Hot Topics Flashcards

(53 cards)

1
Q

What does BIM stand for?

A

Building Information Modelling.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What Is BIM?

A

BIM is a highly collaborative process that allows architects, engineers, developers, contractors, manufacturers and other construction professionals to plan, design, and construct a structure or building within one 3D model.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are the key benefits of BIM?

A

A building information model can be beneficial for the following reasons:
-Visualization: 3D renderings can be easily generated.

-Fabrication drawings: It is straightforward to generate fabrication drawings for various building systems.

-Cost estimating: BIM software has built-in cost estimating features. Material quantities are automatically extracted and updated when any changes are made in the model.

-Construction sequencing: A building information model can be effectively used to coordinate material ordering, fabrication, and delivery schedules for all building components.

-Conflict, interference, and collision detection: Because building information models are created to scale in 3D space, all major systems can be instantly and automatically checked for interferences. For example, this process can verify that pipeowrk does not intersect with steel beams, ducts, or walls.

-Forensic analysis: A building information model can be easily adapted to graphically illustrate potential failures, leaks, evacuation plans, and so forth.

-Facilities management: Facilities management departments can use it for renovations, space planning, and maintenance operations.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What is clash detection?

A

Individual models are created by each design discipline (M&E, architectural, structural etc.) these models are then combined into a federated model using software. Clash detection is the identification, inspection, and reporting of collisions between elements in a structure’s model: Like a pipe running through a steel beam.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

How is BIM information shared amongst the project team?

A

This information in a BIM model is shared through a mutually accessible online space known as a common data environment (CDE), and the data collected is referred to as an ‘information model’.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is a BEP and how does it relate to the EIRs?

A

The EIRs (Employer’s Information Requirements) is a document prepared by the employer, which clearly defines what information is required during, and more importantly what is required at the end of the project to enable the asset to be managed effectively.

The BEP (BIM Execution Plan) is produced by the professional team in response to the EIRs, detailing how the requirements will be met.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Why might a building be listed?

A

A listed building is one that has which has special architectural interest, adding value to the area and are part of our national heritage.

Listed buildings have statutory protection against demolitions or alterations which could affect their character.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What are the three categories of listing in England and Wales?

A

Grade I buildings are of exceptional interest, only 2.5% of listed buildings are Grade I

Grade II* buildings are particularly important buildings of more than special interest; 5.8% of listed buildings are Grade II*

Grade II buildings are of special interest; 91.7% of all listed buildings are in this class and it is the most likely grade of listing for a homeowner.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What are the three categories of listing in Scotland and Northern Ireland?

A

Scotland - The equivalent categories are Grade A, B and C.
Northern Ireland - the equivalent categories are Grade A, B+, B1 and B2.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is a curtilage listing?

A

‘Curtilage’ is generally used to refer to a parcel of land attached to a building and forming one enclosure with it.

The law provides that buildings and other structures that pre-date July 1948 and are within the curtilage of a listed building, are to be treated as part of the same listing. This means that curtilage-listed structures receive the same level of protection as the principal-listed building.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Do you need consent to make alterations to a listed building?

A

Once a building is listed, consent is normally required for:

-Its demolition, in whole or in part.
-Any works of alteration or extension which would affect its character as a building of special architectural or historic interest.
-Any repair work that could affect the historic character of the building.
-Replacement of historic features, fittings or fabric.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is a conservation area?

A

-A conservation area is an ‘area of special architectural or historic interest, the character or appearance of which it is desirable to preserve or enhance’.

-It is the quality and interest of the area, rather than that of individual buildings that is the prime consideration in identifying conservation areas. Buildings, open spaces and landscape features, including trees, may all contribute to the special character of a conservation area.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is planning permission?

A

Planning permission is the legal process of determining whether proposed developments should be permitted. Responsibility for planning lies with local planning authorities (usually the planning department of the district or borough council).

The process is in place to deter inappropriate developments.

Planning permission is usually required when building a new structure or making extensive changes to
an existing one.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What are planning conditions?

A

Where an application is made for planning permission, the local planning authority may grant planning permission subject to conditions as it thinks fit. When used properly, conditions can enhance the quality and mitigate the adverse effects of the proposed new development.

These conditions might require additional approvals for specific aspects of the development (such as the colour of materials) or might restrict the use of the site (for example limiting operating hours).

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What are reserved matters in planning?

A

Reserved matters are items that are excluded from an outline planning application because they will be determined by future planning approval, or have not yet been developed to a satisfactory degree. If outline approval is given, an applicant has three years to submit a new application to gain approval for the reserved matters left off the previous application.

Reserved matters can include any of the following matters:

-Access: Access to and within the site, circulation routes and how these fit into the
surrounding access network.
-Appearance: Aspects of the building or place that determine its visual impression.
-Landscaping: The treatment of the land to enhance or protect the amenities of the
site and the surrounding area, including screening and tree planting.
-Layout: The height, width and length of the proposed buildings.
-Scale: The height, width and length of the proposed buildings.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What are Section 278 agreements?

A

A Section 278 agreement (or S278) is a section of the Highways Act 1980 that allows developers to enter into a legal agreement with the council to make alterations or improvements to a public highway, as part of a planning application.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

What are Section 106 agreements?

A

A Section 106 (or S106) agreement is a legally binding agreement or “planning obligation” between a local planning authority and developer.

The purpose of a S106 agreement is to mitigate the impact of the development on the local community and infrastructure. The agreement will set out the terms binding on the owners or developer to provide, facilitate or fund the provision of infrastructure, services or other measures that may be needed for the development to be acceptable in planning terms.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

How do you monitor risks throughout the lifecycle of your project?

A

As project manager, I continually identify, analyse and monitor risks at regular intervals and at significant project milestones. As environments, stakeholders, and even requirements change, the nature of risks and planned responses should change too. Risk monitoring involves:

Identifying new risks.
Taking corrective action when a risk materialises.
Monitoring the actions of each risk owner to ensure the mitigation strategy is deployed.
Measuring the effectiveness of risk responses.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

Once project risks have been identified, how would you go about allocating risks to a specific ‘owner’?

A

Risks are usually allocated to the individual or party best able to manage it. The allocation should be clearly identified on the risk register.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

What are the four risk categories identified in NRM (New Rules of Measurement) for cost estimating purposes?

A

Employer Change Risk.
Employer Other Risk.
Design Development Risk.
Construction Risk.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

What is a risk allowance?

A

A monetary allowance set aside on the risk register to cover costs should the risk be realised.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

How would you calculate your risk allowances?

A

Order of cost estimate stage - At this stage, a simple percentage is likely to be allocated to each risk (unless detailed information is available).

Cost plan stage - Each risk allowance should be assessed based on the total cost of the risk (should it be realised) and the probability of it occurring.

23
Q

What is CSR?

A

Corporate Social Responsibility (CSR) is about the impact that an organisation makes on society, the environment and the economy.

The aim of CSR is to promote ethical and sustainable activity, as well as generating goodwill and a positive reputation. The overarching purpose of CSR is to give back to the community, to take part in charitable causes, and to provide positive social value.

24
Q

How can construction companies incorporate CSR into usual business activity?

A

Supporting education programmes and apprenticeships.
Supporting local community groups.
Good design and construction of community spaces, such as lighting, cycle paths, landscape etc.
Flexible working for employees.
Work from home plans, gym memberships, subsidised public transport and other employee benefits.

25
If you were to be asked to consult on acceleration of a product what could you do as a QS in fees
Under RICS guidance it is a supplementary service and therefore can charge more fee.
26
If a Client requested formally for the Contractor to accelerate the project what could they do?
Either provide an acceleration quotation or explain why it would be impractical to achieve an earlier completion date.
27
what would the contractor include in a Acceleration quotation?
Time which could be saved, Adjustment to the Contract sum Direct Costs Loss and expense and QS / prep of quotation costs
28
if there is no mention of a clause within the original contract can this be added after it is signed?
Yes, under contract law items can be added or removed from a contract as long as both parties are agreed.
29
do contractors have to deliver the project on time, is there contractual basis
the Contract has to "constantly use their best endeavours to prevent delay, however caused, and to prevent the completion being delayed further or further delayed beyond the relevant completion date" therefore they have to ensure that they do not purposely delay the project.
30
how can contractors accelerate works?
Increase working people on site Increase working hours change the temp works programme and sequencing Methods of working
31
How can Employers accelerate works
Reducing the Spec simplifying the design the work scope and conditions of working
32
what could affect a contractor increasing the amount of working hours on a project?
The local council and their conditions of the project planning, especially if it is in a high residential area, this under the control of pollution act 1974
33
if you increase the amount of people on site what are some of the impacts beyond increased productivity?
Welfare requirements Materials required management potential for conflict between trades
34
if accelerating the works and an item is omitted from the contractors scope are they still entitled to profit on that scope?
Yes, they are because it was part of their original tendered price
35
if considering acceleration what questions should be asked
Does the contract allow for it? is a seperate agreement needed how can it be achieved is the activity on the critical path what is the total cost what costs would be saved? how would you price the risk are the contractor to warrant and earlier date if it fails what are the next steps?
36
What is corporate recovery?
the process and actions taken to bring an ailing company back to full health: can involve provision of financial, restructering, accounts and legal advice by qualified professionals
37
what is the definition of insolvent?
when a company is not in a position to be able to pay its debts or unable to pay when they are due. this can be evidenced by failing to pay creditiors such as HMRC or when a creditor takes legal action to recover debts.
38
What is a release agreement
a document which details the terms of the termination of the contract, with the duties and responsibilities, these are used to avoid any doubt about the termination.
39
can you deal with insolvency?
as a chartered surveyor, i can advise on the impacts of insolvency and deal with the outcomes; however, I would need to be an authorized insolvency practitioner to be able to act directly as a liquidator, supervisor, or administrator.
40
What are the types of insolvency.
1. Company voluntary arrangements 2. Administration 3. Winding up of the party/company or compulsory liquidation 4. Administrative receivership (or receivership) 5. Voluntary liquidation
41
What is a CVA?
Company Voluntary Arrangements, when a company is approaching insolvency, and they appoint a person to negotiate a settlement with the creditors generally less than the total debt.
42
What is administration?
when a company which is insolvent is allowed to continue to operate with revenue protected, to retain market price which are then used to pay the creditors, this method is often to produce a higher return to the creditors of the insolvent company
43
What is winding up/ Compulsory liquidation?
when an creditor of an insolvent company instigates liquidation and takes responsibility for providing funds to the other creditors.
44
what is administrative receivership?
when a company breaches the terms of its borrowing agreement, and the creditor appoints an administrative receiver
45
what is voluntary liquidation?
when the directors of a company agree that the company has too many debts to be able to pay back and appoint a liquidator to realise the company assets for distribution, this as a consequence the company ceases to trade.
46
what is the role of the QS with insolvency?
with insolvency a QS can aid with measurement, financial costings, procurement/retendering, claims, payments and valuations.
47
What are the potential signs of insolvency?
1. Work on site lacks progress 2. applications are grossly overvalued 3. Unexpected claims for additional payments 4. Materials and plant are not ordered for works 5. labour resources are not sufficient 6. word of mouth/verbal evidence 7. Count Court Judgements (CCJs) 8. Reference to Companies House
48
What are the two types of termination?
Contractual and non-contractual
49
What are the contractual termination names?
Termination at will and breach
50
what are the types of non-contraction termination?
Repudiation frustration Expiration vitiation
51
What are the types of formal insolvencies
administrative receivership bankruptcy CVA Creditors voluntary liquidation members voluntary liquidation Winding up Liquidation
52
What are step-in rights?
Step-in rights may be contained within a collateral warranty, whereby the third party may step in and assume the role of the insolvent party.
53
What bonds are often associated with insolvency
Performance bond retention bond