Liquidated Damages and Penalties Flashcards
(9 cards)
1
Q
What are Liquidated Damages
A
- Damages specified in contract to be paid if contract was breached and AVOID
2
Q
What are Penalties
A
- In MOST cases, penalties are unenforceable
3
Q
When are Penalties considered invalid?
A
- If amount is extravagant AND out of proportion
4
Q
What should be compensated instead if its a Penalty?
A
- Common LAW Damages
5
Q
What should be present for Common Law Doctrine to apply?
A
BREACH OF CONTRACT
6
Q
What should be present for EQUITABLE Doctrine to apply?
A
- Whether there has been performance or NON performance
7
Q
What is the 2 Stage Test to determine whether sth is a penalty or liquidated damage?
A
- Does the Penalty doctrine apply?
–> Payable on breach?
–> Payable on occurence of an event that is NOT a contractual obligations?
–> Fee for additional obligation or service - Is the clause a penalty?
–> Amount extravagent and unconscionable and out out of all proportion
8
Q
Should a clause be determined a penalty or liquidated damage BEFORE or AFTER contract formation?
A
BEFORE
9
Q
What is a key case to determine whether something is a penalty?
A
- Dunlop