Key Terms E-K Flashcards
(39 cards)
early finish
The earliest date an activity may finish as logically constrained by the network diagram
early start
The earliest date an activity may start as logically constrained by the network
diagram.
earned value (EV)
The value of the work completed to date as it compares to the budgeted
amount for the work component
earned value measurement (EVM)
EVM is a tool and technique of the Cost Control process that compares what you ’ re received or produced as of the measurement date to what you’ve spent. The three measurements needed to perform earned value measurement are planned value (PV), actual cost (AC), and earned value (EV).
economic model
A type of benefit measurement method. It is a series of financial calculations that provide data on the overall financials of the project and is generally used as a project selection technique.
enterprise project
A project that will be used by users throughout the enterprise
equipment
(a) Resources such as servers, specialized test equipment, or additional PCs that are required for a project. (b) One of the categories of project resources. It includes test
tools, servers, PCs, or other related items required to complete the project.
estimate at completion (EAC)
A forecast of the total cost of the project based on both current project performance and the remaining work. The formula is EAC = AC + ETC.
executing
This project process group is where the work of the project is performed
expert judgment
A technique used in project selection, determining estimates, and determining other related project information that relies on the knowledge of those with expertise on the requested subject matter. Expert judgment can come from stakeholders, other departments, consultants, team members, vendors, or industry groups
external dependency
A type of dependency where a relationship between a project task and a factor outside the project, such as weather conditions, drives the scheduling of that task.
extinction
This is a type of project ending that occurs when the project is completed and
accepted by the stakeholders.
failure costs
The cost if the product fails, including downtime, user support, rework, and
scrapping the project.
fast - tracking
A schedule compression technique where two activities that were previously scheduled to start sequentially start at the same time. Fast - tracking reduces schedule duration.
feasibility study
A formal endeavor that is undertaken to determine whether the project is a viable project, the probability of project success, and the viability of the product of the project
finish - to - finish
A project task relationship in which the finish of the successor task is
dependent on the finish of the predecessor task.
finish - to - start
A project task relationship in which the successor task cannot begin until
the predecessor task has completed
fixed - price contracts
A contract that states a fixed fee for the work that the vendor will perform.
float time
The amount of time the early start of a task may be delayed without delaying the finish date of the project. Also known as slack time .
flowchart
A diagram that shows the logical steps that must be performed in order to accomplish an objective. It can also show how the individual elements of a system interrelate.
forcing
This is a conflict - resolution technique where one party forces their solution on the
others. This is an example of a win - lose conflict resolution technique
formal communications
Planned communications such as project kickoff meetings, team
status meetings, written status reports, or team - building sessions.
forward pass
The process of working from the left to the right of a network diagram in order to calculate early start and early finish dates for each activity.
functional organization
A form of organizational structure. Functional organizations are traditional organizations with hierarchical reporting structures.