Tell me about when you have prepared a detailed Building Survey report
for a client containing detailed information, conclusions and
recommendations.
I recently prepared a building survey report on a water damaged ground floor property within a block of flats. I was instructed to comment on the damage, determine a cause and make recommendations for remedial works. I included detailed nifromation on the construction of the property, cavity walls, dry lined, no insulation or foil, concrete floors. I concluded that damp was primarily coming from the leaking bathroom fittings but also condensation. I recommended that all of the bathroom fittings, floor covering and dry lining be removed and the substrate allowed to dry. I also recommended that a intrusive investigation of the cavity is completed to assess damage to wall ties and also to understand potential for CWI.
Prestwick Road Subsidence
What advice did you give to your client?
I advised the client that the approach suggested by the loss adjuster to repair the superstructure of the building only solving the immediate problems was concerning. I advised that further investigations should be completed to make a concerted effort for a claim to remove more of the trees. I also suggested that the resident should be removed from the property and a schedule of repairs should be developed to present to the loss adjuster.
Prestwick Road Subsidence
What were the recommendations you made regarding remedial work internally and externally.
Internally I recommended that existing poorly filled cracks with cement are removed. The cracks would then need to be repaired appropriately and decorations completed inside. Externally we recommended that the property was underpinned the full length of the wall that was being affected by subsidence.
Prestwick Road Subsidence
What made you consider it was subsidence
Previous reports were compelted by other surveyors which concluded that the damage was caused by shrinkage. From site there were significant BRE Cat 3 cracks that had opened up, with some doors not fitting within frames. From a desktop study, monitroing had shown further movmeent during summer months, this cyclical movement removed possibility of drainage issues. There was also a trial pit report where tree roots were found in the soil.
Prestwick Road Subsidence
What did you advise about the potential for damage after tree removal?
If more of the trees were removed to the rear of the property this could result in heave as moisture would not be removed from the ground from the trees, this can take several years. To avoid the potential damage of heave, the underpinning should be installe dto more than 2m.
Emma Rothschild Condition Report
What was the life expectancy for the roof covering compared to the photovoltaic panels
The remaining life expectancy of the concrete roof tile covering was approximately 30 years. Photovoltaic panels have a life expectancy of 40 to 50 years. However, we advised that by the end of the life expectancy of roof covering the technology of the panels would likely be obsolete/redundant and the panels could be renewed at teh same time.
Emma Rothschild Condition Report
What were the significant details founds?
The defects found on the roof were all related to mainteance i.e. cracked or slipped concrete tiles. There was a poorly installed boiler flue which had penetrated the underfelt and not patched repaired. We recommended that a pacth repair was conducted.
Emma Rothschild Condition Report
What was your advice to the client about the roof covering.
I advised that the roof covering had approximately 30 years of life expectancy remaining. There were no significant defects other than maintenance issues. There was also evidence of any issues a being addressed through the maintenance.
Cladding Surveys, London
What RICS guidance did you follow?
Before undertaking my surveys I reivewed the cladding for surveyors supplementary guidance.
Carlton Vale Estate condition survey
What defects did you look for in the concrete frame?
I was looking for cracking and any spalling that may be related to carbonation of the steel reinforcement.
Carlton Vale Estate condition survey?
Did you consider the use of HAC in the building?
The buildings of the estate are of the correct age for the concrete frame to be of HAC. However, when asking for the pre-survey information from the client it included test reports indicating the concrete was not HAC.
Carlton Vae Estate condition survey
What deleterious materials did you find
Considering the age of the property I was looking out for potential ACM. The reports provided by the client did however confirmed no presence.
Carlton Vale Estate condition survey
How did you deal with inaccessible areas during your survey?
I comminicated the client before the survey to ensure that I was able to gain access on to all of the roofs of each of the blocks. I inspected the condition of gable walls and rear elevations from ground floor level with binoculars. When reporting on the condition of windows and doors, I included a discalimer in my report that my recommendations were based on a sample of flats that I gained entry into.
Carlton Vale Estate condition survey
When inspecting the flats what additional legislation did you need to take into considetration that did not apply to the communal areas
During my inspection of the flats I was sure to consider S11 of the landlord and tennant act to ensure the structure of the property was maintained and that no water was penetrating the property. I was also careful to check if all homes were fit for habitation.
Carlton Vale Estate condition survey
Did you make any recommendations to your client about the inspection of elements above ground level.
Yes, I did make recommendations for the refurbishment of the steel double glazed windows. From my inspections of a sample of flats I found that the double glazing seals had been comproimsed throughout. I recommended that a full survey of all windows should be completed to determine the level of refurbishment and potential replacement required. I also recommended the replacement of some of the flat roof covering due to issues with leaking, I also included in my recommednation for the introduction of isnulation to meet building regulatiosn and also to aid in energy perfroamcne and condesnation within the property.
Carlton Vale Estate condition survey
How has the verdict of Ryb V Conway Chartered Surveyors altered what you inspect when surveying a property?
The result of the case has not altered what I survey during a property but has reitterated to me the requirement to be thorough when completing my inspections and ensure that my CPD and training is inkeeping with current market trends and the tasks I am completing.
What is a dilapidation survey?
Dilapidation refers to a property falling into disrepair
A dilapidation survey is usually carried out at start or end of tenancy
Involves the recording of the condition of the property
Surveyor will compare the condition of the property with the details of the tenancy agrement and advise on any potential breaches of agreement
The survey should also provide, where relevant, quantiteis of repair required and method
What is a scott schedule?
Document included alleged breaches of tennancy
Cost of remedy works
Defendants comment on tehe costs
Defendant can provide estimate cost
Dispute can be decided by a judge
What are the contracted and implied covenants in a tenancy agreement?
Express or contracted items are included within the contract. Implied terms are not included in the tenancy but implied by law.
What were the 2018 ammendments to Approved Document B?
Following Hackitt review of guidance due to Grenfell. The us of plain English in approved docuemtn B. Properties over 18m that have rooms of residency should only have materials of limited combustibility, minimum euroclass A2. An assessment of extenral wall system should not be used in lieu of on site testing.
Cladding Surveys, London
What do you mean approved document B height?
Checkin ghte hight of property is under 18m. This is from the first floor to top of ceiling. This would determine the classification of risk in the building.
Cladding Surveys, London
What were the materials you were most concerned to find on your inspections?
External wall insulation
Aluminium composite materials
High pressure laminates
These materials all had a high chance of becoming combustible?
Cladding Surveys, London
What was the process of completing the cladding surveys to fulfill the requirements of the approved document B ammendment?
Phase 1 report to determine height and external materials
Provided to fire engeineer for review
Phase 2 report of on site testing was required due to material classification or building height
Phase 3 report from fire engineer if ESW1 option A could not be awarded.
Cladding Surveys, London
How did you identify areas fro intrusive inspections?
The primary reason for the survyes was to determine the external wall system suitability. This meant locating compartment lines, horizontally and vertically. Areas requiring closure i.e. around windows also needed to be determined.