Introduction Flashcards

(229 cards)

1
Q

What does Prince2 stand for?

A

Projects In Controlled Environments

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

What have the 3 main revisions of Prince2 been?

A

1975 - Promtpt
1989 - Prince (focus on IT projects)
1996 - Prince2 (suitable for all projects regardless of size and environment)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What are the 4 integrated elements of Prince2?

A

7 Themes - Ingredients
7 Processes - Instructions
7 Principles - Good practises/Why
Project Environment - Tailoring

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

What are the 3 core management products within Prince2?

A

Baseline products - e.g business case, PMP
Records - logs, register, configuration records
Reports - Prince2 recommended reports

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What’s the difference between projects and BAU?

A
Projects:
Bring change
Higher risk
Project life cycle
Six major variables
Deliver products
BAU:
Repetitive 
Easy to f/c
Easy to improve efficiences
Low risk
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What is Prince2 definition of a project?

A

A temporary organisation that is created for the purpose of delivering one or more business products according to an agreed business case

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What are the 7 themes?

A

Business case:
Justifies project, documents project f/c benefits.

Organisation:
Roles & responsibilities, accountability

Plans:
Project, stage and team plans.

Risk:
How to manage risks

Quality:
Quality approach
Meet requirements, standards

Change:
How to manage change

Progress:
Monitor & controlling the project successfully

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

List the 7 themes of Prince2

A
Business case
Organisation
Plans
Risk
Quality
Change
Progress
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

What are the 7 processes?

A
Starting up a project (SU)
Directing a Project (DP)
Initiating a Project (IP)
Controlling a Stage (CS)
Managing Product Delivery (MPD)
Managing a Stage Boundary (SB)
Closing Project (CP)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

What is SU?

A

Starting up a project (SU):
Should the project go ahead? Viable?
Triggered by project mandate.
Project brief is outputted

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What is DP?

A
Directing a Project (DP):
Analysis of project brief undertaken
Used to make decisions about the projects future
Used throughout lifecycle 
Project Board has exclusive access
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

What is IP?

A

Initiating Project (IP):
Detailed analyis of whole project undertaken to answer:
Who, what, when, where, why, how much etc.
Project Initiation Document is outputted from this process.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What is the PID?

A

Project Initiation Document:
Prince2 version of the PMP
Collection of all key documents required to manage the project
Reviewed by project board in DP (directing project) to ensure viability
Requires approval before project can progress

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

What is CS?

A

Controlling a stage (CS):
PM uses this stage to allocate work
Work allocated in work packages
Corrective action taken where required
Progress reported on
PM provides highlight reports to the project board via the DP theme
Captures and deals with risks/issues/changes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What is MPD?

A

Managing Product Delivery (MP)
Accept work from the PM
Complete work
Handback to PM once completed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

What is SB?

A

Managing a Stage Boundary:
When the end of a stage is nearing
Requires planning of the next stage
Progress of the current stage should be reported to the project board
Project board need to approve plan for next stage and the end of stage report.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

What are the two reports used to report progress between the PM/Project Board?

A

Highlight Report

End of Stage Report

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

What 3 processes are repeated until project closure?

A

CS (Controlling Stage)
MPD (Managing Product Delivery)
Managing a Stage Boundary (SB)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

What is CP?

A

Closing Project (CP)
Formally handover the products
Review the project and how it was managed
Review performance
Project Board have to authorise project closure

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

What are the 7 principles?

A
Continued Business Justification
Learn From Experience
Defined Roles & Responsibilities 
Manage By Stages
Manage By Exception
Focus on Products
Tailoring
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

What does the continued business justification principle refer to?

A

Must be a valid business case to justify project
Must remain valid throughout the project
Should be reviewed regularly

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

What does LFE mean?

A
Learn From Experience
Emphasise good practise
Avoid bad practises
Continually improve
Become more mature
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

What is the roles and repsonsibilities principle?

A

Who’s doing what

Accountability

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

What is the principle of managing by stages?

A
Doing work to progress the project then reviewing the work/progress
May be at predetermined stages
May follow the project life cycle
Undertaken by project board
Go / No go decision made
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
What is managing by exception (principle?
Project board only meeting at the end of each stage to give authority to proceed Set tolerance for next stage which the project can act within Only meeting at predetermined stages unless there is an emergency etc.
26
What are tolerances?
Permissable deviation from the plan that is allowed before it needs to be escalated
27
What is the focus on products principle?
Discuss what products to build Standard at which they're to be built Embodied in product based planning technique, plans and quality themes
28
What is the tailoring principle and what does it ensure?
Being aware of the project context, environment and size Tailoring Prince2 to meet the project needs Ensures the right level of governance, planning and control IAW prince2 is implemented on the project given its nature.
29
What can tailoring be applied to?
Processes - combined or adapted Themes - Applied using appropriate techniques Roles - Combined or split in a way to ensure accountability and prevent conflicts of interest Management Products - Combined or split into any number of elements Terminology - Changed to suit other standards or policies
30
What is the PM responsible for in relation to tailoring?
Responsible for idenitfying the level of tailoring required and how it will be implemented on the project. PM should then document this in the PID (Project Initiation Document), control section. This then requires approval from the project board.
31
Who may support/advise the tailoring of the project?
PM/Project Board may take advice from: Project assurance Project support Team managers Centre of excellence
32
What are the 6 variables of a project that require management?
``` Timescales Costs Quality Scope Benefits Risks ```
33
In relation to the theme, organisation, what does prince2 assume is the structure / who are the mains stakeholder representatives?
Customer supplier environment | Customer & supplier
34
What is the method and what viewpoint is it written from?
Outlines how the project will be delivered. | Written from customer view point.
35
What is the customer and what is their view on the project?
Persons/Organisation who fund the projcet. Business and user perspective Focuses on value for money and the realisation of benefits
36
What is the user and what are their priorities?
User is: Concerned with quality and functionality of the products Will be using the project outputs or maintaining products
37
What is the supplier & what view do they provide on a project?
An internal or external person or group that supplies skills or products. Focus on supplier aspect.
38
What are the four levels of management?
Corporate / programme management or customer ``` Project Board (Directing) Project Manager (Managing) Team Manager (Delivering) ```
39
What are the corporate / programme mgt or customer responsible for?
Provide the project mandate Appoint the project executives Set project tolerances
40
What is the project board & their responsibilities?
``` Make decisions r.e the project Provide strategic direction Report to the customer/organisation 3 key roles within the project board: Executive (sponsor) Senior user (represents users) Senior Supplier (represents supplier/s) ```
41
What is the project manager & their responsibilities?
Managing the project on day-to-day basis | Ensure the project produces the required products
42
What is the team manager & their responsibilities?
Executes assigned work packages | Builds and delivers required products
43
With reference to the project board, what is the executive?
AKA the sponsor Accountable for the project being a success Represents the business Owns the business case Responsible for funding Focus on business strategy and benefits realisation
44
With reference to the project board, what is senior user?
Represents those who use the products Ensure user needs are specified and met Ensure the user can realise the benefits Concerned with quality and functionality
45
With reference to the project board, what is senior supplier?
Represents the internal/external suppliers providing skills or products required for the project.
46
What are the project board collectively responsible for / expected to do?
Monitor risks Authority to commit and manage resources Make decisions using the DP (directing project) process to guide the team.
47
When do the board meet?
At the end of each project stages to make decisions r.e progress and viability. Apart from this, they meet by exception. Rely on highlight reports from the PM
48
The project board need to be confident that?
The project manager is in control | Project is progressing as expected/reported
49
With relation to project assurance, what are the project boards responsibilities?
Executive: Focus on risk and finance assurance Senior User: Ensures products meet user requirements. Senior Supplier: Ensures suppliers are following quality standards Ensures product descriptions are correct
50
Can the project boards assurance responsibilities be delegated? If so, who can this role be delegated to?
Yes: It can be delegated however, it cant be delegated to the PM, project team or team managers. If delegated, highlight reports should be used to provide confidence to the project board.
51
What are the PMs main responsibilities?
Plan the project and the stages within it Allocate work packages Monitor progress using checkpoint reports Take corrective action where required Report progress using highlight reports Prepare benefits management approach
52
What are the team managers main responsibilities?
Takes direction from PM Agrees work packages with the PM Reports progress via checkpoint reports
53
What are the project teams main responsibilities?
Managing registers and logs Collating and analysing data Updating the schedule and plans May also include procurement, finance and configuration support. Role may not be required and may be undertaken by PM
54
What is the change authority and what is their main responsibilities?
Decide whether change requests are implemented or not Accept / Reject / Defer changes Assess changes Usually the project board is responsible however this may be delegated or there is a separate group of people responsible for change.
55
How may the project board roles be merged?
Executive: Executive Senior user Assurance Project Manager: PM Project Team Team managers Senior Supplier: Project Assurance Suppliers
56
What are the three primary stakeholder interests?
User Business Supplier
57
What is a stakeholder?
individual, group or organisaiton that can be effected by or effect or perceive to be effected by a project and its activities.
58
When are stakeholders identified and analysed?
Start Up (SU) and Intiation of the project (IP)
59
Whena are stakeholders engaged?
Throughout the project life cycle.
60
What does the communication management strategy define?
Defines means and frequency of communications.
61
What 3 things must the project do to be a Prince2 project relating to organisations & structures.
Define organisation structure and roles Document rules for delegates and change authority Define approach to engaging and communicating with stakeholders.
62
What are the two organisational products/documents required?
PID - project initiation document | Communications management approach
63
Which role makes sure the right people are involved?
Project assurance
64
How does Prince2 define the business case?
The BC establishes mechanism to judge whether the project is (and remains) viable, achieveable and desireable to support decision making in its investment.
65
When referring to the business case, what does desirable mean?
Examing cost beenfit balance Benefits should outweigh costs and risks Taking account of risks
66
When referring to the business case, what does viable mean?
Satisfied and confident that the products/scope required can actually be produced.
67
When referring to the business case, what does achieveable mean?
Satisfied that the products produced will achieve the expected benefits.
68
When is the business case produced / developed?
``` During the pre project / intiation stages of the project life cycle Done during the following processes: SU = Starting Up the project DP = Directing the Project IP = Initiating the Project ```
69
Is the business case included in the project brief? If so, what does this allow?
Yes This allows the project board to have a clear understanding on the reasoning and business option to progress the project.
70
When is the business case refined after it has initially been accepted?
Initiation Stage / IP (Initiating Project) Business case is refined using the information from the Proejct Plan which is then formed apart of the PID (project intiaition document)
71
At what other points in the project life cycle is the business case reviewed and updated? What is updated?
End stage assessments are done by the project board to ensure the Business Case remains viable At the end of each project stage the business case is also updated to reflect the most accurate information r.e costs, schedule, risks etc.
72
What if the business case is invalid or becomes invalid during the project?
The project should be stopped
73
When are the business case f/c benefits reviewed?
These are reviewed apart of the benefits management approach where a comparison of actual benefits realised are made in comparison to what was outlined in the business case.
74
What are outputs?
Outputs are the product/deliverables of the project
75
What are outcomes?
The result of the change that the project outputs bring.
76
What are benefits?
The tangible or intangible measurement at which the project brings to the business.
77
When referring to the business case, what does desirable mean?
At an end stage assessments
78
List and explain the 9 contents within the business case?
Executive Summary - Provides a summary to senior management on the project Reasons - Describes problem trying to solve or the new opportunity. Describes the current situation. Options - Do nothing, Minimum, Maximum. Analysis and recommendation provided. Benefits - Expected benefits to result from executing the project. Disbenefits - Bad things that might happen as a result of the project Timescales - Duration of project, how long it will take to realise benefits. Cost - Total costs of running project, operational and maintenance costs. Funding arrangements Investment Apprailsal - How VFM is achieved, financial appraisals of each option Major Risks - Major risks impacting business case. High probability and impact, red risks.
79
What is the benefits management approach and when is it produced?
Produced in the IP process | Decribes how benefits will be benchmarked and measure benefits, analyse progress, document and f/c benefits.
80
What are the 4 aspects a projcet must follow to be a Prince2 project?
Create and maintain a business justification for the project, usually a business case Review and update the business justification throughout the project Define the management actions necessary to create the outcomes and realize the benefits and Define and document the roles and responsibilities for the business case and benefits management approach.
81
In a customer/supplier environment, who has a busienss case?
Both the supplier and the customer. Supplier - Justifies their involvement in the project Customer - Justifies the reasoning and need for the project
82
Who owns the business case and which is most important?
Project Executive owns the customers business case which is the basis of the project and drives decision making.
83
What is the Prince2 definition of plans?
A document describing how, when and by who a specific or set of targets will be achieved. Targets refer to the projects products, baselines, timescales, costs, quality and benefits.
84
What is the Prince2 purpose of plans?
The facilitation of communications and control by defining means of delivering products (who, what, when, where, why, how, how much).
85
What are the 4 levels of the project organisation/
Customer/Organisation Project Board Project Manager Team Manager
86
What is the first plan to be produced on a project?
Initiation plan Developed in the SU (starting up) process Brief and high level Shows key dates and brief activities
87
What plans do the project board require?
Project Plan and/or Programme plan if applicable. | This will outline key activities, critical path and milestones on the project.
88
What plans do the PM require?
Stage Plans (Delivery) Provide more detail to allow the PM to manage the project day to day. Timescales, resource requirements, costs, critical path etc.
89
What plans do the team managers require?
Team Plan Provide further detail than the stage plans. Provide more detail r.e work packages etc.
90
What is the exception plan?
Something managed and requested by exception and requested by the project board if the project is exceeding initial plans and tolerances. Project board requests, PM produces.
91
What is the Project Plan, when is it created and updated? | How does the project plan relate to schedules?
Provides an overview of the entire project Produced in the initiation of the project (IP) process. Part of the Project Plan is schedules and key decision points are identified in the plan. This is then used to define stage boundaries. Updated at the end of stages
92
How does the business case relate to the plan?
Business case is updated to reflect costs and timescales as documented in the plans.
93
Whats the difference between the project plan and the stage plan?
Project plan provides an overall plan across the project life cycle (Pre Project, Initiation, Delivery, Final Stage Delivery, Post - Project. Stage plans focus on the Delivery stage primarily and provide plans for activities within this stage. Stage plans produced at the end of each stage whereas project plan is produced during the project initiation.
94
What are stage plans for?
Used to monitor and control daily activities in the stage.. Developed in the managing a stage boundary process (MSB)
95
What are team plans?
Produced by team manager. Helps accept and manage work packages Developed and produced in the Accepting Work Packages / Managing Product Delivery (MPD) processes. Required on complex projects but optional.
96
What are exception plans?
Requested by the project board when tolerances are exceeded on either the team or stage plans. Outcomes of the exception plans may be that the project is terminated however, more likely the baselines and plans are just updated using the exception plan.. More information might be requested Requires approval by project board through an exception assessment. Once approved, this becomes the new baseline.
97
What if the project plan requires an exception plan?
Same process as the exception plans used for stage and team plans however, the exception plan for the project plan will be escalated to the customer or organisation for approval.
98
What are the 7 steps required in a prince2 plan (used for project, stage and team plans)
1. Design Plan - What type of plan will be used, how much detail required, estimating techniques. Produced during initiation stage. 2. Define & analyse products - PBS, prioritise, list products to be produced. 3. Identify activities & dependencies - Create network diagram. 4. Prepare Estimates - Duration & Cost 5. Prepare Schedule - Resource requirements and usage 6. Document Plan - Describe plan and produce formal baseline. 7. Analyse Risks - Take into account of risks and continually assess throughout project.
99
Why do we have different levels of Plan?
Reflect the needs of different levels of management involved at the project, stage and team levels.
100
What plans do exception plans replace?
Project & Stage Not team plans because they're optional
101
How does planning help provide the basis for project controlling and monitoring?
By providing a realistic and achievable plan
102
What are the 6 management stages a project schedule will need to be split into?
``` Pre Project Initiation Delivery Final Delivery Post Project ```
103
Where does the project board need to make decisions?
After significant development or achievements Before major investments or commitments These are known as decision points and typically take place at the end of each stage within the lief cycle to provide a no/go decision.
104
Why are stages beneficial in monitoring and controlling a project?
Provides control to the project board as the project cannot progress without their decision.
105
What is the difficulty when determining stage boundaries?
Their relationship with the projects delivery steps. Usually delivery steps and stage boundaries overlap so stage boundaries must be inserted part way through a delivery step. Delivery steps are recommended to split into two or more parts.
106
What are project delivery steps?
``` Use of specialist skills during the project relating to: Specification Design Build Test Commissioning ``` Delivery steps are recommended to split into two or more parts. Best practise to control projects: High risk projects - Establishing frequent and shorter management stages. Low risk projects - Fewer and longer management stages
107
What are the four Prince2 products that require maintenance?
The project product description Product descriptions A product breakdown structure And a plan.
108
A project plan must have the following in order to be classed as Prince2: (7)
Make sure the plans enable the business case to be realised Have at least two stages, initiation and one further management stage Have a project plan for the whole project and a stage plan for each stage Use the product based planning technique Produce plans for managing exceptions as needed Define the roles and responsibilities for planning And use any lessons from previous projects to inform planning.
109
What is product based planning?
Process of being able to identify what products are needed, what the specs are and what work is required to produce these products.
110
What are the 4 stages to product based planning?
1. Project Product Description - Defines the project and its main components. Completed during the Stating Up a Project (SUP). Defines the scope. 2. Product Breakdown Structure (PBS) - Hierarchical breakdown structure of all products the project will produce and how they relate to each other. 3. Product Description - Defines each product and its requirements/features. 4. Product Flow Diagram (PFD) - In what order products will be produced.
111
What are grouping products?
``` Categorising the products that will be produced to make it easier to identify further products. E.g when building a house, the grouping products might be: Raw materials Electrics Plumbing Units Etc ``` Grouping products aren't products, they act as headings to identify products.
112
What is an external product?
Something that has already been produced which wasnt initially included within the scope of the plan. Products produced that are external from the plan and scope.
113
What is a PFD?
Product Flow Diagram Shows the order in which products are created and the relationship between them The last product on the PFD is the top product on the PBS. Typically, the design comes first within the PFD.
114
What is quality?
Degree to which a set of inherent characteristic, product, service, process, person, organisation, system or resource fulfils its requirements. Fit for purpose.
115
What is the purpose of quality?
Define and implement the means by which the project will create and verify products that are fit for purpose.
116
Should quality be measurable?
Yes – have to be able to quantify the quality of products. E.g a new office must be warm. A new office must be able to reach 37 degrees.
117
What is acceptance criteria?
Whether the requirements and measurable quality statements have been met. If so, this meets the acceptance criteria and is fit for purpose.
118
What is quality criteria?
An individual products characteristics and requirements that need to be met.
119
What does prince2 quality approach ensure?
It ensures the products meet business expectations and enable the business benefits to be achieved
120
Define quality management
The co-ordinated activities to direct and control an organisation with regard to quality.
121
Whats the difference between Quality Control and Quality Assurance?
QC = Ensuring products are built to specification, requirements, standards and criteria as stated in the product description to meet their quality criteria. Walk through, inspections/measurement, test equipment, control charts.
122
What is the role of project assurance with regards to quality?
To ensure the project is managed properly and that the appropriate checks are undertaken.
123
What is quality planning and why is it important?
Quality planning involves defining the projects products, quality criteria, quality methods, effort required, product approval and quality responsibilities. Ensures;Obtain approval from the project board on the overall approach to quality Communicate these agreements to all stakeholders Establish effective baseline for quality
124
What are the 9 quality management approaches that require defining in order for the project to follow Prince2 practises?
# Define approach to quality control Define approach to quality assurance How quality is communicated throughout the lifecycle Define roles and responsibilities Specify quality criteria for project products Maintain Records Specify customer quality expectations Prioritise acceptance criteria Use LFE to inform quality planning
125
What are the two products that must be created and maintained in relation to quality management?
Quality management approach Quality register
126
When will the PM discuss the requirements with the executive and the senior user to establish the initial scope of the project? Where will these requirements be stored?
During the SU (starting up the project) process. | Requirements will be stored in the project product description (PPD)
127
What is the PPD?
Project Product Description | Document that defines what the project must deliver to gain acceptance.
128
Where is the quality management approach stored / what is it apart of?
PID - project initiation document
129
Whats the purpose of the quality management approach?
Includes specific processes, procedures, techniques, standards and responsibilities which should be applied in the project. Process adopted for quality control key responsibilities, defines the records to be kept and reports to be issued.
130
What is the purpose of a product description?
To understand the nature of the product, its function, appearance, attributes and specifications. Also defines who will use the product (end-user), skills required to build the product and the sources of information or supply for the product. Defines the quality criteria that will be used to judge whether the product is fit for purpose. Defines the quality criteria to assess whether the product is fit for purpose. Defines the quality method (way in which the product will be tested). Quality responsibilities (who the producer, reviewer, approver for the product is).
131
What are the main aspects related to Quality (9)
Quality Control Quality Assurance Quality Criteria Product Description Quality Planning Quality Tolerances Quality Method Quality Responsibilities Quality Register
132
What document is used to record when products will be tested during the build cycle / project life cycle?
The quality management approach will document this. For example, the strategy may state that we check our products at draft, interim and final stages of production.
133
What are the two types of quality checking activities?
In process - regular checks conducted on quality throughout the build cycle Appraisal – relates to the final test at the end of the build cycle
134
What are the three main quality checks/reviews once a product has been built?
Review preparation – Someone tests the product Review meeting – Discuss the results Review follow-up – Problems are resolved, product is re-tested and signed off
135
What are the four main roles associated with quality reviews?
Chair – the person who organises and oversees the process. Checks the product is ready during the review. Reviewer – Person who checks the product against product descriptions. Annotate minor errors of spelling and grammar on the product hence why this technique is aimed at documentation. Presenter – Represents the producer and presents the product for review. Distributes the product and its product description to the reviewers. Administrator – Provides admin support to the chair and records the result and any actions. *Approver – Responsible for providing final approval of the product. However, this is an optional role.
136
What is the main purpose of a quality review?
List the problems and actions required rather than to solve the problems during the review.
137
What are the outcomes / results of the quality review?
Complete – The product is fit for purpose. Conditionally complete – A few minor problems to the product Incomplete – Product requires a complete re-review due to the nature of the problems and their corrections.
138
What is the Prince2 definition of risk?
An uncertain event or set of events that, should it occur, will have an effect on the achievement of objectives.
139
What is the Prince2 definition of risk management?
Systematic application of principles, approaches and processes to the tasks of identifying and assessing risks, planning and implementing risk responses and communicating risk management activities with stakeholders
140
What are the four activities required to ensure risk management is effective? / what is the risk management process?
Identify, capture and describe risks Assess the probability and impact of each risk Plan appropriate risk responses and assign these to people to action and own Implement responses, monitor and control their effect.
141
Why is communication important with regards to risk?
It’s a continuous process required to report the status or risks and LFE Should form apart of all regular and exceptional communications Ensures clarity, awareness and alignment Helps expose opportunities
142
What project process/stage is the risk register created?
IP (initiating project)
143
How are risks assessed?
Probability x impact | PIG chart
144
What is risk proximity?
The forecast on when the risk might occur (timescales)
145
What are the approaches/responses to risks and opportunities?
``` Opportunities: Exploit Enhance Reject Share Contingency ``` ``` Risks: Avoid Accept Reduce Transfer Contingency ```
146
What are the contingency plans?
A plan made in response to a specific risk if it occurs
147
What is the project exposure to risk?
The amount of on-going risks that could occur | The overall impact of these risks if they occur
148
What project documentation is used to report risks?
``` Checkpoint report Highlight report End stage report End project report Lessons report ```
149
What is risk appetite?
A company's attitude towards risks and the amount fo risk an organisation is willing to take on.
150
What is risk tolerance?
acceptable amount to deviate from the projects plans in terms of time and cost without having to escalate it to senior management.
151
For a project to follow prince2, what must it do with regards to risk?
Define risk management approach Maintain risk register Follow risk management approach Use LFE to inform the process
152
What are the 2 documents required/outputted in risk management?
Risk management approach | Risk register
153
What is the purpose of the project progress theme?
To establish mechanisms to monitor, control and compare actual achievements vs what was initially f/c. Forecast project objectives, viability and control deviations.
154
What are the 4 stages in the control loop?
Plan Delegate work Monitor progress Controlling action
155
Why is tolerance needed?
As plans are just estimates | Helps the project progress without escalation all the time
156
What is tolerance cascade?
Defines who sets the levels of tolerance | Describes how deviations are escalated
157
Where are tolerances established/documented?
Project brief SU process Reviewed in IP process
158
What is the programme mgt / corporate / customers role with regards to tolerances?
They set the project tolerances
159
What is the programme project boards role with regards to tolerances?
Discuss tolerance with the PM and its requirements. Help apply tolerances to stages
160
What is the programme PMs role with regards to tolerances?
Work with stage tolerance and allocate tolerance to work packages
161
What is an exception?
A f/c that there will be a deviation beyond the agreed tolerance levels
162
If the following exceptions occurred, who would they be managed by? Work packages Project stages Project
``` W/P = managed by PM Stage = Managed by PM and Project Board Project = Managed by the customer ```
163
Where are project tolerances recorded and documented?
Other tolerances: Project brief & project intiation document (PID) Cost time & scope tolerances: Project plan at stage, team and project level. Risks: Risk mgt approach Quality: Project product description
164
Who owns the project control?
The person who: Receives the report Makes decisions
165
What does the project board control / do?
Auhtorises activities in the DP (directing project) | Gives project board control over changes
166
What information do highlight reports provide?
Information needed to control corrective action
167
What information do end-stage reports provide?
Information needed to authorise the next stage of the project
168
What information do exception reports provide?
Help facilitate decision making by providing info on issues and exceptions.
169
What are checkpoint reports and who provides the information?
Team manager provides the information as per the frequency stated in the work package. Provides info r.e progress to the PM Corrective action can be taken if needed
170
What do highlight and checkpoint reports both have in common?
Time driven | Both report progress
171
What information do log and LFE reports provide?
Info on risks Issues registers Quality registers
172
What is the product status account?
Reports on config items | Status of products in various stages
173
For a project to be prince2 it must:
Describe the approach to monitoring and controlling in PID Have at least 2 management stages Set tolerances to allow management by exception Review business justification Learn and apply lessons throughout
174
What is the purpose of change?
To identify, assess and control any potential and approved changes to baselines.
175
What is a baseline?
Starting point / agreed expectation on one core project constraint i.e cost, time, scope, quality etc. A snapshot of a product at a particular point
176
What is configuration management?
Managing interdependencies between products and individual components to ensure they work as expected and work as expected with other products.
177
What are configuration items?
Products that have been identified that require controlling and baselining
178
Where are configuration items recorded and what does this document provide?
Configuration item record Describes the: Status Version Variant of a configuration item and any details of the important relationship between them.
179
What is a product status report?
Required products can be specified by the identifier or part of the project in which they were developed. An update on their current status i.e revision etc
180
What must a project do with regards to change to be a Prince2 project?
# Define change control approach which covers the issue management process, roles and responsibilities. Define how baselines are created and maintained Maintain some form of issue register & ensure issues are managed Use LFE to inform issue identification and management.
181
What are the issues?
Relevant events that has happened which were not planned and require management action.
182
What are the 3 categories of change?
Request for change: Someone requests that the products do something different than previously designed/thought. Off specification: The product doesn't meet the initial product specification Project board can grant a concession if they accept the defect Problem/Concern: Covers all other aspects of change
183
List and describe the 5 steps in the Prince2 change/issue management process.
1) Capture Determine the issue / change type Determine severity / priority Log request in the register 2) Examine Assess the impact on project objectives, business case, risks and baselines. Seek advice from the project board or change authority Explore the impact on other interrelated products. 3) Propose Identify options Evaluate options Recommend options to change authority/project board What is the impact of the proposed solutions? ``` 4) Decide Request advice Escalate if required Approve, reject or defer Provide issue report which includes the change recommendation. ``` 5) Outcome communicated to relevant stakeholders Plans and records are updated Take corrective action as per request / solution
184
What is the role of the change authority?
Decide the outcome of changes Delegate responsibility if needed Allocate and manage the change budget
185
What's the difference between formal and informal issues?
Informal: If the issues are easy to resolve, the PM can resolve the issue and update the log. Formal: If the issue is serious (change request e.g) it will be dealt with formally. An issue report is prepared and entered into the issue register.
186
Which product provides a full and firm foundation for the initiation of the project?
Project brief
187
What process is triggered by the Project Manager's request to initiate a project?
Directing a Project (DP)
188
Which product gains agreement from the user on the project's scope and requirements
Project Product Description
189
When is the lessons log created?
SU (Starting up a project)
190
Which plan(s) is used by the Project Board as a baseline against which to monitor project progress stage by stage?
Project plan
191
When is the review of the business justification for the project done?
Managing a stage boundary process (MSB)
192
Which role in a Quality Review is responsible for producing a consolidated question list?
The chair
193
Which is an objective of the quality review technique?
Involve key interested parties to promote wider acceptance of the product
194
What is the difference between technical and management stages?
Management stages are sequential but technical stages can overlap
195
Which document is created in outline in Starting up a Project and finalised in Initiating a Project?
Business case
196
Which is the purpose of the Managing Product Delivery process?
Controls the link between the Project Manager and the Team Manager(s)
197
Which product defines how and when a measurement of the achievement of the project's benefits can be made?
Benefits review plan
198
In which document are the acceptance criteria recorded?
Project product description
199
How should a Team Manager escalate a suggestion for an improvement to a product?
Raise an issue
200
What's the difference between the SU and IP process?
SU = starting up a project. This process aims to ensure the project is viable and worthwhile to undertake. IP = Initiating a project. Understands what the scope of work, sets the foundations for the project, identifies initial outputs and benefits, conducts the financial appraisal etc before the project gets the go ahead. A more in-depth analysis than SU
201
What is the project mandate and when is it produced?
Brief, high-level document (depending on whether a feasibility study has been created) Nominates the executive, briefly outlines the project. Produced in the SU process/phase
202
What is the project brief and when is it produced?
More indepth document than the project mandate. Provides info on what tools and techniques will be delivered, how the project will be managed, defines the project, provides further documentation. Produced in the SU phase and replaces the project mandate once produced.
203
What are the 5 different Prince2 recognised tools and techniques?
Records: What info is required, the format of registers logs etc Reporting: Issue report, product status account format Purpose of info, timing and recipients Timing: When something will be done and how often Roles & Responsibilities: Who, RACI, accountable person Scales: Priorities for change Priorities for issues/risks
204
When is the project scope captured and defined?
During the SU stage. Designed to indicate user requirements, skills required to help establish the team Scope may not be fully defined however
205
When are the following produced and what are they: Project product description Outline business case
Project product description: Defines outputs and products that the project will produce. This helps define the scope of work Outline business case: Feasibility of the project, strategic, commercial, management, financial, economic, financial appraisal etc. Both produced during the SU phase / process
206
What are 'lessons' and when are they used in the project?
AKA LFE Used in the SU & IP phases to help plan the project based on historic data Reported and discussed at the end of stages and when the project has been complete Updated throughout the project however
207
What is the project approach?
AKA options appraisal Defines how the options stated in the business case will be delivered
208
What is the first plan produced in a Prince2 project?
Initiation stage plan: Varies depending on project complexity but should give an overview.
209
What questions does the IP stage answer?
``` Who What When Where Why How What if How much How good ```
210
What are the four approaches of PM that the IP stage defines?
Risk (risk/issue register) Quality (Quality plan / log) Change (log / register) Communications management Ultimately defines how they will be managed
211
When is the communications management approach finalised?
After the stakeholder analysis has been complete From this, it allows the team to be refined from the initial SU process
212
Once the approaches have been defined during IP, what plans can be made? What do these plans help define?
``` Gant chart PBS Flow diagram Budget Resources ``` ``` Helps define: Stages Levels of control Frequency of reports Team meetings ```
213
Who produces the benefits management approach and what is it?
PM is responsible to produce Documents information relating to benefits realisation, measurement and timescales
214
What is MSB and what is its main aim?
Managing Stage Boundary Helps assemble PID Helps plan the next stage in the project Helps evaluate current stages
215
What 3 documents / outputs are presented to the project board at the end of the IP stage?
Project INitiation Document Benefits Management Approach Stage Plan
216
What are the main outputs from the SU and IP stages?
SU: Project mandate Which gets replaced by the project brief IP: PID Benefits mgt approach
217
What is the CS process and what are its three areas and what does it aim to do?
CS = Controlling Stage ``` Process managed by the PM Used to assign work & WP Monitor progress of Team managers Deal with issues Report progress to the project board Take corrective action Ensure stage remains within tolerance ``` Grouped into 3 areas: Completing work Monitoring & control Dealing with issues
218
What is the MPD process and what are its main aims?
MP = Managing Product delivery ``` Managed by the team manager Agrees with the PM over what needs to be done Execute work Handover completed work Process links the PM and team manager ```
219
With regard to the CS process, what is the stage plan used for?
Used to plan and agree work packages between the PM and team managers
220
The meeting between the PM and team manager during the CS process defines what?
``` What needs done Quality expectations Time scales Frequency of checkpoint reports How to accept / document when work is done ```
221
What is the process of developing/executing work packages once they've been agreed? (Team manager)
Produce team plan or allocate a work package to the teams The team executes work package Quality checks are undertaken as stated in the quality management approach and plan. The quality register is updated and the product is baselined Team manager provides checkpoint reports to the PM as stated in the WP Team manager signs off the WP and hands over to the PM PM accepts and reviews the quality register and configuration management system
222
What does the PM do once they receive checkpoint reports?
Evaluate progress, take corrective action if needed. Reviews and updates the plan, amends the schedule.
223
When might corrective action be required by the PM and what will be the actions from this?
When issues exceed tolerances Requires comms with team members and SMEs Amendment to the plan Escalation if needed
224
What is the review management stage status?
When the PM assesses and evaluates the whole stage progress as well as WP.
225
What report does the PM provide to the project board during stages?
Highlight report as agreed upon
226
When are risks and issues assessed?
Captured and assessed during the CS process
227
Where are the risks and issues recorded?
Risks - risk register | Issues - issue register
228
What are the actions to take if an issue is in or outside of tolerance?
Within tolerance: PM takes corrective action Dealt with informally Outside of tolerance: Requires escalation and consultation to change authority/project board.
229
What are exception situations and what do they require?
When issues happen by exception. Requires an exception report to the project board