L4 - Time-Impact on schedules Flashcards

(5 cards)

1
Q

Time Impact analysis

A

Unplanned delays.
Delays beyond the GC’s control.
Construction law.
Time impact analysis.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Non-excusable delays

A
Normal weather.
Inadequate workforce/supervision/equipment.
Untimely material procurement.
Failure to coordinate subs.
Shortage of capital.
Foreseeable labor problems.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Non-compensable delays

A

Acts of God.
Strikes/labor unrest.
Unusually severe weather.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Excusable delays

A

No liquidated damages.

Could be compensable or non-compensable.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Compensable

A
By time/money.
Changes.
Shop drawing review.
Site availability.
Owner-furnished material.
Disruption.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly