip of wood nailed to the underside of floor joists or rafters from which the ceiling is suspended or fastened.
Ceiling Strap or Hanger
136
An ornamental molding usually of wood or plaster, running around the walls of the room just below the ceiling.
Cornice
137
A concave or canted interior corner or molding, esp. at the transition from wall to ceiling or floor
Cove
138
A flat projection from an interior wall or partition at the floor, covering the joint between the floor and the wall and protecting the wall from kicking, mopping, etc.
Baseboard
139
A vertical structural member which acts as a supporting element in a wall or partition. The typical size of a wood stud is 2"x4".
Stud
140
A small post supporting the handrail or a coping
Baluster/Banister
141
A series of rows of balusters joined by a handrail.
Balustrade
142
A large square newel hollow inside, used in post to post balustrades.
Box Newel
143
A scroll-shaped decorative member mitered to the riser and fastened over the open stringer.
Bracket
144
That portion that supports the steps of wooden stairs
Carriage
145
Support for winders wedged into the walls secured by the stringers.
Bearers
146
It is a term given to winding staircase
Cockel Stair
147
The first step by which a stair is ascended, terminating at the end in the form of a scroll.
Curtail Step
148
A thin moulding that is fitted into plowed handrail and shoe rail between balusters.
Fillet
149
Steps in a flight that are parallel with each other
Flyers
150
A short transverse joist that supports the end of the cut-off joist at a stairwell hole.
Header
151
It is the corvex bend at the back of the handrail.
Knee
152
The front edge of the step that project beyond the riser
Nosing
153
The central column where the steps of a circular staircase wind.
Newel
154
The angle of inclination of the horizontal of the stairs.
Pitch
155
The angle formed by stairway.
Spandril
156
The board next to the well hole which receives the ends of the steps
String Board
157
The underneath of an arch or moulding.
Soffit
158
A supporting joist that carries an end portion of a header.
Trimmer
159
A tapered strip of wood driven into stringer routings to fasten treads and risers securely
Wedge
160
The opening in floor at the top of a flight of stairs
Well Hole
161
Steps not parallel with each other
Winders
162
Concrete in which steel reinforcement is embedded in such a manner that the two materials act together in resisting forces
Ferroconcrete
163
Constructed of cement mortar over wire mesh that has been pre-shaped over a mold
Ferrocement
164
Features on steel reinforcements to increase adhesion to concrete
Lugs
165
A reinforcement device to resist shear and diagonal tension stresses in beam
Stirrups
166
Length of steel bars
20', 25', 30', 35', 40'
167
Class A concrete mixture ratio
1:2:4
168
Concrete is an artificial stone made out of _______
Cement, sand, gravel, water
169
Fine Aggregates are materials smaller than ____ mm, while Course Aggregates are larger than it.
9mm
170
An excavating machine for cutting trenches.
Backhoe
171
Soil replaced in an area that has been excavated previously.
Backfill
171
What is the typical thickness of a 1-meter cantilever?
100m
171
TRUE/FALSE: Admixtures containing chloride ions shall not be used in pre-stressed concrete containing aluminum embedments.
TRUE
172
It refers to the soil or rock directly beneath the footing
Foundation Bed
173
Standard distance of reinforcement bars
25mm
174
The main reinforcements are placed at a right angle perpendicular to the wall uniformly spaced with each other and longitudinal reinforcement parallel with the wall.
Wall Footing
175
Voids left in the concrete owing to the failure of the mortar to fill effectively the space among coarse aggregate particles
Honeycomb
176
A piece of concrete that holds or supports steel reinforcement in its proper position.
Spacer
177
It has reinforcement consisting of vertical or longitudinal bars held in position by lateral ties.
Tied Column
178
A deformed bar used as tie to hold vertical reinforcements of columns in place.
Tie Bars or Lateral Bars
179
A short reinforcing bars of steel that extend approximately equally into two abutting pieces of concrete to increase the strength of the joints
Dowel
180
Size of wire to attach or connect steel reinforcement
16 GI Wire
181
To connect two similar members, usually in a straight line by fastening lapped ends using mechanical end connectors.
Splice
182
A pile that depends principally on the frictional resistance of the surrounding earth for support
Friction Pile
183
The documents furnished to bidders that includes not only contract documents but also bidding requirements.
Bidding Documents
184
TRUE/FALSE: Bidding documents are supplied by the architect during the bidding phase of a project before construction.
FALSE - supplied by the owner
185
The documents that comprise a contract, including the owner-architect agreement, drawings/plans, specifications, general conditions, special provisions, addenda, and modifications
Contract Documents
186
Includes contract terms, and bidding requirements to communicate the written and graphic design for the administration of the construction contract.
Construction Documents
187
Printed or written documents containing agreed-upon terms and conditions signed by or on behalf of contracting parties, confirming their willingness to be bound by the contract terms.
Contract Forms
188
The contract between the owner and the contractor undertaking the project described in the contract documents
Agreement
189
TRUE/FALSE: An agreement or a Contract of Service may be made between an Architect and a Contractor stipulating conditions.
FALSE - There is no Architect-Contracto r Agreement
190
The approved form of security furnished by the contractor and his surety is a guarantee of good faith on the part of the contractor to execute the work by the terms of the contract.
Performance Bond
191
The approved form of security furnished by the contractor and his surety is a guarantee of good faith on the part of the contractor to pay all obligations arising from the contract.
Payment Bond
192
Include certificates of insurance and certificates of compliance with applicable laws and regulations.
Certificates
193
The procedural and administrative aspects of the contract which sets forth the rights, responsibilities, and relationships of the parties involved.
General Conditions
194
Contract documents that outline contract terms, rights and duties of parties, safety requirements, legal compliance, work management procedures, contractor payments, and similar general provisions.
Conditions of the Contract
195
They represent that part of the contract documents which supplements and may also modify provisions of the general conditions.
Supplementary Conditions
196
Instructions which may be issued to the bidding to supplement and/or modify drawings, specifications, and/or general conditions of the contract.
Special Provisions
197
Detailed written document defining the scope of work, materials, installation methods, quality standards, and requirements for a contracted project.
Specifications
198
As a legal consideration, specifications shall govern over drawings (TRUE/FALSE)
TRUE
199
Additional information that may be issued as an addition or amendment to the provisions of the specifications.
Supplementary Specifications
200
A standardized document intended to guide the specifier in preparing a particular portion of the contract documents.
Guide Specifications
201
Graphical presentations of the work involved in the project.
Drawings
202
Drawings intended for use by a contractor, subcontractor, or fabricator, which form part of the contract documents for a building project.
Working Drawings
203
Drawing documents prepared by an architect for a construction project
Architectural Drawing Documents
204
Drawing documents that are technical, and used to define requirements for engineering items or work. e.g. structural, electrical, mechanical, and sanitary plans and details.
Engineering Drawing Documents
205
Written or graphic instruments that supplement the bidding documents to clarify, correct, or add to the specifications previously issued
Addenda
206
Addenda are changes made after contract execution (TRUE/FALSE)
FALSE, Addenda are changes made before contract execution
207
Those additions to, deletions from, or modifications of the work that are made after the agreement has been signed.
Contract Modifications
208
Contract modifications can be issued at any time during the contract period (TRUE/FALSE)
TRUE
209
Type of contract modification that authorizes a change in the work, an adjustment in the contract sum, or the contract time as originally defined by the contract documents.
Change Orders
210
Type of contract modification that effects a minor change in the work not involving an adjustment in the contract sum or an extension of the contract time.
Field Orders or Construction Change Authorizations
211
Type of contract modification that comes in the form of minor instructions not involving an adjustment in the contract sum or an extension of the contract time.
Supplemental Instructions
212
A complete set of bid and contract documents that include the bidding requirements, contract forms, contract conditions, and project specifications.
Project Manual
213
Document or material provided to the Architect/Engineer for review or acceptance.
Submittal
214
A specification that stipulates how a particular component or system must perform without giving the means to achieve the results.
Performance Specification
215
A specification that stipulates the exact quantities and qualities or properties of materials to be furnished and how they are to be installed in a construction.
Descriptive Specification
216
A specification that refers to a standard specification to indicate the properties desired.
Reference Specification
217
A specification that stipulates the use of specific products, systems, or processes without provision for substitution.
Proprietary Specification
218
A type of proprietary specification where the desired product is specified by the name given by the manufacturer or by the manufacturer's name and model number.
Brand name specification
219
A type of proprietary specification that can be single product or multi-product. Typically used to specify materials that must match existing materials in terms.
Closed Specification
220
A type of proprietary specification where products meet the description specified may qualify to bid, often using "or equal."
Open Specification
221
A combination of performance, descriptive, and reference specifications but never a combination of open and closed specifications.
Combination Specification
222
Describes in detail the materials, workmanship, installation, and procedures for contractors to achieve expected results; a form of descriptive specification.
Method System
223
In writing specification, state only requirements and do not provide reasons for the requirements (TRUE/FALSE)
TRUE
224
Traditional specification language using "shall" in nearly every statement, often causing wordiness and monotony
Indicative Mode
225
The recommended method for installation instructions, starting sentences with a verb.
Imperative Mode
226
This technique uses a colon (:) to mean shall or shall be.
Streamlined Mode
227
Used as a basis for project specifications, including standard work items, clauses, and numerous alternatives normally encountered by the organization.
Master Specifications
228
A weather-resistant mortar joint compressed and shaped with any tool other than a trowel
Tooled Joint - Concave joint - V-joint Raked joint Troweled Joint - weathered - flush - struck
229
San Agustin Church traditional mortar for stone masonry
Lime or apog
230
Additives to concrete to modify its properties
Admixture
231
Concrete curing period: 70% compressive strength
7 Days
232
Concrete curing period: 75% compressive strength
14 Days
233
Concrete curing period: 90% compressive strength
28 Days
234
Cement-to-Sand Ratio of 1:2
Class A
234
Bonding agent for masonry, plastic mixture of lime or cement mixed with water and sand
Mortar
235
Cement-to-Sand Ratio of 1:3
Class B
236
Cement-to-Sand Ratio of 1:4
Class C
237
Footing common in old churches in the Philippines; wall footing is a shallow strip footing
Strip footing
238
Strongest glass, common in high-rise
Laminated
239
Best choice for safety glazing in hazardous locations
Tempered or or Laminated Glass
240
Cobble filled retention structure
Gabion
241
zigzag/arched pattern beam
Castellated beam
242
Where are door fire ratings specified?
Door schedule
243
Sprayed mortar under high pressure
Gunite
244
Concrete construction, Common aggregate size for structural members
¾” to 1”
245
Ideal pile material in marshy watersfor low-rise
Wood
246
Measured using a slump cone, to measure the consistency of freshly mixed concrete
Slump test
247
Bar Number 2 = ¼ inches or 4mm
Bar number divided by 8 equals its diameter in inches
248
AAA = 1:1:2:6 for prestressed or post-tensioned AA = 1:1.5:3:6 for underwater retaining walls A = 1:2:4:6 for typical structural members, footings, columns, beams, slabs B = 1:2.5:5:6 slabs on fill C = 1:3:6:6 concrete plant boxes, and parapets D = 1:3.5:7:6 for pathways
Concrete : Sand : Gravel : Water or C:S:G:W