determine if this statement is true or false. all lifts reqire some type of lift plan.
- true
- false
page 2
- true
page 2
determine if this statement is true or false. all lift plans require an engineering staff and site drawing.
- ture
- false
- false
page 2
which of the following would be included in a detailed lift plan:
1. size, shape, weight of the load
2. size, type, set-up of crane
3. ste-by-step movements of cranes
4. all of the above
4. all of the above
(1. size, shape, weight of the load
2. size, type, set-up of crane
3. ste-by-step movements of cranes)
page 2
Determine If this statement is true or false. A documented pre-lift plan will state the names of the engineers and supervisors who have worked to prepare the plan.
- true
- false
- true
page 2
Determine if this statement is true or false. A documented pre-lift plan will state the names of the operator(s) and the riggers who will rig the load and perform the lift.
- true
- false
- true
page 2
Determine if this statement Is true or false. As crane signaling is only a basic function and the signal-person knows where the loads will be positioned, training or
testing of the signal-person should not be required.
- true
- false
- false
page 3
When using hand signals to direct a crane operator, an extended arm with the thumb vertical and the fingers opening and closing into a fist indicates:
1. lower load
2. raise boom and lower load
3. raise the load line
4. extend boom
- raise boom and lower load
page 4
Two closed fists with both thumbs pointing toward each other is the signal for:
1. retract hydraulic boom
2. lower jib
3. lower load slowly
4. secure load in position
- retract hydraulic boom
page 4
Determine if this statement is true or false. A crane component made by a crane company can be used on any other crane made by that company.
1. true
2. false
- false
page 6
Which type of crane would be best to use where a tight turning radius is required?
1. all-terrain
2. crawler crane
3. carrier-mounted
4. ringer crane
- crawler crane
page 9
To prevent damage, what type of sling should be used to lift a lattice boom?
1. wire rope slings
2. chain slings
3. metal mesh slings
4. synthetic web slings
- synthetic web slings
page 17
When Is the proper time to attach the counterweight to the crane?
1. before load Is lifted
2. prior to Installation of the complete boom
3. after installation of boom
4. only if load weight exceeds crane weight
- prior to Installation of the complete boom
page 18
In order for a crane to lift its own counterweight for loading or off-loading, which of the following criteria should be met to ensure maximum safety?
1. must be on firm level ground
2. gantry must be fully extended
3. four part load line must be used
4. all of the above
- all of the above
page 18
When assembling lattice boom sections, which set of pins are installed first?
1. left side
2. right side
3. both lower
4. both upper
- both upper
page 20
When installing the boom pins, the pin should be pointing:
- out away from boom center
- in toward boom center
- out away from boom center
page 22
When dismantllng a lattice boom, which boom pins should be removed first?
- □ left side
- right side
- both lower
- both upper
- both lower
page 23
Determine If this statement is true or false. It is safe to climb under a boom to knock out the boom pins if the crane has tension on the pendant lines.
- true
- false
- false
page 24
Which position should the gantry of a crane be In when lifting a load?
1. highest position
2. third position
3. mid position
4. lowest position
- highest position
page 25
Jib forestay and backstay pendant lines should be:
1. of equal length, or the forestay pendant lines should be longer
2. of equal length, or the backstay pendant lines should be longer
- of equal length, or the backstay pendant lines should be longer
page 27
Determine If this statement is true or false. Jib capacity “increases” as the angle to the ground decreases.
1. true
2. false
- false
page 28
To avoid torsional loading, the boom tip sheaves should be reeved:
1. non-symmetrical
2. symmetrlcal
3. with an even number of line parts
4. with an uneven number of line parts
- symmetrlcal
page 29, 30
Which of these conditions could be dangerous when operating a crane around a newly constructed building?
1. height of structure
2. uncompacted soil
3. protected pedways
4. compacted soil
- uncompacted soil
page 33
Whenhoistingonoutriggerswithapermitted360degree swing, which position is the most hazardous in most conditions?
1. over front
2. over rear
3. over side
4. over corner
- over corner
page 35,36
Determine if this statement is true or false. The ground pressure under outriggers is higher than it Is under a crawler track because of a smaller bearing surface.
1. true
2. false
- true