Liquidated Damages + Penalties Flashcards

(14 cards)

1
Q

What is a liquidated damages clause?

A

A clause which stipulates a certain sum which is to be payable on a particular breach of contract.

  • parties agree it
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Purpose of a liquidated damages clause?

A

a) commercially advantageous - it fixes the amount that will be due for breach as a debt arising under the contract without C having to deal w uncertainty of est its case for damages

b) clarity - makes clear to a party what is at stake if it fails to comply w its obligation. A party can then take the risk into account when determining the price for the contract.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Where are these clauses common in?

A

construction and technology industries to deal w consequences of non-performance such as delay

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Can the court intervene in relation to liquidated damages clauses?

A

instances where court will intervene.

  • strike down a liquidated damages clause if regarded as a penalty on a breaching party + C will only be entitled to ‘unliquidated’ damages (ie damages assessed in the normal way) as compensation for the breach.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Whats a penalty clause?

A

a liquidated damages clause which req breaching party to pay an excessive sum, such that it becomes a penalty = clause not upheld.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

What 2 cases determine whether a clause is a valid ‘liquidated damages’ clause?

A

1) ParkingEye Limited v Beavis

2) Cavendish Square Holdings BV v Talal El Makdessi

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

What is the 1st part of the test in Cavendish Square Holdings BV v Talal El Makdessi?

A

1) Is clause primary/ secondary obligation?
- primary = if part of primary obligations in the commercial context of the contract, ie furthers the commercial objective of the contract.

If primary = clause will not engage the penalty rule at all (so = valid).

  • secondary = if an obligation triggered by breach of contract to compensate the innocent party.
How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

What is the 2nd part of the test in Cavendish Square Holdings BV v Talal El Makdessi?

A

If clause secondary obligation = clause is penalty if imposes a detriment out of all proportion to any legitimate interest of the innocent party in the performance of the primary obligation.

To determine this - 2 steps:

1) What (if any) legitimate business interest is served + protected by the clause?

2) Is the detriment imposed to protect that interest extravagant, exorbitant or unconscionable?

burden = on person alleging clause = penalty

party can have a legitimate interest in enforcing performance which goes beyond simply being compensated for losses - a clause which was not disproportionate to that protection of that legitimate business interest = upheld.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Can the court intervene in a contract because it considers the price of a clause unfair?

A

No

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

When will it be hard for the party paying liquidated damages to challenge the validity of it on basis that its a penalty?

A

where parties have negotiated a contract, on a level playing field and with the assistance of professional advisors

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

If a clause is a primary obligation, is it a penalty clause?

A

No

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

If a clause is a secondary obligation, is it a penalty clause?

A

No - IF it protects a legitimate business interest + imposes a detriment which is not disproportionate to protect the legitimate interest.

= courts hold this to be a valid liquidated damages clause.

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

What happens if a court finds that a liquidated damages clause is a penalty?

A

liquidated damages clause = struck down + C entitled to unliquidated damages assessed by court using normal rules of contract law

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Difference between primary + secondary obligation?

A

primary obligation = won’t engage the penalty rule
secondary obligation = could potentially be a penalty

How well did you know this?
1
Not at all
2
3
4
5
Perfectly