Lecture 7 - NPV and PI Flashcards

(22 cards)

1
Q
  • What is NPV?
A
  • First, let’s recall present value (PV) and future value
    (FV)
    Present value (PV): the value of the assets (cash flows) now.
    Future value (FV): the value of the assets (cash flows)
    on a specific date in the future.
    PV = FV/(1+R)T and FV = PV * (1+R)T
    where R is the discount rate, T is the number of period,
    PV is the present value of the cash flow and FV is the
    future value of the cash flow.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q
  • Then, what is the present value of a series of cash
    flows?
A
  • In this case, you can take this series of cash flows as a
    special case of an annuity.
  • For a conventional annuity, we start receiving annual
    payments in one year and the annual payments are
    identical.
  • For this special case, there is a cash flow occurs at the
    beginning (time point 0), and the annual cash flows
    may not be identical.
  • The present value of this special case is called the net
    present value (NPV)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Net present value (NPV)

A
  • An example of NPV
    Given required rate of return is 10%, what is the NPV of
    following cash flows?

Points in time
(Yearly intervals)
Cash flows (£)
0 -10
1 10
2 8
3 10
4 8
5 10

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q
  • Example Illustration (breakdown to each year)
A

Year/Cash flow(FV)/PV
0 -10 -10
1 10 10/(1+10%)
2 8 8/(1+10%)2
3 10 10/(1+10%)3
4 8 8/(1+10%)4
5 10 10/(1+10%)5

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q
  • Example Illustration
A
  • The NPV of these cash flows is the present values of all individual cash flows.
  • NPV = -10 + 10/(1+10%) + 8/(1+10%)2 +
    10/(1+10%)3 + 8/(1+10%)4 +10/(1+10%)5
    = £24.89
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Net present value (NPV)

A
  • Net present value (NPV) is simply the sum of
    present values of all cash flows (including the
    one occurring at time 0).
  • The general formula of NPV
    Where CFt is the cash flow occurring at time
    point t and R is the required rate of return (or
    interest rate or cost of capital or discount rate…).
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

NPV and investment decision

A
  • For a business project, normally, there is an initial
    cost (cash outflow) at the beginning of the
    project. And then, the project will generate gross
    profits (cash inflows) in the future during the life
    of the project.
  • Should we invest in this project? (Are those
    future cash inflows enough to cover the initial
    cash outflow? )
  • The NPV approach can be applied on project
    appraisal to make investment decisions.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

NPV and investment decision 2

A
  • The NPV of a project is the sum of present
    values of all future cash flows and deduct the
    initial outlay.
  • The NPV rule in investment decision
  • If NPV ≥ 0, the project should be accepted.
  • If NPV< 0, the project should be rejected.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q
  • The NPV approach
A
  • It takes time value of money (we calculate PV
    of each cash flow!) into consideration.
  • If NPV ≥ 0, it indicates the future gross profits
    are enough to offset the initial cash outlay,
    and the project will make a profit.
  • If NPV< 0, it indicates the future gross profits
    are not enough to cover the initial cash outlay,
    the project will suffer a loss.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q
  • Example
A

A company is examining two projects, A and B, the
cash flows are as follows:
Points in time
Cash flows (£)
(Yearly intervals)
A B
0 (cash outlay)
1
2 250,000 250,000
3 200,000 20,000
100,000 120,000
20,000 220,000

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q
  • Example
A

Using required rate of return (discount rate) of 8%, and then 16%, calculate the NPVs and state which project is superior.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

NPV and investment decision
* Example illustration

A

When R = 8%

NPVA = -250,000+200,000/(1+8%)+100,000/(1+8%)2
+20,000/(1+8%)3 = 36,796

NPVB = -250,000+20,000/(1+8%)+120,000/(1+8%)2
+220,000/(1+8%)3= 46,043

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q
  • Example illustration
A

Using an 8% discount rate, both projects produce
positive NPVs, according to the NPV rule, If NPV ≥ 0,
the project should be accepted, so both projects
should be accepted (if they are not mutually
exclusive). Between two projects, B is superior
because it creates more value (higher positive NPV)
than project A. If projects are mutually exclusive,
only up to one project can be accepted.
* What if the discount rate is 16%?

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q
  • Example illustration
A

When R = 16%
NPVA :
-250,000+200,000/(1+16%)+100,000/(1+16%)2
+20,000/(1+16%)3 = 9,543

NPVB :
-250,000+20,000/(1+16%)+120,000/(1+16%)2
+220,000/(1+16%)3= -2,634

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q
  • Example illustration
A
  • According to the NPV rule, project A should be
    accepted as it generates a positive NPV, it
    implies the company will make a profit from
    project A.
  • While project B should be rejected as it
    generates a negative NPV, it implies the
    company will suffer a loss from project B.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q
  • Example illustration
A

Tired of calculation? We can use present value
table (Table A-3) to get the same result!
Take project A with a discount rate of 8% for
example.
NPVA = -250,000 + 200,0000.9259 +
100,000
0.8573 + 20,000*0.7938
= 36,796 (same as our previous calculation)
* Have a try on the discount rate of 16%

17
Q
  • The NPV approach (Pros)
A
  • It takes into account the time value of money
  • It is easy to apply
  • It takes into account investment size (absolute
    amount)
  • It can handle non-conventional cash flows
18
Q
  • The NPV approach (Cons)
A
  • Prediction on future cash flows could be
    inaccurate.
  • It assumes the predicted future cash flows are
    not subject to change.
  • Prediction on future discount rate could be
    inaccurate.
  • The result of the NPV approach could be
    contradictory to other approaches.
19
Q

Profitability index (PI)

A
  • A method to make project investment decision
  • It is the ratio of sum of PVs of all future cash flows divided by the absolute value of initial cash outlay

PI = PV of all future cash flows/inital cash outlay

20
Q
  • Example (assuming discount rate is 8%)
A

Points in time
Cash flows (₤)
(Yearly intervals)
A B
0 (250,000) (250,000)
1 200,000 20,000
2 100,000 120,000
3 20,000 220,000

21
Q

Profitability index (PI)
* Example illustration

A

PIA =[200,000/(1+8%)+100,000/(1+8%)2
+20,000/(1+8%)3]/250,000 = 1.15

PIB = [20,000/(1+8%)+120,000/(1+8%)2
+220,000/(1+8%)3]/250,000= 1.18

22
Q

Profitability index (PI) rules in investment
decision making

A
  • To independent projects
  • Accept the project if PI>1
  • Reject otherwise
  • To mutually exclusive projects
  • Accept the project has the highest PI given PI>1
  • Reject remaining projects
  • We follow the NPV rule if it is contradictory to the
    PI results.