Lean Manufacturing and JIT Flashcards

1
Q

The traditional production system is based on the forecast of _______ and on the _______ .

A

Demand, stocks

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

In a pull production system the last operation receives customer’s _______ and transfers its needs to the _______ operation, and so on.

A

Order, previous

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

The Just in Time system is a pull system. [True/False]

A

True

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

The JIT stock is the _______ to keep system activity.

A

Minimum

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

To reduce the stock level is necessary to reduce the size of the batches. [True/False]

A

True

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Reduce the batch size makes the costs of stocks…
A. Sometimes increase and others decrease
B. Increase
C. Do not vary
D. Decrease

A

B

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

When the batch size is 560 the average stock
is _______ units.

A

280

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

In a JIT system the current (optimal) batch it has to be reduced to a third of the its size. Knowing that the other conditions remain constant, how much the issue costs would have to reduce?
A. One quarter
B. One third
C. One ninth
D. Not vary

A

C

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

The SMED method is used to _______ the _______ time employed to switch from one product to another on a machine or process.

A

Reduce, prepartion

How well did you know this?
1
Not at all
2
3
4
5
Perfectly