Level 1 - Written Documents Flashcards

(39 cards)

1
Q

When would you use JCT & NEC Contracts?

A
  • Both suites provide a variety of options to suit client requirements
  • Consider procurement route, scale & size of project, payment method, quantification, design and the client approach
    NEC Contract if:
  • Collaborative approach
  • Limited experience; plain english
    JCT Contract if:
  • Previous experience with JCT
  • Prepared set of amendments
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Name some differences between the two if you were advising a client on what to use as a proposed form?

A

PALM:
- Programme - unamended JCT not contractual whereas it is in a NEC
- Admin - JCT is administered by the CA/EA whereas in NEC the Project Manager
- Language - JCT contracts use complex legal jargon whereas, NEC plain English
- Money & Time - JCT has relevant events & relevant matters whereas NEC together in compensation events

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Can you name the types of NEC Contracts?

A
  • Option A: Priced Contract with activity schedule
  • Option B: Priced Contract with BoQ
  • Option C: Target Contract with activity schedule
  • Option D: Target Contract with BoQ
  • Option E: Cost reimbursable Contract
  • Option F: Management Contract
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Can you name the contract within the JCT suite?

A
  • Minor Works
  • Intermediate Building Contract
  • Standard Building Contract
  • Design & Build Contract
  • Major Projects Construction Contract
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Describe the layout of JCT?

A

Articles of agreement:
- Recitals
- Articles
- Contract particulars
- Attestation
Conditions:
- Section 1: Definitions and Interpretations
- Section 2: Carrying out the works
- Section 3: Control of the works
- Section 4: Payment
- Section 5: Change
- Section 6: Injury, Damage and Insurance
- Section 7: Assignment, third party rights and collateral warranties
- Section 8: Termination
- Section 9: Settlement of Disputes
Schedules:
- Contractors design submission procedure
- Supplemental provisions
- Insurance Options
- Code of practise
- Third Party rights
- Form of Bonds
- Fluctuation Options

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

How do you pick which contract to use?

A
  • Consider the project specific requirements
  • Procurement Route
  • Scale of the project
  • Method of payment / quantification
  • The design of the project
  • Clients drivers / approach (Time/Cost/Quality/Risk)
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

When would you use JCT Standard Building Contract?

A
  • SBC used for Traditional procurement route
  • Where detailed contractual provisions are required
  • ‘with quantities’ and ‘without quantities’ both fixed price lump sum
  • ‘with approximate quantities’ is remeasurement
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

When would you use an Intermediate contract?

A
  • Used for traditional procurement route
  • Used to bridge the gap between Standard and Minor works contract
  • Less lengthy contract terms than standards, more detailed than minor
  • Fixed Price Lump Sum
  • Intermediate with CDP is available
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

When would you use Minor Works Contract?

A
  • Minor works contract is for Traditional procurement route
  • Used for smaller, lower value, basic construction works where detailed contract provisions not required
  • Not suitable where project is complex enough to require bills of quantities, detailed control procedures, or provisions to govern work carried out by named specialists
  • Fixed Price Lump Sum
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Whats the difference between minor works and intermediate?

A
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

What’s the difference between intermediate and standard building contract?

A

SBC has 3% retention
ICD has 5% retention
ICD has no provision for third party rights
ICD has no provision for retention bonds

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

When would you use JCT Design and Build Contract?

A
  • Design and Build Procurement Route
  • Client wants Contract to take design and construction responsibility
  • Used where detailed contractual provisions are required - project can vary in size/scale
  • Fixed price lump sum
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Name some contractual mechanisms within the D&B contract?

A
  • 2.3 Date of Possession; Contract Particulars; date when site is given to the contractor, begin construction and proceed to complete on it before completion date - can be sectional completion
  • 4.7 Payment - 4.7.1 Method of Payment - Periodically in accordance with Alternative B (clause 4.13)
  • 4.7.2 - Interim Payments - Interim Valuation Dates; one month after the Date of Possession
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Do you have Collateral warranties in a D&B contract?

A

Yes

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

What are Collateral Warranties?

A
  • Create a contractual link between the employer and a third party which would not be there otherwise.
  • For the benefit of those parties that may otherwise have no recourse, if one party defaults
  • I would advice the Client to request CW’s for all subcontractors who have any design responsibility, for example; the facade, steelwork, roof
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

Who may want a collateral warranty?

A
  • Employer with sub-contractors who have design responsibility
  • Third party with a financial interest in the project but is not protected by the contract e.g. funding institutions/ future purchasers
17
Q

How are defects addressed in JCT contract?

A
  • Under JCT contract the employer can issue a Schedule of Defect - up to 14 days after the rectification period
  • Contractor must return at no cost to the employer and rectify the defects - unless otherwise instructed
  • If agreed that the contractor will not return, reasonable adjustment can be made to CSA
  • Once defects are rectified a ‘notice of completion of making good’ will be issued by the CA/EA
18
Q

What is a change called in a JCT Design and Build Contract?

19
Q

What constitutes a change in JCT SBC?

A
  • Alteration or modification of the design, quality, or quantity or the works
  • Employer imposed additional or altered obligations or restrictions e.g. access to the site, limitations on working space
20
Q

What is a change called in a JCT Standard Building Contract?

21
Q

What are the valuation rules?

A

There are a variety of valuation rules, the main ones are:
- Using rates within the priced document (CSA) - when works are of a similar ‘character’ to the contract documents
- Value at fair rates and prices - when works are not of a similar nature
- Dayworks - when works cannot be properly valued by measurement
- Changes to the CDP works -

22
Q

What are dayworks?

A

NRM2 defines dayworks as - ‘the method of valuing work on the basis of time spent by the contractors workpeople, the materials used and the plant employed’.

23
Q

What happens at practical completion?

A
  • Certificate of practical completion is issued
  • Release of 50% retention
  • Defects liability period begins
  • Ends contractors liability for LD’s
  • O&M are handed over
  • H&S file handed over
  • As built drawings are issued by the contractor
  • Client takes possession & responsibility for insuring the site
24
Q

What is sectional completion?

A
  • Pre-planned and defined sections of work which allow different completion dates for each section.
  • Follows same procedure as PC for the whole job apart from some items will remain outstanding
25
What is partial possession?
Where the employer with consent of the contractor takes possession of parts of the works before practical completion.
26
What happens at partial possession?
- the part is deemed to have achieved practical completion - Half of the retention for that part is released - Defects liability period (or rectification period) begins for that part - Liquidated damages reduced proportionally - Client is responsible and should insure that part
27
What insurances are required under a JCT Standard Building / Design & Build Contract?
- Option A: Taken out by Contractor (Joint names) - Option B: Taken out by Client (Joint Names) - Option C: Taken out by Client (Joint Names) for works to Existing Structures
28
What insurances would you expect under JCT?
- Contractors Public Liability Insurance - (injury to persons or property in course of completing the works). - Employer Liability - (contractor takes out insurance in names with Employer, protects Employer from any claims due to injury / damage to property etc.) - Works Insurance - Option A / B / C - Terrorism Cover - Pool Re cover against loss or damage due to terrorism - Professional Indemnity Insurance - Contractor takes out insurance to protect against negligence claims
29
What constitutes a contract?
- Offer - Acceptance - Consideration - Intent to create legal relations - Capacity - Legality - Certainty - Performance
30
What is the difference between a CA and a EA?
CA - referee, act impartially in the spirit of the contract - manages the contract on behalf of both parties EA - coach, act on behalf of the client on all matters - employer gives authority to manage the project on their behalf
31
Why did you advise that the rectification period be changed from 6 to 12 months?
This allows for a full years use of the building through all seasons to discover any latent defects.
32
What is all risk insurance?
- Cover against any physical loss or damage to works / materials - Covers cost to remove debris, shoring and propping of works - Excludes - repair, replace and rectify costs
33
What is Joint Names Policy?
- Insurance that includes the Employer and Contractor as composite insurers - Means insurers have no recourse against another named party
34
What is subrogation?
- Subrogation is another party's legal right to collect a debt or damages on your behalf - Insurers have the right to subrogate and claim back from another party - Does not apply on joint names policies
35
What is Pool Re Cover?
- Insurance against damage to works or materials from terrorism
36
What is Specified Peril?
Fire / Flood / Earthquake / civil commotion / lightening
37
What is a Schedule of Amendments?
- A set of Amendments to the standard form of contract - Parties set out agreed changes to published terms - Must be read in conjunction with the contract - Must be properly incorporated into the contract
38
What is a Parent Company Guarantee?
- Typically a parent company or another group company of the Contractor - They will guarantee their performance of the works under the same contract terms - If the contractor defaults, guarantor effectively steps in to complete the work
39
What is a performance bond?
- The bond protects the insured party should a contracted entity fail to meet its obligations set out in the contract between the insured and the contractor. - Usually around 10% of the contact sum. - Provided at client expense - Usually limited to a value of 10% of CSA - limits the loss that could be recovered - Client will have to find another Contractor to take on the risk of completing the works