MEE Practice Question Rules Flashcards
(38 cards)
The UCC controls contracts for:
the sale of goods
The common law controls contracts for:
services or real estate
Anticipatory repudiation occurs when (UCC):
there has been an unequivocal refusal of the buyer or seller to perform, OR when a party creating reasonable grounds for insecurity fails to provide adequate assurances within 30 days of the demand for such assurances
Repudiation allows:
the nonrepudiating party to resort to any remedy given by contract or code
Repudiation may be retracted:
Until the repudiating party’s next performance is due, UNLESS the aggrieved party: (1) has since accepted the repudiation, acted in reliance on the repudiation, or brought an action for breach
Proper retraction of repudiation:
includes any assurances of performances that the other party has justifiably demanded about whether the retracting party will perform, and reinstates the repudiating party’s contract rights
If a transaction includes both goods and services:
the predominant purpose test is applied to resolve whether the common law or UCC applies to the entire transaction
Material breach under the common law occurs when:
the non-breaching party does not receive the substantial benefit of the bargain
A material breach allows:
the non-breaching party to withhold any promised performance and to pursue remedies for the breach, including damages
A minor breach allows:
the non-breaching party to any remedies that would apply to the non-material breach
Substantial performance occurs when:
a party substantially complies with an implied or constructive condition, which triggers the obligation of the other party to perform
A party that substantially performs their contractual obligations can:
can recover the contract price minus any amount that it will cost the other party to obtain the promised full performance
A party that has non substantially performed:
generally cannot recover damages based on the contract, but may be able to recover through restitution (restitution requires willful breach)
If a party intentionally furnishes services that are materially different that what was promised:
they cannot recover anything in restitution unless the non-breaching party has accepted or agreed to accept the substitute performance
The general measure of damages in construction contracts is:
the difference between the contract price and the cost of construciton by another builder, PLUS any progress payments made to the breaching builder and compensation for delay in completion of the construction
When a breach results in unfinished constrction:
if the award of damages based on the cost to fix or complete the construction would result in economic waste, thena a court may instead, at its discretion, award damages equal to dimunition in market price caused by the breach.
Economic waste occurs when:
the cost to fix or complete the construction is clearly disproportional to any economic benefit or utility gained as a result
Compensatory damages are:
meant to compensate the non-breaching party for actual economic losses
Expectation damages are:
intended to put the non-breaching party in the same position as if the contract had been performed; they must be calculated with reasonable certainty
Consequential damages:
are damages that arise out of special circumstances unique to the parties to the contract, rather than arising necessarily from the contract itself.
Consequential damages still result directly from the breach, but:
may not be foreseeable to one of the parties unless the special circumstances are known; they must be reasonably foreseeable by the breaching party in order to be recoverable
Unforeseeable consequential damages are not:
recoverable unless the breaching party had some reason to know about the possibility of these unforeseeable consequential damages
Damages are considered foreseeable and thus consequential if:
they were the natural and probable consequences of breach, or if they were “in the contemplation of the parties at the time the contract was made, or they were otherwise foreseeable
There must be a causal link between the consequential damages and:
the breach for damages to be recoverable