Misc Flashcards
(118 cards)
Backlog
Remaining fee yet to be billed
Addenda
Change order in bidding phase
Change order
Changes that effect the contract
Construction change directive
Change order but without established agreement, can result in arbitration later
Used when people can’t agree but project needs to keep going
AIA G701
Standard change order form
If a design change is requested onsite, how should it be handled?
The gc should submit the request through an addenda, rfi or bulletin
Percent complete
Subject evaluation of how much of the total work is completed
Work in place
Billable time and expenses that have been completed but not yet invoiced
Who pulls a C of O
Owner
Who certifies substantial completion?
Architect
Most frequently cited cause of communication claims by an owner
Lack of procedures to identify conflicts, errors and omissions
Float time
the time between when payment is authorized and received
Things affected by construction type (II-A vs V-A)
Structural spans, max floor area, allowable building height
A101
Owner/contractor
- means and methods
- schedule
- controls safety on job site
B101
Owner/Architect
- design intent
- decision making
- code compliance
A201
General conditions
- sets the context
- defines terminology
Right to stop work
Can leave at a safe and reasonable place (likely due to nonpayment)
Owners can do for any reasons
Right to carry out work
Gives contractors first chance to finish out work before being replaced on work
The work
What the architect produces; design intent
The project
All of the building; furniture, landscape, etc
Instruments of service
Drawings, notes, research
Copy right
Default to architect, owner can obtain if agreed to. Likely in franchise, governments, laboratory
Indemnification
One party is paying damages for another (insurance is an example)
Administrator of the contract
Between the owner and contractor is assumed to be the architect