General Questions Flashcards
(132 cards)
What is the role of a PD ?
Responsibility for co-ordination of H&S during the pre-construction phase. Gives responsibility for CDM to an individual that has the ability to influence the design.
How did you assist as PD?
Issued an F10 Notice.
What is required for an F10 Notice?
Construction work is likely to last longer than:
30 working days/20+ workers working at any point in the project,
exceeds 500 person days.
Who do you submit an F10 Notice to?
HSE
What did CDM 2015 replace a PD with?
the role of CDM co-ordinator (CDMC)
What does CDM stand for?
Construction Design and Management Regulations (2015)
What is the purpose of CDM?
To cover the health and safety and management of Construction projects?
What are the five key parts of CDM
1) Interpretation
2) Client Duties
3) Health and Safety Roles and Duties
4) General Requirements
5) Transitional Arrangements.
How many regulations are in CDM 2015
39
How many key dutyholders are listed under CDM 2015?
5
Who are the five key dutyholders under CDM?
Client, Principal Designer, Principal Contractor, Designers and Contractor.
How does a Principal Designer meet the criteria to act as PD?
HSE suggests you demonstrate through technical knowledge, ability to understand manage and plan the PCS, CPD Records or being a member of the Association for Project Safety. Self assessing using PAS 91.
Difference between a PD and a CDM advisor?
PD= Legal duty under CDM regs
CDM advisor- not recognised role under CDM
PD cannot transfer legal duties to CDM advisor.
What is CLEAPSS?
Consortium of Local Education Authorities for the Provision of Science Services
What is CLEAPSS and how did they assist
Advisory service in the United Kingdom providing support in science and technology. I had early consultations with CLEAPSS to understand best teaching practice prior to submitting the feasibility report.
What is FFE?
Furniture, Fixtures and Equipment
What is a single stage traditional (fully designed) open tender?
Went to tender with completed design and specification. Contractor prices the schedule of work. This was uploaded to the DPS, which was an open tender allowing anyone to submit a tender to supply the goods or services
What is included in the Feasibility Stage 1 report
Establish client requirements and objectives, undertake desktop investigations and on-site investigations. Produce design options with technical considerations including initial drawings and a budget cost estimate.
What is a budget cost plan?
An early initial cost appraisal, using BCIS, quotes from manufacturers and similar projects to establish a likely cost of the project.
What types of surveys were undertaken at Feasibility?
- Measured survey
- CCTV drainage Survey
- Condition Survey
- R&D Asbestos Survey
How did you merge the concept-technical design and why?
A full report was requested by the client at RIBA Stage 1 and 4, for RIBA stages 2 and 3 a technical review took place.
What was some of the considerations in the stage reports?
Design/options, Cost Plan, Risk matrix, Procurement strategy, Logistics, Drawings, Next steps.
What software did you use to specify the works
NBS Specification (aware of new Chorus software)
What third parties/statutory bodies did you deal with?
Building Control, Strategic Procurement (Haringey)