Instructions, Variations & Quotations Flashcards

1
Q

What are variations

A

Additions, omissions and substitutions enacted through an instruction

Priced by measuring changed work then applying existing rates and prices from the contractors tender

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What are changes

A

Changes to scope, key dates and completion date

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

How does NEC4 approach claims

A

NEC4 does not have claims (retrospective recovery of loss and expense)

CE’s are used instead, most of which try to avoid a problem or minimise it’s impact, thereby minimising dispute likelihood

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Three traditional contract processes

A

Variations/changes

EoT’s

Loss and expense

NEC4 combines 2 & 3 into compensation events

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What are CE’s

A

No contractual definition

An event which is the clients risk, and if it occurs, affects the contractor, entitles the contractor to be compensated for any effect on the Prices, and the Key Dates and the Completion Date

They are listed in the contract (29 maximum dependent on secondary options)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

How does change quantification differ between NEC4 and traditional contracts

A

Trad. - variation priced on account to be settled at final account (can lead to more disputes and loss of control given time period between FA and variation occurrence(s))

NEC4 - CE’s assessed as they happen, including continual assessment of the Prices, delay costs, disruption costs and delays to Key Dates and Completion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Example CE’s

A

Scope change

Client does not provide something on time

Searching for absent defect

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

How are CE notifications addressed in NEC4

A

PM notifies Contractor when they create a CE

Contractor to notify PM of CE if the contractor believes the event is a CE and the PM has not already informed them

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

How are quotations addressed in NEC4

A

Contractor can be instructed by PM to prepare quotations for several way to deal with a CE

PM selects most advantageous to the client in terms of time and money

Quotations are offers that are accepted or rejected

How well did you know this?
1
Not at all
2
3
4
5
Perfectly