Misc Flashcards

(118 cards)

1
Q

Backlog

A

Remaining fee yet to be billed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Addenda

A

Change order in bidding phase

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Change order

A

Changes that effect the contract

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

Construction change directive

A

Change order but without established agreement, can result in arbitration later
Used when people can’t agree but project needs to keep going

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

AIA G701

A

Standard change order form

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

If a design change is requested onsite, how should it be handled?

A

The gc should submit the request through an addenda, rfi or bulletin

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Percent complete

A

Subject evaluation of how much of the total work is completed

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

Work in place

A

Billable time and expenses that have been completed but not yet invoiced

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

Who pulls a C of O

A

Owner

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

Who certifies substantial completion?

A

Architect

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Most frequently cited cause of communication claims by an owner

A

Lack of procedures to identify conflicts, errors and omissions

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Float time

A

the time between when payment is authorized and received

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Things affected by construction type (II-A vs V-A)

A

Structural spans, max floor area, allowable building height

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

A101

A

Owner/contractor
- means and methods
- schedule
- controls safety on job site

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

B101

A

Owner/Architect
- design intent
- decision making
- code compliance

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

A201

A

General conditions
- sets the context
- defines terminology

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Right to stop work

A

Can leave at a safe and reasonable place (likely due to nonpayment)
Owners can do for any reasons

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Right to carry out work

A

Gives contractors first chance to finish out work before being replaced on work

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

The work

A

What the architect produces; design intent

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q

The project

A

All of the building; furniture, landscape, etc

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

Instruments of service

A

Drawings, notes, research

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

Copy right

A

Default to architect, owner can obtain if agreed to. Likely in franchise, governments, laboratory

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

Indemnification

A

One party is paying damages for another (insurance is an example)

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

Administrator of the contract

A

Between the owner and contractor is assumed to be the architect

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Right to test the work
Arch right to ask for something to be tested on behalf of the owner
26
Essence of contract
Scope, schedule, budget
27
Application for payment
Contractor applies for the architect to review. Lists trades and percent done
28
Pencil draw
Amount that contractors think they should be paid based on percent complete
29
Retainage
Special escrow account for subcontractors so that there is leverage if they need to come back and do finishing touches
30
Certificate of payment
Approved draw for a percent of work
31
Can material that is bought but not installed be put on a draw for payment
Yes if stored properly
32
Substantial completion
A level of completion that is safely occupiable Architect decides when this is reached
33
When do warranties start
At substantial completion
34
Contractor liability insurance
Covers means and methods but no code compluandrt
35
Owners liability insurance (builders risk insurance)
Covers things during construction immediately while final liability is being determined
36
Performance bond
Insurance for the owner that the contractor will be able to preform their job
37
Subrogation
right held by most insurance carriers to legally pursue a third party that caused an insurance loss to the insured
38
Termination for cause
Any party can use
39
Termination for convenience
Usually reserved for owner
40
SD Budget Techniques
comps, per SF numbers
41
DD Budget Techniques
LF or SF of assemblies (cladding, structure, insulation, etc), easy to make decisions off of and swap things out per unit (hotels)
42
FF&E
Fixtures, Furnishings and Equipment: separate budget item because they can be separated from the building
42
Unit Prices
separated out units in a bid for potential changes
42
Schedule of Values can also be known as
Estimate, sworn statement
42
When reviewing submittals, the architect is responsible for:
1. finishes 2. VOC content 3. Materials
43
Administrative adjustment
Small nonconformity to building/zoning code that reviewers can approve
44
Variance
An approval for a bigger nonconformity, may require formal review
45
Amendment
Change to zoning code
46
By right
The rights given by the zoning code. No non conforming aspects
47
When does an egress path end
When you are 30’ clear from the building, all the way out Keyless in the direction of egress
48
Construction responsibilities outline in the project manual specifications
Standard of workmanship Submittal procedures Quality of materials and products
49
What does an architect need to review during the submittal process for toilet accessories?
Finish
50
Steps needed during an architects project close out
Store project related documents Internally share project information Maintain project contact file
51
Project delivery method for risk management and high quality
Design build (CMa also but has more contracts)
52
Code things that affect max allowable area and height
Occupancy class Fire protection Construction type
53
If a material is changed drastically during construction but agreed upon by contractor and owner, what should the architect do?
Issue add services to document the change
54
A project has an 18mo delay, first thing arch should do upon restarting…
Preform a code review
55
Body that provides guidance to conflict with AHJs
ICC
56
Most common procurement method for design-build
Best value
57
Performance standard
Describes the ways that materials or assemblies can be tested to determine a relative level of performance. ASTM and UL are performance standards
58
Slump test
Used to measure the consistency of concrete before it sets. Checks the workability and determines if it’s a properly mixed batch
59
Benefit of asking for bid alternates with a contractor
Give contractors some wiggle room if the design or other changes should arise during construction
60
What does the architects review of shop drawings check for?
Conformity to design intent
61
What assembly group is a daycare within a place of worship?
A-3 because it falls under the worship category Group E otherwise
62
What is a good first step in the programming process for a renovation of an existing laboratory?
Benchmarking tours
63
Contractor responsibilities to review at a pre construction conference
Schedule of values Construction schedule Insurance bonds and permits
64
ADA counter height max for bathroom
34”
65
Good cost estimating technique for design development
Assemblies technique (Calculating sf of assemblies and multiplying by assembly cost)
66
Order of magnitude cost estimating
67
Unit price cost estimating
determining a cost per unit, like cost per hospital bed or apt unit (can be done based on comps or historical data)
68
Criteria design phase
Period where performance/sustainability goals are outlined for the project, pre DD
69
Architects must assist the owner in negations with prospective contractors T/F
True
70
Good project delivery method for an owner interested in minimizing their involvement
Design Build
71
Good project delivery method for complex and tight schedule project
Construction Manager
72
Tool to motivate a contractor to meet a strict deadline
Liquidated damages provision - a predetermined amount of money to be paid as damages for failure to perform under contract
73
Good schedule type for short duration projects with few tasks
Milestone chart Good for fees under $35,000
74
Which governing body handles ADA violations?
department of justice
75
Architect's Responsibilities prior to project completion
review contractors final change order review contractor's final application for payment final inspection
76
How is the critical path determined in a critical path schedule
the route through that is longest
77
In a standard agreement, how long does a contractor have to notify an architect of schedule affecting on site discoveries
14 days
78
Construction Manager as Constructor (CMc)
A CMc advises on constructability and cost estimates during the design of a project, and then shifts to the responsibilities of building according to the contract.
79
Construction Manager as Advisor (CM-Advisor)
A CM-Advisor provides advice on constructability and cost estimation but does not construct buildings.
80
Construction Manager at Risk (CMAR)
CMAR is a delivery method where the construction manager (CM) commits to complete the project within a guaranteed maximum price (GMP), which is based on the construction documents and specifications.
81
Construction Manager as Agent (CMa)
A CMa is brought on board early during a project to advise the owner on constructability aspects, and can stay further into the project to coordinate construction for a fixed price.
82
What is a good project delivery method for an architect to act as a constructability reviewer?
CMc
83
Project phases that lend themselves to hourly billing
SD and CA
84
Project phases that lend themselves to fixed fee billing
DD and CD
85
What does contractor contingency cover
Errors in contractor pricing Costs related to dispute resolution Contractor errors during construction
86
When to use a narrative meeting report?
SD, DD, and CD
87
When to use an action item report
CA
88
What do specifications do?
communicate the type and quality of building components and systems.
89
Information that should always be included in a change order
net change cost to date the amount the specified change increases/decreases the project sum new date of substantial completion contract sum prior to change order
90
A typical project manual consists of
Bidding requirements Contract forms Contract conditions Specifications
91
A201
general conditions of the contract
92
A133
agreement between owner and construction manager
93
Who is responsible for the cost of the revisions that do not match the architect's final design?
The contractor
94
What type of meeting is best held face to face
project kick off
95
who pays sales tax during construction
the contractor
96
who pays for utilities during construction?
the contractor
97
who pays for the building permit
the contractor
98
who renders judgement on variances, exceptions and zoning ordinances
Zoning board of appeals
98
how to list a budget item that hasn't been decided upon yet
Allowance
99
what constitutes that start of construction?
when the owner issues a notice to proceed
100
In design-bid-build, who legally issues to CDs for bidding?
the owner
101
Initial rate of return =
= annual savings / investment
102
what are some responsibilities of HR
legal compliance training and prof dev retention programs onboarding
103
Stipulated sum contract
the bid number doesn't change, profit/loss is taken on by the contractor
104
best way for contractors to reduce risk when committing to a GMP
include the highest possible contingency
105
Percent used to determine contingency period based off design time
10% of design time
106
things that need to take place before final payment is made to the contractor
Architect final inspection Final change order review Contractor submission of required affidavits
107
items to be attached to a certificate of substantial completion
Punch LIst Date of Substantial completion Owner/contractor responsibilities for insurance Completion date for punch list items
108
Ways to make a change to a project after CDs
A written amendment to the contract signed by both parties A change order A construction change directive A written order for a minor change in the work issued by the architect
109
What body determines accessibility requirements for multifamily housing
Fair Housing Act
110
Bid Bond
a bond to guarantee a contractor will enter into the contract with the owner if they are the winning bidder
111
Surety
money given to support an undertaking that someone will perform a duty Bond that a contractor will construct the project
112
Who is responsible for recording field changes
the contractor
113
Contractors must hire engineers to do what
shoring and bracing
114