- What is a contract?
A legally binding agreement (between two parties) to provide goods and services within a specified timeframe.
- What is necessary to form a contract?
Offer Acceptance (or counter offer) Consideration Intention (to be legally bound) Capacity (to make agreement) (e.g. power of attorney on behalf of a company)
- How is a contract executed?
- Under hand, signed by both parties, 6 year limitation period. Means that a party must bring about any claim for breach of contract within 6 years of the breach taking place. Any later and the claim will be time-barred.
- Under Seal (as a deed), signed and witnessed, 12 year limitation period. Valuable consideration not required,
- What are common contract documents?
- The Contract (with any amendments)
- Preliminaries
- Contract sum analysis/Pricing Schedule
- Drawings
- Specification
- Planning conditions/agreements
- Contractors Proposals
- What are the main contract suites?
- JCT (Joint Contract Tribunal)
- NEC (New engineering contract)
- FIDIC (International federation of Consulting engineers)
- ICE (Institution of Civil Engineers)
- How did you try to mitigate a delay on one of your projects?
Coventry demolition - Liasing with Main contractor to overlap the works, early survey work can begin on site whilst last section of demolition taking place.
N 1. Why use standard forms of contract?
- They are cheaper than getting a bespoke contract drawn up
- Offer a level of familiarity between the parties
- Tried and tested contracts in court, therefore you should be able to predict the outcome in the courts.
N 2. Why wouldnt you use a bespoke contract?
- They are costly to produce and time consuming
- Contractors do not like them, as they regularly put alot of the risk onto the contractor
- They are not tried and tested like a standard form
N 2. Why wouldnt you use a bespoke contract?
- They are costly to produce and time consuming
- Contractors do not like them, as they regularly put alot of the risk onto the contractor
- They are not tried and tested like a standard form
N 3. What is required to form a contract?
Offer Acceptance Consideration Capacity Intention Legality?
N 4. What should you consider when selecting the contract?
- The criteria of the client
- The procurement method you are going to use
- Nature of the works
- Timings, are the works required to start quickly or do you have time to produce robust set of docs
N 7. What standard forms of contract do you know that are offered by JCT?
- SBC 2011/2016
- Intermediate building contract 2011/2016
- Minor works Building contract 2011/2016
- Major Projects building contract 2011/2016
- Design and build contract 2011/2016
- Management Building contract 2011/2016
- Construction management contract 2011/2016
- Prime cost building contract 2011/2016
N 8. Can you name some NEC standard contract forms?
NEC - Engineering and Construction Contract (ECC)
- Option A, Priced contract w/ Activity Schedule
- Option B, Priced contract w/ BoQ
- Option C, Target contract w/ Activity Schedule
- Option D, Target contract w/ BoQ
- Option E, Cost reimbursable
- Option F, Management contract
N 12. When is a JCT Minor Works contract NOT suitable?
- Complex projects
- Detailed control procedures
- Where there are named Sub-Contractors
N 13. Can you provide more information on the JCT Major project construction contract?
- Used on large , complex project by experienced clients
- They place most of the risk on the contractor
- Has sub-contract derivatives
- All derivatives/versions have a yellow and purple cover
N 14. Can you provide more information on the JCT Design and Build Contract 2011?
- They are used by all types of clients, create a single point of responsibility for the design and construction with the contractor
- Can be used on projects of all sizes
- Client must produce the Employers Requirements
- Has a sub-contract derivative broken into two parts: JCT DB11 Sub-contract Agreement, JCT DB11 Sub-contract Conditions
- All derivatives have a Yellow and pink cover
N 15. Can you provide more information on the JCT Management Building Contract?
- Used then a management contracting route is chosen
- Used by experienced clients who understand the construction costs
- No real cost certainty until all packages are let
- Works are completed by a number of ‘Works Contractors’ who are placed under a management works contract.
- Works Contractors are contracted to the Management Contractor
- Management Contractor is a fee earning professional onto the the final construction costs.
- All derivatives have a yellow and brown cover
N 16. Can you provide more information on the JCT Construction management contract?
- Used where a CM procurement route is chosen
- Used by experienced clients who understand the construction costs
- No real cost certainty until all packages are let
- Works are completed by a number of ‘Trade Contractors’, who are placed under a ‘Construction Management Trade Contract’.
- Trade contractors are contracted directly with the client
- The Construction Manager is only responsible for looking after the programme and construction.
- All derivatives have a Yellow and Brown cover.
N 17. Can you provide more information on the JCT Prime Cost Building Contract?
- Used on projects which require an early/quick start
- Usually on a cost plus basis, as the extent of the works are not known until the project is underway
- Has sub-contract forms
- All derivatives have a yellow and pink cover
N 18. Can you provide more information on the NEC Option A contract?
Priced Contract with an Activity Schedule
- For all types of clients, the balance of risk is mainly with the contractor
- It comes with/requires an activity schedule, containing a list of activities the contract expects is required to complete construction.
- Lump sum
N 19. Can you provide further information on the NEC Option B contract?
Priced Contract with a Bill of Quantities
- For all types of clients, the risk is mainly with the contractor
- Comes with a detailed BoQ, which can either be produced by the client or Contractor, which is a detailed statement of all the works that will be undertaken.
- Lump sum
N 20. Can you provide further information on NEC Option C contract?
The NEC Option C is a target cost contract with activity schedule where the out-turn financial risks are shared between the client and the contractor in an agreed proportion
N 21. Can you provide further information on NEC Option D contract?
Option D provides for a target cost with a bill of quantities:
A target cost introduces a mechanism that enables the contractor, and/or the consultant team, to share in the benefits of cost savings, but also to bear some of the cost when there are cost overruns. This is typically shared in a pre-agreed proportion.
Option D includes core and secondary option clauses, the schedules of cost components, and contract data.
N 22. Can you provide further information on NEC Option E contract?
Option E is a cost reimbursable contract
Contractor is reimbursed the actual costs they incur in carrying out the works, plus an additional fee.
The financial risk involved is largely taken by the client.
A cost reimbursable contract might be used where the nature or scope of the work to be carried out cannot be properly defined at the outset, and the risks associated with the works are high, such as, emergency work (for example, urgent alteration or repair work, or if there has been a building failure or a fire requiring immediate reconstruction or replacement of a building so that the client can continue to operate their business).
Option E contains the core clauses, secondary option clauses, schedules of cost components, contract data, and so on.