Level 1 Flashcards
(45 cards)
What standard forms of contract are you aware of?
JCT (Joint Contracts Tribunal)
Minor Works – for simple, low-risk projects.
Intermediate Building Contract – for medium-sized projects with more complexity.
Standard Building Contract – for large, complex jobs with detailed design.
Design and Build Contract – where the contractor takes on design responsibility.
What are the timescales involved with an extension of time request on a standard JCT contract?
- Notification by the Contractor
- The contractor must notify the contract administrator (CA) of any Relevant Event that may delay completion “as soon as it becomes reasonably apparent”.
- There’s no fixed number of days stated, but prompt notice is expected to help mitigate delays. - Submission of EOT Request
-The contractor must provide supporting details for the delay, including:
-The cause (Relevant Event)
-The effect on the completion date
-Any extension they believe is due
-This should be submitted without delay once the impact is clear. - CA’s Assessment and Response
-The contract administrator must assess the EOT request fairly and reasonably.
-There’s no strict deadline for the CA’s decision in the standard JCT, but they are expected to respond within a reasonable time. - Non-Completion and Liquidated Damages
-If no extension is granted and the contractor overruns, liquidated damages may apply unless a new completion date is formally agreed.
Ongoing Evaluation
The CA can review or revise an EOT decision later if more information becomes available or further Relevant Events occur.
Does an instruction need to have an agreed value contained within it?
A Contract Administrator (CA) can issue an instruction to vary the works (e.g. design changes, materials, sequence) without an agreed price upfront. This allows work to proceed promptly, especially if there’s a risk of delay.
The contractor fails to complete the project by the completion date what measures do the CA/EA take and what are the consequences of this?
*Check for valid Extensions of Time (EOT) due to Relevant Events.
*Issue a Non-Completion Notice to formally acknowledge the delay.
*Deduct Liquidated Damages (LDs), if specified in the contract, as compensation for the delay.
*Monitor progress and ensure work quality.
*Issue Practical Completion Certificate once the works are substantially complete to stop further LDs.
*Consequences for the contractor include financial penalties, reputation damage, potential contract *termination, and delays in final payment or retention release.
The CA/EA fails to issue a non-completion certificate on an over running project what are the consequences of this?
🔑 Key Consequences:
-Loss of Liquidated Damages: The employer cannot enforce penalties for delay.
-Delayed Payment: Final account and retention release could be delayed.
-Breach of Contract: There could be legal implications for the CA/EA.
-Disputes Over Extensions of Time: Lack of clear status could create confusion in EOT assessments.
What is your understanding of bespoke contract?
What do you understand as the difference between a bespoke contract and standard form of contract?
ChatGPT said:
A standard form contract is a pre-written, widely used agreement (like JCT or NEC) designed for general use, offering legal certainty and faster setup. A bespoke contract is fully customised for a specific project, offering flexibility but requiring more time, cost, and legal input, with potentially less clarity if not well drafted.
✅ Standard = familiar, efficient, legally tested
🛠️ Bespoke = tailored, flexible, more complex to manage
When was the JCT contract suite last updated? Tell me about some of the key changes that were made.
2024
Modernisation and Streamlining: Adoption of gender-neutral language and increased flexibility around the use of electronic notices. Can be served via email
New Contract Family: Introduction of the JCT Target Cost Contract (TCC), comprising a main contract, sub-contract, and guide.
Legislative Changes: Updates to reflect the Building Safety Act 2022, Corporate Insolvency and Governance Act 2020, and provisions related to the Construction Act.
Future-Proofing: Incorporation of previously optional supplemental provisions relating to Collaborative Working, Sustainable Development, and Environmental Considerations into the main document.
How does the JCT work alongside the Construction Playbook?
Sets out principles and expectations that should be embedded into standard or bespoke contracts (like JCT, NEC, etc.) used in public projects.
What is the JCT Fluctuations Hub used for?
Developed by the Joint Contracts Tribunal (JCT) to assist construction professionals in managing the impact of economic volatility—such as inflation, material shortages, and supply chain disruptions—on construction projects. It provides comprehensive guidance on the application of fluctuation provisions within JCT contracts
Explain the JCT Target Cost Contract to me.
It is designed to promote collaborative working, shared risk, and cost transparency between the client and contractor—making it suitable for complex or cost-sensitive projects where teamwork and budget certainty are key.
What form of NEC contract might the Target Cost Contract be a good alternative for?
NEC4 Option C: Target Contract with Activity Schedule and NEC4 Option D: Target Contract with Bill of Quantities.
What are the qualities of the NEC form of contract?
Proactive management of time, cost, and quality.
Risk allocation designed to be fair and transparent.
Collaboration encouraged through open communication and early warnings.
Clear terms for dispute resolution.
Flexibility to adapt to various types of projects.
What changes were last made to the NEC form of contract?
NEC3 to NEC4 in 2017
What is the difference between a Relevant Event and Relevant Matter?
Relevant Event
-A Relevant Event refers to specific events or circumstances that are beyond the contractor’s control, which might delay the completion of the works. When a Relevant Event occurs, it may entitle the contractor to an extension of time for the completion of the project.
Relevant Matter
A Relevant Matter refers to circumstances or issues that impact the contractor’s entitlement to an extension of time but are more specific to the contractor’s performance and may require the contractor to carry out corrective actions.
What guidance is there on contract administration?
Contract administration is a critical function in the successful execution of construction projects. The guidance provided by contract-specific documents like JCT, NEC, FIDIC, and RICS, as well as regulations like CDM 2015
What are the duties of a CA under JCT contracts?
Issuing instructions to the contractor.
Assessing and issuing certificates for payment and completion.
Managing and agreeing upon variations.
Assessing and granting extensions of time.
Monitoring progress and ensuring timely completion.
Identifying and rectifying defects.
Ensuring compliance with quality and standards.
Managing payments and financial control.
Assisting with dispute resolution.
Administering the contract documentation and ensuring legal compliance.
Providing advice to the client.
Managing project risks.
When authorising payment for goods or materials stored off site what must you obtain to protect your client in the event of the contractor going bankrupt?
- Proof of Ownership
- Proof of Payment
- Material Insurance:
If you are concerned that a contractor is in financial difficulties name 3 things as CA you should do?
- Review the Contractor’s Financial Status
- Ensure Compliance with Payment Terms
- Consider Contractual Remedies or Mitigation Actions
What insurance provisions are in the JCT and NEC standard forms of contract?
Both JCT and NEC contracts set out clear insurance requirements, including coverage for works, liability, and employees, although the specific provisions may vary depending on the type of contract and the needs of the project.
Where is the minimum financial cover for the contractor’s liability for injury death and damages to property other than the works contained?
minimum cover of £10 million for public liability insurance
What is your understanding of what a letter of intent is?
non-binding document that expresses one party’s intention to enter into a contract with another party. It is often used in construction to authorize preliminary work or to establish initial terms before a full contract is signed
What would you say if the client asked you to draft a letter of intent?
I would first clarify the purpose, scope, and any specific terms they want to include. I would emphasize that an LOI is typically non-binding, with potential legal obligations for certain actions. I’d also ensure that it includes limitations, particularly around liability and commitments, and recommend seeking legal advice for clarity
What is the final account (FA)?
The final account (FA) is the final statement that reflects the total cost of a construction project at its completion. It includes the final assessment of all costs, adjustments, and variations that have occurred during the course of the project. The final account is typically agreed upon by the contractor and the client (or their representatives) and represents the final amount that the client owes the contractor for the completed works.