HVAC Rough Flashcards
(45 cards)
The air handler and/or gas furnace in the attic is to be hung ________, _____________, and secured from all four corners of the unit to the top chord of the trusses.
plumb, level,
The air handler is to be completely sealed to the ___________ to eliminate any air intake from the attic, walls, or garage.
plenum/platform
The plenum is to be completely sealed to the air handler using a _________ type product.
mastic
The air handler panel door is to be installed using __________ clips or ___________. (No tape).
- plastic
- screws
Line sets at the air handler are to be completely sealed to the unit using a ________ __________.(No cork tape).
silver tape
All unused openings on the air handler are to be plugged with a _________ type or ____________ plug. (No tape).
- plastic
- approved
Condensate lines to slope min. _______” per foot away from pan (no reverse fall, humps, or bellies).
1/8”
Primary condensate line installed on the exterior of the home approximately ______”- _____” AFF, extend _______”-_________” past the stucco with a 90° elbow at the end.
- 6” - 8”
- 2” - 3”
Secondary condensate line to terminate above a clear __________ (no obscure or glass block), extend past the pop out with a 90° elbow at the end.
window
Run all ______________ lines separately.
condensation
Condensate lines are to be run ____________ in the middle of the stud.
vertically
No pipe __________ is to be left on any exposed concrete.
glue
The condensate pan should slope _____” per foot.
1/4”
What is the tolerance for construction material, or debris in the pan?
No tolerance
All metal to metal duct connections are to be sealed with an approved ___________ type product to prevent air leaks.
mastic
Flex duct is to be kept a min. of ______” from the roof sheeting.
2”
Flex duct is to be secured every _____’.
4’
Flex duct must retain ______% of the diameter of the duct.
80%
Furnace flue pipes are to extend _____”-_______” above the roof tile to the bottom of the flue cap
12” - 24”
Flue pipes above the roof line are to be plumb within a _____” per foot.
1/4”
All furnace flue pipes and hot water heater B-vents are to have _________ collars.
storm
All hood, dryer, and exhaust vents that terminate on an exterior wall are to be plumb & level. What is the tolerance?
No tolerance
A sheet metal (insulation) barrier is to be installed around all hot water heater _________ pipes. The sheet metal barrier is to be approx. __________” in height and is to maintain a min. _______” clearance from any combustible material.
- flue
- 24”
- 1”
A ________” tall, sheet metal dryer box is to be installed directly on the bottom plate at all ________ locations.
- 24”
- dryer