Level 2 Flashcards
(43 cards)
What does Contractors Design Portion mean?
It is an agreement for the contractor to design specific parts of the works. The contractor may in turn sub-contract this design work to specialist sub-contractors.
Does the Minor Works have a CDP Portion?
The JCT Minor Works Contract has a ‘with contractor’s design’ option and a separate sub-contract with sub-contractor’s design.
How do you ensure that the costs allowed for LDs were accurate?
- Research and confirm costs
What sections were included within the contract docs?
- Main JCT contract
- Specification
- Priced SoW
Explain the difference between single stage and two stage tendering.
Single Stage – Go to tender with completed consultants design and specification. Contractor prices the bill of quants, schedule of work or performance spec. Benefits include greater cost and programme certainty, reduced cost due to competitive tender, clear allocation of risk.
Two Stage - The first stage tender is based on a partially developed consultant’s design (prelims, prov sums, demolitions, earthworks, schedule of rates etc.). The contractor selected at the first stage is then able to assist with the final development of the design and tender documents used to obtain tenders for the construction works. The second stage can either be tendered or negotiated to arrive at a contract sum. Benefits include contractors input and buy in to the design, collaborative working relationship.
What is a tender?
A submission made by a prospective supplier in response to an invitation to tender. It makes an offer for the supply of goods or services.
What can a client do before an invitation to tender to ensure the prospective contractor is competenent?
Pre-qualification questionnaire (PQQ)
Pre-tender interview.
What is a PQQ?
Series of questions for potential tenderers to answer regarding their level of experience, capacity and financial standing.
What can a PQQ enable the client to identify?
To produce a short list of suppliers that are likely to be most appropriate for their project. Short-listed suppliers may then be invited to tender for the contract.
What is the main objectives of a pre-tender estimate?
Assess the tenderers understanding of the commission.
Assess the tenderers likely approach to the project.
Assess the tenderers current workload.
Assess the tenderers enthusiasm.
Clarify ambiguities on either side.
Verify that the proposed timescale for the tender process is achievable.
Verify that the proposed nature of the tender process will obtain the best results.
Define and explain the purpose of tendering.
To select a suitable contractor at a suitable time
The offer of a price is required from the contractor at an appropriate time. This offer will be the basis for the ensuing contract
What is a tender analysis?
Assessment of tenders to identify the most economically advantageous tender (MEAT) as opposed to the lowest price.
How were the tenders analysed to identify the most econimcally advantageous tender?
It was a 60/40 split between price and quality. The client assessed the quality whilst I evaluated the price. As it was scored out of 60, the lowest cost was given 60.0, the quality had a maximum score of 40. These points were added together to give the final tender evaluation score.
What is a bona fide tender?
Without intention to deceive tender, assumed genuine and real.
What is a framework?
A framework agreement is an ‘umbrella agreement’ that sets out the terms (particularly relating to price, quality and quantity) under which individual contracts (call-offs) can be made throughout the period of the agreement (normally a maximum of four years)
What are the benefits of a framework?
A selection of contractors shortlisted to be capable of providing the delivery of a project
What is the Dynamic Purchasing System?
Electronic method of procurement, used for the supply of goods and/or services. It’s different to traditional procurement routes as it operates an ‘open market’ for suppliers to join either constantly or very frequently. This allows buyers to continually expand their network of suppliers and welcome new businesses that can meet their changing needs.
What is the difference between DPS and a Framework?
DPS- continually open/regularly re-opened for the buyer to build up a pool of suppliers that they can call upon whenever they need it.
Framework is restrictive with the application window/frequency.
DPS flexible in terms of the amount of suppliers they allow into the network. A framework will determine a number of suppliers required when it is put out to tender.
The pro’s of a DPS for the supplier?
Open/reopen, more accessible for less experienced suppliers to get on public sector, typicall less/time effort/documents for DPS.
The con’s of a DPS for the supplier?
No guarentee of work. Larger pool of suppliers means more competition.
The pro’s of a DPS for the buyer?
Larger pool of talent to call upon.
Becoming more popular
Isn’t restricted to a number of suppliers. Less risk.
Encourages smaller enterprises.
The cons of a DPS for the buyer?
Larger administration task to pre qualify, welcome and add new suppliers to the DPS network.
The buyer could end up with a supplier list that is not being effective and lose close partnerships.
What are the five main types of tender?
Open tender
Selective Tender
Negotiated Tender
Single stage and two stage tender
What is the difference between procurement and tendering?
Procurement: is the overall act of obtaining goods and services from external sources (i.e. a building contractor) and includes deciding the strategy on how those goods are to be acquired by reviewing the client’s requirements (i.e. time, quality and cost) and their attitude to risk.
Tendering: is the bidding process, to obtain a price; and how a contractor is actually appointed.