Lecture 2 - Types of Contracts in Construction Industry Flashcards

1
Q

Traditionally, the _____ commissions a design.

A

employer

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

The _____ then is required to build in accordance with the design prepared by the employer.

A

contractor

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Under such a contract, the contractor’s responsibility is only to _______

A

construct in accordance with the design.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

If there is a failure of the structure eventually, as long as the contractor has constructed in accordance with the design, then liability falls on the______

A

designer.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

This method is well-proven and long-established in the industry.

A

The Traditional Contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

COMPENSATION TO CONTRACTOR

A

a. ) Lump – Sum Contracts
b. ) Measure and Value Contracts
c. ) Cost Plus Contracts

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

the price for the entire scope of works are fixed.

A

lump sum contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Lump sum contracts may come with ______, in which case the lump sum represents the total set out in the _____

A

Bills of Quantities

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Alternatively, the _____ may be based on drawings only. In that case, the contractor has to estimate the quantities involved in order to quote a _____.

A

lump sum

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Usually, the price of a lump sum contract cannot be varied due to any fluctuations of costs, currency, etc. unless there is a ____________

A

valid variation order

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Lump sum contracts are good for employers,________

A

where the scope of work can be reasonably ascertained up-front.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

A ________ would determine the rates for works to be carried out, or for supplies.

A

measure and value contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

This would usually be set out either in an approximate BQ or in a schedule of prices/rates.

A

measure and value contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Final amount to be paid would depend on the actual quantity of works carried out or supplies made.

A

measure and value contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

measure and value contract are good for ___________

A

contractors, who will be remunerated based on the actual quantum of work carried out.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

In a ______ , the contractor receives reimbursement of his actual cost plus a top-up to cover his profit.

A

cost plus contract

17
Q

Cost plus contracts are good for:

A

Employers, if they can ensure the costs are fair.

- Contractors, especially in an uncertain environment with fluctuating costs and currencies.

18
Q

__________ is one where the contractor undertakes both design work as well as the work of construction for the contract.

A

design and build contract

19
Q

design and build contractis advantageous for

A

employers who get a complete design, full scope of works and stipulated price from the outset.

20
Q

A variant of the design and build contract is the_______

A

turnkey contract.

21
Q

In a ______, the contractor does not only carry out design and construct obligations.

A

turnkey contract.

22
Q

( turnkey contract.) The contractor is also responsible for

A
  • Financing
  • Approvals
  • Procurement
  • Fitting out
  • Intellectual property issues (transfer of technology).
23
Q

It is also becoming increasingly common for parties to enter into _______instead of building contracts.

A

MANAGEMENT CONTRACTS

24
Q

In a _______, the contracted manager’s role is to ensure the implementation of the contract is carried out effectively.

A

management contract

25
The ______ gets involved early in the process, as opposed to the building contractor who is engaged later when the project is ready to be constructed.
contracted manager
26
It may well be that the “______” is a related company of the “______” eventually.
manager----contractor
27
A______usually happens for public infrastructure works.
BUILT-OPERATED-TRANSFER (BOT) CONTRACTS
28
In a_______, the private company builds, and operates a concession on the infrastructure built for an agreed period of time before transferring the infrastructure to the Government.
BUILT-OPERATED-TRANSFER (BOT) CONTRACTS
29
Ideally, a _______ would be a good mechanism for the private sector to fund infrastructure projects.
BUILT-OPERATED-TRANSFER (BOT) CONTRACTS
30
There are parties in the construction industry who are involved in supplying materials only, and do not participate in any actual construction.
SUPPLY CONTRACTS
31
For such contracts, the liability of the contractor is limited to supplying materials that meet the specifications.
SUPPLY CONTRACTS
32
It is important when dealing with supply contracts that proper tests are carried out before accepting the materials supplied.
SUPPLY CONTRACTS
33
For maintenance, __________ would be a common practice, whereby a contractor is required to maintain a certain facility for a pre-agreed term at a pre-agreed price
term contracts