What is a payment bond?
It guarantees everyone gets paid
What is a performance bond?
It guarantees that the contractor will complete the project
What is a bid bond?
It is something given to the owner by the contractor to guarantee the contractor will do the work if they win
“All Risk Builders Insurance” is purchased by who?
Whoever owns the property
What are the Workers Compensation benefits for death on the job?
The dependents receive 80% of the after tax wage for 500 weeks
It also covers up to $6000 in funeral costs
Can horseplay be compensable under Workers Compensation?
Yes, though if it was intentional misconduct then it would not be
True or False – Certain workers can get a Workers Compensation exclusion.
TRUE
Can a Sole Proprietor be covered under Workers Compensation?
No
What is the threshold that requires your company to have Workers Compensation?
If you have one employee that works more than 35 hours per week for 13 or more weeks in a year
Through workers compensation you can be paid up to what percent of your after tax wages?
80%
In order to collect workers compensation you must be off work how long?
1 Week
What form must be submitted for a workers compensation injury report?
Form 100
Employers must prevent asbestos exposure in excess of _______.
0.1 Fiber per cubic cm
or 1% of air as an 8 hour weighted average
What is the Radon Take Action Level?
4 PCI/L
What is used to help control radon
4” of gravel under floor slabs and a 6 mil vapor barrier
How long does lead stay in the blood?
30 days
How long does lead stay in the soft organs?
6 - 8 month
How long does lead stay in the bones and teeth?
Forever
Are you required to provide owner and tenants the “Renovate Right” pamphlet and obtain proof of delivery when working on a home that may have lead paint?
Yes
You cannot disturb more than _____ of lead paint without being lead certified.
Interior –> 6 square feet
Exterior –> 20 square feet
Lead based paint can be in homes built before what date?
1978
Employers must protect employees against lead exposure in order to keep it below _______.
50 micrograms per meter squared of air over an 8 hour period
Substantial completion of work is obtained when?
The owner can take possession and use the property as intended
What is the implied warranty period?
1 year