Labour variances Flashcards

1
Q

What is labour variance?

A

It is the difference between the standard cost of labour for the actual level of production and the actual cost of labour used.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Overall labour variance =

A

(standard hours x standard rate) -

actual hours x actual rate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

What is labour rate sub-variance caused by?

A

It is caused by the actual hourly rate paid to employees being different from the budgeted hourly rate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Labour rate sub-variance =

A

Actual labour hours x

standard hourly rate - Actual hourly rate

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

What is the labour efficiency sub-variance caused by?

A

It is caused by the standard number of hours for the actual level of production being different from the actual number of hours

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Labour efficiency sub-variance =

A

standard rate x

standard hours - actual hours

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Overall labour variance 2 =

A

Labour rate sub-variance + labour efficiency sub-

variance