Module 6: Short-term and Long-term decision making Flashcards

(94 cards)

1
Q

The role of _______ and ________ information is critical to the ________-________ process

A

relevant; reliable; decision-making;

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
2
Q

Decision making always involves a choice between __________ _______ of ______

A

alternative courses; action;

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
3
Q

Steps in the decision-making process:

1) Define the _________
2) Identify ______-_______ ________ (goals and objectives)
3) Develop __________ _________/____________ which might contribute towards achieving goals and objectives
4) C______ and ________ relevant ____ about each __________
5) S_____ an __________ and _____ the __________ outcome

6) Implement the decision

A

problem;
decision-making criteria;
alternative solutions/opportunities;
Collect; analyse; data; alternative;
Select; alternative; state; expected;

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
4
Q

In a l_______ f______ situation, c___________ will be maximised by earning the _______ _________ __________ per unit of ________ ______

A

limiting factor; contribution; biggest possible contribution; limiting factor;

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
5
Q

Possible limiting factors include:
- S____
- L_____
- M_______
- M__________ c_______

A

Sales;
Labour;
Materials;
Manufacturing capacity;

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
6
Q

Colour makes two products, the Red and the Blue. Unit variable costs are as follows:
Direct materials (Red) = $1
Direct materials (Blue) = $3
Direct labour ($3/hr)(Red) = $6
Direct labour ($3/hr)(Blue) = $3
Variable Overhead (Red) = $1
Variable Overhead (Blue) = $1
The sales price per unit is $14 per Red and $11 for Blue. During July 20X2 the available direct labour is limited to 8000 hrs. Sales demand in July is expected to be 3000 units for Reds and 5000 units for Blues
Determine the profit-maximising production mix, assuming that monthly fixed costs are $20,000 and that opening inventories of finished goods and work in progress are nil.

A

Units (Blues) = 5000
Units (Reds) = 1500
Profit = $9000

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
7
Q

Jam Co. makes two products, the K and the L. The K sells for $50 per unit, the L for $70 per unit. The variable cost per unit of the K is $35, that of the L is $40. Each unit of K uses 2kg of raw material. Each unit of L uses 3kg of raw material.

In the forthcoming period the availability of raw material is limited to 2000kg. Jam Co is contracted to supply 500 units of K. Maximum demand for the L is 250 units. Demand for the K is unlimited.

What is the profit-maximising product mix?

A

625 units K
250 units L

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
8
Q

The ‘make’ option should give management more _______ ________ over the _____

A

direct control; work;

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
9
Q

The ‘buy’ option often has the benefit that the ________ organisation has a _________ ______ and _________ in the _____

A

external; specialist skill; expertise; work;

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
10
Q

In conducting the ‘make or buy’ decision, the organisation will need to _________ ____________ in both _________ and _______ costs

A

consider differences; variable; fixed;

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
11
Q

Complete Make or Buy worked example on page 252 of textbook

A

see textbook

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
12
Q

Outsourcing is the use of ________ _________ as a source of __________ ________, ____________ or ____________.

This is also known as ________ ___________ or ___-___________.

A

external suppliers; finished products, components; services;

contract manufacturing; sub-contracting;

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
13
Q

Frequently an outsourcing decision is made on the grounds that __________ ________ can offer _________ __________ and __________.

A

specialist contractors; superior quality; efficiency;

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
14
Q

Contracting out ______ ________ and ___________ ______ that can then be invested in core activities such as _______ __________

A

frees capital; management time; market research;

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
15
Q

Contractors generally have the _________ and ___________ to start production very quickly to meet sudden _____________ in ________.

A

capacity; flexibility; variations; demand;

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
16
Q

In _____________ and __________ functions, organisations are increasingly likely to use specialist companies

A

administrative; support;

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
17
Q

Decisions such as the following are common:

  • Whether the _______ and _____________ of a ____ ___________ ________ should be entrusted to in-house data processing staff or whether an external software house should be hired to do the work
  • Whether ____________ and ________ of certain items of equipment should be dealt with by in-house engineers, or whether a maintenance contract should be entered into with a specialist organisation
A

design; development; new computer system;

maintenance; repairs;

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
18
Q

Advantages of outsourcing:

  • It ______ ___ ______ of existing staff
  • It allows the company to _____ ___________ of ________ ___________ and ____________
  • It may be _______, once time savings and opportunity costs are taken into account
A

frees up time;
take advantage; specialist expertise; equipment;
cheaper;

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
19
Q

Disadvantages of outsourcing:

  • Without ___________ there is no guarantee that the service will be __________
  • Contracting out may be ___________
  • Organisation misses out on ______ ___________ opportunities
  • Risk that __________ ____ will get into the wrong hands
  • There may be ________ considerations
A

monitoring; performed;
expensive;
skill development;
sensitive data;
ethical;

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
20
Q
  • To minimise risks associated with outsourcing, organisations can enter into ____-___ ________ with their suppliers that specify ____, ________ and ________ ________
A

long-run contracts; costs, quality; delivery schedules;

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
21
Q

A company manufactures and sells a single product. The variable cost of the product is $2.50 per unit and all production each month is sold at a price of $3.70 per unit. A potential new customer has offered to buy 6000 units per month at a price of $2.95 per unit. The company has sufficient spare capacity to produce this quantity. If the new business is accepted, sales to existing customers are expected to fall by 2 units for every 15 units sold to the new customer.

What would be the overall increase in monthly profit which would result from accepting the new business?

A

$1740

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
22
Q

Cost-volume-profit (CVP) analysis/break-even analysis is the study of the ________________ between _____, _______ and ______ at various levels of activity

A

interrelationships; cost; volume; profit;

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
23
Q

The break-even point is the ________ _______ at which there is neither _______ nor ____

A

activity level; profit; loss;

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
24
Q

The Safety Margin is the amount by which ______ ______ can fall below ____________ _____, without a loss being incurred

A

actual sales; anticipated sales;

How well did you know this?
1
Not at all
2
3
4
5
Perfectly
25
Breakeven point
Total fixed costs / Contribution per unit Contribution required to breakeven / Contribution per unit
26
Expected sales = 10,000 units at $8 = $80,000 Variable cost = $5 per unit Fixed costs = $21,000 Compute the break-even point, and the C/S ratio
$56,000
27
Contribution to Sales (C/S) ratio
Contribution required to break even / C-S ratio Fixed Costs / C-S ratio = Breakeven point in terms of sales revenue
28
The Contribution to Sales (C/S) ratio is sometimes also called a _____/_______ or _ / _ ratio
Profit/Volume; P/V;
29
The C/S ratio (or P/V ratio) is a measure of how much ____________ is earned from each $1 of _______
contribution; sales;
30
Assume the C/S ratio of product W is 20%. IB, the manufacturer of product W, wishes to make a contribution of $50,000 toward fixed costs. How many units of product W must be sold if the selling price is $10 per unit?
25,000 units
31
A company manufactures a single product with a variable cost of $44. The contribution to sales ratio is 45%. Monthly fixed costs are $396,000. What is the break-even point in units?
11,000 units
32
Mal de Mer makes and sells a product which has a variable cost of $30 and which sells for $40. Budgeted fixed costs are $70,000 and budgeted sales are 8000 units. Calculate the break-even point and the safety margin.
Break-even point = 7000 units Safety margin = 1000 units
33
S = V + F S = _____-____ _____ _________ V = ______ ________ ______ F = _______ ________ ______
break-even sales revenue; total variable costs; total fixed costs;
34
S - V = F That is, _____ __________ = ______ ______
Total contribution = Fixed costs
35
Butterfingers makes a product which has a variable cost of $7 per unit. If fixed costs are $63,000 per annum, calculate the selling price per unit if the company wishes to break even with a sales volume of 12,000 units.
$12.25 per unit
36
The target profit is achieved when _ = _ + _ + _ Where _ = required _____
S = V + F + P; P; profit;
37
S - V = F + P which also means total ____________ required = F + P
contribution;
38
Riding Breeches makes and sells a single product, for which variable costs are as follows: Direct materials = $10 Direct labour = $8 Variable Production Overhead = $6 and so: Total Variable Costs = $24 The sales price is $30 per unit, and fixed costs per annum are $68,000. The company wishes to make a profit of $16,000 per annum. Determine the sales required to achieve this profit?
14,000 units or $420,000 in revenue
39
Seven League Boots wishes to sell 14,000 units of its product, which has a variable cost of $15 to make and sell. Fixed costs are $119,000 and the required profit is $70,000. What sales price per unit is required to achieve this target profit?
$28.50;
40
Stomer cakes bake and sell a single type of cake. The variable cost of production is 15c and the current sales price is 25c. Fixed costs are $2600/month, and the annual profit for the company at current sales volume is $36,000. The volume of sales demand is constant throughout the year. The sales manager wishes to raise the sales price to 29c per cake, but considers that a price rise will result in some loss of sales. Ascertain the minimum volume of sales required each month to raise the price to 29c?
40,000 cakes per month
41
Close Brickett makes a product which has a variable production cost of $8 and a variable sales cost of $2 per unit. Fixed costs are $40,000 per annum, the sales price per unit is $18, and the current volume of output and sales is 6,000 units. The company is considering hiring an improved machine for production. Annual hire costs would be $10,000 and it is expected that the variable cost of production would fall to $6 per unit. (a) Determine the number of units that must be produced and sold to achieve the same profit as is currently earned, if the machine is hired.
5800 units;
42
Close Brickett makes a product which has a variable production cost of $8 and a variable sales cost of $2 per unit. Fixed costs are $40,000 per annum, the sales price per unit is $18, and the current volume of output and sales is 6,000 units. The company is considering hiring an improved machine for production. Annual hire costs would be $10,000 and it is expected that the variable cost of production would fall to $6 per unit. (b) Calculate the annual profit with the machine if output and sales remain at 6,000 units per annum
$10,000;
43
High Ladders has developed a new product which is about to be launched on to the market. The variable cost of selling the product is $12 per unit. The marketing department has estimated that at a sales price of $20, annual demand would be 10,000 units. However, if the sales price is set above $20, sales demand would fall by 500 units for each $0.50 increase above $20. Similarly, if the price is set below $20, demand would increase by 500 units for each $0.50 stepped reduction in price below $20. Determine the price which would maximise High Ladder's profit in the next year.
The total contribution would be maximised, and therefore profit maximised, at a sales price of $21 per unit, and sales demand of 9000 units.
44
Betty Battle manufactures a product which has a selling price of $20 and a variable cost of $10 per unit. The company incurs annual fixed costs of $29,000. Annual sales demand is 9,000 units. New production methods are under consideration, which would cause a $1000 increase in fixed costs and a reduction in variable cost to $9 per unit. The new production methods would result in a superior product and would enable sales to be increased to 9,750 units per annum at a price of $21 each. If the change in production methods were to take place, the break-even output level would be how much higher or lower than the current output level?
400 units lower;
45
A breakeven chart has the following axes: - A ___________ axis showing the ______/______ (in value or units) - A ________ axis showing _ for ______ __________ and _____
horizonal; sales/output; vertical; $; sales revenues; costs;
46
The following lines are drawn on the breakeven chart: - The _______ line - The ______ ______ line - The _______ _____ line
sales; fixed costs; total costs;
47
The sales line: - Starts at the _______ - Ends at the point signifying ________ ______
origin; expected sales;
48
The fixed costs line: - Runs ________ to the __________ axis - Meets the _________ axis at a point which represents total ______ costs
parallel; horizontal; vertical; fixed;
49
The total costs line: - Starts where the ______ costs line meets the ________ axis - Ends at the point which represents ___________ ______ on the horizontal axis and ______ _____ of ___________ ______ on the _______ axis
fixed; vertical; anticipated sales; total costs; anticipated sales; vertical;
50
The budgeted annual output of a factory is 120,000 units. The fixed overheads amount to $40,000 and the variable costs are $0.50 per unit. The sales price is $1 per unit. What is the profit for the period, the breakeven point in units, and the safety margin?
Profit = $20,000 Breakeven point = 80,000 units Safety margin = 40,000 units
51
Breakeven charts are used to: - Plan the _____________ of a company's __________ - Plan the ____________ of a company's ___________ - To give a _______ _______ of the ____________ calculations
production; products; marketing; products; visual display; breakeven;
52
As an alternative to drawing the _____ cost line first, it is possible to start with _________ costs. This is known as a ___________ ______
fixed; variable; contribution chart;
53
One of the advantages of the ___________ chart is that it shows clearly the __________ for __________ ______ of ___________
contribution; contribution; different levels; production;
54
The _____/_______ (_/_) chart is a variation of the breakeven chart which illustrates the relationship of _____ and _______ to _____ and the ______ _____
profit/volume (P/V); costs; profits; sales; safety margin;
55
In a Profit / Volume (P / V) chart: - 'P' is on the _ axis and comprises _____ and ___________ to _____ - 'V' is on the _ axis and comprises either _______ of _____ or ______ of _______ (revenue)
y; profit; contribution; profit; x; volume; sales; value; sales;
56
The _ / _ chart shows clearly the effect on _____ and ___________ point of any changes in _______ price, ________ cost, _____ cost and/or _____ demand
P/V; profit; breakeven; selling; variable; fixed; sales;
57
Limitations of breakeven analysis: - It an only apply to a _______ ________ or ______ of ________ that are produced and sold in a fixed mix. - A break-even chart may be ____-_________ to prepare - It assumes _____ costs are _______ at all levels of output - It assumes that _________ costs are the _____ per unit at all levels of output - It assumes that _______ prices are _______ at all levels of output
single product; group; products; time-consuming; fixed; constant; variable; same; sales; constant;
58
Payback is the ____ ________ for the ____ _______ from a capital investment project to equal the ____ ______ so that the returns from the __________ pay back the initial ______
time required; cash inflows; cash outflows; investment; outlay;
59
Payback is a ____ _______ measure It does not consider ______
cash based; profit;
60
An asset costing $120,000 is to be depreciated over 10 years to a nil residual value. Profits after depreciation for the first five years are as follows: Year 1 = $12,000 Year 2 = $17,000 Year 3 = $28,000 Year 4 = $37,000 Year 5 = $8,000 How long is the payback period to the nearest month, assuming that cash flows occur at an even rate during each year?
3 years 7 months
61
Disadvantages of the payback method: - It ignores the ______ of ____ _____ - It ignores the _____ _______ of ______
timing; cash flows; time value; money;
62
Advantages of the payback method: - Assesses period for which ________ is ____ __ - Focus on _____ ________ can enhance __________ - Investment risk is _________ if payback is ________ - S_______-____ forecasts are likely to be more ________ - The calculation is ______ and _______
capital; tied up; early payback; liquidity; increased; longer; Shorter-term; reliable; quick; simple;
63
The ARR is also called the _______ on _______ _________ (_ _ _ _) method or the ________ on __________ (_ _ _) method
return; capital employed (ROCE); return; investment (ROI);
64
What are the three definitions of ARR? (and what is the one most commonly used in an exam)
ARR = Average annual profit from investment / Average investment; ARR = Estimated total profits / Estimated initial investment; ARR = Estimated average profits / Estimated initial investment;
65
A company has a target accounting rate of return of 20% and is now considering the following project: Capital cost of asset = $80,000 Estimated life = 4 years Estimated profit before depreciation: Year 1 = $20,000 Year 2 = $25,000 Year 3 = $35,000 Year 4 = $25,000 The capital asset is depreciated by 25% of its cost each year, and has no residual value. Assess whether the project should be undertaken.
Project would not be undertaken because its ARR is 6250/40k = 15.625% and so it would fail to yield the target return of 20%
66
Disadvantages of ARR - Based on __________ _______ which are subject to a number of different accounting treatments - It is a ___________ measure rather than an ___________ measure - It takes no account of the ________ of the project - Ignores the _____ _______ of _______
accounting profits; relative; absolute; length; time value; money;
67
Advantages of ARR: - It is _____ and _______ to calculate - It involves a _________ concept of a ___________ _______ - Accounting profits can be easily calculated from __________ _______ - It looks at the entire ______ _____
quick; simple; familiar; percentage return; financial statements; project life;
68
Question 8 P280
a) D b) A c) C
69
In general, risky projects are those which have _________ cash flows, and hence project returns are likely to be _________
future; variable;
70
People may be: - Risk ______ - Risk _______ - Risk _________
averse; neutral; seekers;
71
What is scenario planning used for? - To develop __________ ______ to cope with specific threats or risks - As a technique to predict the ________ _______ ___________ ____________ for the company and to identify appropriate actions
contingency plans; possible future operating environment;
72
Stages of investment decision making: - O_________ of ___________ - P_______ __________ - A_______ and ___________ - M__________ and _______
- Origination; proposals; - Project screening; - Analysis; acceptance; - Monitoring; review;
73
Budget limits or constraints may be imposed ____________ (____ ________ rationing) or ___________ (____ __________ rationing)
internally (soft capital; externally (hard capital;
74
Capital expenditure often involves the outlay of _____ ____ of ______, and expected benefits may take a _________ of _____ to _________
large sums; money; number; years; accrue;
75
The overriding feature of any _________ is that it should be ________ with the ____________ ________ ________ to achieve its _________
proposal; consistent; organisation's overall strategy; objectives;
76
What are the different steps of Analysis and Acceptance? Step 1) Complete and submit standard format financial information as a ______ __________ _________ Step 2) Classify the _______ by ____ Step 3) Carry out _______ _______ of the ________ Step 4) Compare the outcome of the _________ _______ to predetermined acceptance criteria Step 5) Consider the project in the light of the _________ _______ for the _______ and ________ operating periods. Step 6) Make the _________ - _______/_______ Step 7) Monitor the ________ of the ________
formal investment proposal; project; type; financial analysis; project; financial analysis; capital budget; current; future; decision - accept/reject; progress; project;
77
'Invest' or 'don't Invest' decisions on projects may be made at different levels within the organisational hierarchy, depending on three factors: - The _____ of ____________ - Its perceived ___________ - The ______ of ___________ _________
type; investment; riskiness; amount; expenditure required;
78
During the project's progress, _______ _______ should be applied to ensure the following: - C______ _______ does not exceed the amount ___________ - The implementation of the ________ is not _________ - The anticipated benefits are eventually __________
project controls; Capital spending; authorised; project; delayed; obtained;
79
- Many capital projects such as the purchase of replacement assets and marketing investment decisions do not have _______ ___________ _____ and _______. - Some degree of monitoring and control can be exercised by means of a ____-__________ _________ or ______ ______
clearly identifiable costs; benefits; post-completion appraisal; audit review;
80
A post-completion audit (PCA) is an objective _____________ ____________ of the success of a __________ _________ in relation to a ____
independent assessment; capital project; plan;
81
The PCA is a ________-________ technique. It seeks to ________ ________ _______ to be learned from a project
forward-looking; identify general lessons;
82
Advantages of PCA's: - Can ______ ________ to achieve promised benefits from the project - It can _______ ________ and highlight ________ that should be _____________ - Helps improve the discipline and quality of ___________ for future investment decisions - Original estimates may be more realistic if managers aware that they will be __________
motivate managers; improve efficiency; projects; discontinued; forecasting; monitored;
83
Neale and Homes (1990) found that managers see the following advantages to PCA's: - They improve the ________ of _______ _______ - They improve _________ _____________ - They improve _______ and ___________ - They encourage a more _________ approach to new investment project _________ ________ - They help to identify _________ ________ ________
quality; decision making; organisational performance; control; guidance; realistic; decision making; critical success factors;
84
Which projects should be audited? A reasonable guideline might be to audit all projects above a _______ ____, and a random selection of ______ _______
certain size; smaller projects
85
When should projects be audited? Approximately ___ ____ after the ___________ of the _________
one year; completion; project;
86
Who performs a PCA? - Not ____ ____________ - To avoid conflicts of interest, _______ _______ could be used
line management; outside experts;
87
Problems with PCA: - It may not be possible to identify separately the ____ and ________ of any particular project - PCA can be a ______ and ____-_________ exercise - May lead to managers becoming ____-________ and unneccessarily ____-______ - The strategic effects of a capital investment may take ______ to materialise and in fact, it may ______ be ________ to identify or quantify them effectively
costs; benefits; costly; time-consuming; over-cautious; risk-averse; never; possible;
88
Despite the growth in popularity of post-completion audits, bear in mind the possible alternative control processes: - Teams could manage a project from beginning to end, ______ being used before the project is started and ______ ___ ____, rather than at the end of its life. - More _____ could be spent ______ ________ rather than checking __________ projects
control; during its life; time; choosing projects; completed;
89
- Shorter-term forecasts are likely to be more ________ than longer-term forecasts - Risk-averse investors __ ____ wish to _______ risk entirely - Investment risk is ________ when payback is ________ - Early payback improves ________, not _____________
reliable; do not; avoid; higher; longer; liquidity; profitability;
90
- The payback method of investment appraisal uses accounting profits _______ depreciation charges - The ARR method of investment appraisal uses accounting profits ______ depreciation charges
before; after;
91
ARR ________ cash flows, and hence it is deemed __________
ignores; unreliable;
92
Mutually exclusive capital expenditure options may arise as a consequence of ________ __________
capital rationing;
93
Project control is to: - Keep ______ over _____ - Try to ensure that ____________ is not _________ - Try to ensure that the anticipated ________ are __________
control; costs; implementation; delayed; benefits; obtained;
94
The proper authorisation of expenditures is a necessary _________ _______, but this is linked to the aim of keeping costs ______ _______ and ____________ ____________
financial control; under control; avoiding overspending;