Kaplan Flashcards
General Conditions
One of the AIA contract documents that comprise the construction contract between the owner and the contractor, the AIA Document A201. This legal document defines the rights and obligations of the parties involved. However, it also contains pertinent information from AIA Document B141 to better inform the contractor of the agreement between the owner an the architect.
With regard to the owner, what is the architect’s role in the bidding process?
During the CD phase, the architect is required to assist the owner in the preparation of the bidding documents and requirements. Other obligations include assisting the owner in:
- Compiling a list of prospective bidders or contractors.
- Obtaining competitive bids or negotiated proposals.
- Preparing and awarding contracts for construction.
- Evaluation of the successful bid proposal.
General Requirements
This is the title for Division 01 of the CSI Masterformat or the AIA’s Masterspec systems for organizing specifications. This division is used to explain the administrative and procedural requirements of the trades involved in the construction industry.
Substantial Completion
Sometimes called substantial performance, this is the date in the progress of the project when it is sufficiently complete, according to the contract documents, and the owner may occupy all or a portion of the project for it’s intended use.
Typically, the date used for the certificate of occupancy and is established when the architect, contractor, and owner sign the Certificate of Substantial Completion (AIA Document G704).
Cost Plus Fee
An owner/contractor or owner/architect agreement in which the contractor or architect is reimbursed for the actual expenses to perform the work, including salaries, employee benefits, office overhead, etc., plus a negotiated fee for profit. Usually includes a guaranteed maximum price (GMP). (See AIA Document A111)
Percentage of Construction Cost
A method of compensation for construction or professional services based on a percentage of the total cost of construction. (See AIA Document B141)
What happens at substantial completion?
Warranties generally become active, the final application for payment is processed, and the contractor is due the contract sum, less the value of the unfinished work. At final completion the contractor receives the final payment.
Design-Bid-Build
Most common method of project delivery. An architect is hired by an owner. The design documents are bid upon by various contractors and the acceptable proposal with the lowest bid is usually selected to build the project. The owner has a separate contract with both the architect and the contractor.
Design-Build
Project delivery method used when the owner requests that a single entity be responsible for both design and construction services. The owner has one contract with the architect/contractor.
Construction Management
Project delivery method often used in large or complex building projects when budget and scheduling issues are critical. This method was developed as a result of owner demand for technical advice early in the process. A consultant may be contracted by the owner to act as advisor, agent, or constructor, during design and construction.
Project Delivery
The method of approach to a construction project. Each one ha different characteristics regarding the roles and responsibilities of the owner, architect, and contractor. These methods form the basis for selection of the design team, contractors, types of contracts, and organization for the construction process from project inception to completed construction.
What are the most common project delivery methods?
- Design-Bid-Build
- Design-Build
- Construction Management
- CM Advisor
- CM Agent
- CM Constructor (CMc)
Construction Management
This is one of the 3 main methods. Under a CM approach, an owner hires a construction manager in addition to an architect and a contractor, usually on complex or fast-track projects. They provide budget, scheduling, construction and technical expertise and work with the architect. This service can be provided by an architect, contractor or other qualified party.
CM-Advisor
The CM advises the owner regarding constructability and budget issues during the design and construction process and assisted the owner in contractor selection but does not act as builder.
CM-Agent
The owner hires the CM first. The CM assumes financial authority and manages the entire project, through construction, on behalf of the owner.
CM-Constructor (CMc)
Hired by the owner when design is 30% complete. The CM advises the owner prior to construction and then builds the project, usually for a Guaranteed Maximum Price based on the design documents at the end of design development.
The Final Certificate for Payment may be issued after the contractor accomplishes what task?
Upon the contractor’s completion of the work outlined in the punch list, the architect may issue the final certificate of payment to the contractor.
How much time does an architect have to process shop drawings submitted by the contractor?
With regard to submittals, the architect is expected to: review and approve, or take other action with “reasonable promptness”, according to the AIA General Conditions (A201). This allows sufficient time for architectural review without causing a delay in the progress of the project. The exact time amount is not specified but 10 working days is common.
When is the use of mock-ups appropriate?
This is the process of modeling an object or building component, to scale or full size, for the purpose of studying or clarifying construction details, aesthetics, scale, or testing performance. It is useful when an innovative detail is specified and the additional time and cost of preparing the model outweighs the potential cost of unforeseen problems.
When is the architect authorized to act as the owner’s agent?
Under the design-bid-build and CM project delivery methods, during the architect’s administration of the Contract for Construction (the CA phase). Specifically, during construction until final payment is due, and also on occasion during the 1 year period for correction of work by the contractor.